HomeMy WebLinkAboutReso 27-24 Approving the Cooperative Agreement with Alameda County Transportation Commission for the Construction Phase of the Green Stormwater Infrastructure Project
Reso. No. 27-24, Item 5.4, Adopted 04/16/2024 Page 1 of 2
RESOLUTION NO. 27 – 24
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING THE COOPERATIVE AGREEMENT WITH ALAMEDA COUNTY
TRANSPORTATION COMMISSION FOR THE CONSTRUCTION PHASE OF THE GREEN
STORMWATER INFRASTRUCTURE PROJECT
WHEREAS, the City completed the preliminary engineering, environmental clearance and
permitting, and final design phase for the Green Stormwater Infrastructure – Iron Horse Trail,
South of Amador Valley Boulevard project, CIP No. ST0121, (City Project) to treat stormwater
runoff from the adjacent neighborhoods prior to discharge into South San Ramon Creek and
Alamo Creek; and
WHEREAS, Alameda County Transportation Commission (Alameda CTC) is the lead
agency implementing the Project Approval and Environmental Document, Plans, Specifications &
Estimate and Right of Way phases of the SR84 Expressway Widening and SR84/I-680
Interchange Improvements project (Alameda CTC Project), including the improvements to meet
stormwater treatment and flow control requirements specified in the San Francisco Bay Regional
Water Quality Control Board (RWQCB) Clean Water Act Permit 401 Certification No.
WDID#2CW435077; and
WHEREAS, the California Department of Transportation (Caltrans) and the RWQCB have
approved off-site stormwater treatment and flow control for the Alameda CTC Project; and
WHEREAS, the City Project has been modified to accommodate the above-referenced
requirements of the Alameda CTC Project, by incorporating certain modifications to increase the
tributary area of impervious surface and incorporate flow control; and
WHEREAS, the City is willing to modify the City Project to assist Alameda CTC in meeting
these requirements, so long as Alameda CTC reimburses the City for the additional costs of both
design and construction; and
WHEREAS, the City and Alameda CTC entered into Alameda CTC Agreement No. A23-
0012, effective March 15, 2023, for the design phase; and
WHEREAS, the City and Alameda CTC now desire to enter into an agreement for the
construction phase, which includes costs associated with the construction contract and
construction management and inspection services, of the City Project, as modified to
accommodate the requirements of the Alameda CTC Project related to stormwater treatment and
flow control, as further described in the Cooperative Agreement, Alameda CTC Agreement No.
A24-0014, attached hereto as Exhibit A.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby approve the Cooperative Agreement with Alameda CTC, attached hereto as Exhibit A to
this Resolution.
DocuSign Envelope ID: 7823305E-34D4-413D-AAE9-4A320D786947
Reso. No. 27-24, Item 5.4, Adopted 04/16/2024 Page 2 of 2
BE IT FURTHER RESOLVED that the City Manager is authorized to execute Exhibit A
and make any necessary, non-substantive changes to Exhibit A to carry out the intent of this
Resolution.
PASSED, APPROVED AND ADOPTED this16th day of April 2024, by the following vote:
AYES: Councilmembers Hu, Josey, McCorriston, Qaadri and Mayor Hernandez
NOES:
ABSENT:
ABSTAIN:
______________________________
Mayor
ATTEST:
_________________________________
City Clerk
DocuSign Envelope ID: 7823305E-34D4-413D-AAE9-4A320D786947
Alameda CTC Agreement No. A24-0014
1
COOPERATIVE AGREEMENT
BETWEEN
ALAMEDA COUNTY TRANSPORTATION COMMISSION
AND
CITY OF DUBLIN
Caltrans Project: SR84 Expressway Widening and SR84/I-680 Interchange Improvements
Dublin Project: Green Stormwater Infrastructure – Iron Horse Trail, South of Amador
Valley Boulevard
This COOPERATIVE AGREEMENT (“Agreement”), dated for reference purposes only as of
April __, 2024, is entered into by and between the City of Dublin (“City”), a municipal corporation,
and Alameda County Transportation Commission (“Alameda CTC”), a joint powers agency. This
Agreement shall become effective on the date the same is fully-executed by both parties (“Effective
Date”).
RECITALS
A.City completed preliminary engineering, environmental clearance and permitting, and is
nearing completion of the final design phase for the Green Stormwater Infrastructure –
Iron Horse Trail, South of Amador Valley Boulevard project (“City Project”) to treat
stormwater runoff from the adjacent neighborhoods prior to discharge into South San
Ramon Creek and Alamo Creek.
B.Alameda CTC is the lead agency implementing for Project Approval and Environmental
Document (PA&ED), Plans, Specifications & Estimate (PS&E) and Right of Way phases
of the SR84 Expressway Widening and SR84/I-680 Interchange Improvements project
(“Alameda CTC Project”), including the improvements to meet stormwater treatment
and flow control requirements specified in the San Francisco Bay Regional Water Quality
Control Board (“RWQCB”) Clean Water Act Permit 401 Certification No.
WDID#2CW435077.
C.The California Department of Transportation (“Caltrans”) and the RWQCB have
approved off-site stormwater treatment and flow control for the Alameda CTC Project.
D.City Project can accommodate the above-referenced requirements of the Alameda CTC
Project, if the City Project incorporates certain modifications to increase the tributary area
of impervious surface and incorporate flow control.
E.City is willing to modify the City Project to assist Alameda CTC in meeting these
requirements, so long as Alameda CTC reimburses City for the additional costs of both
design and construction.
Exhibit ADocuSign Envelope ID: 7823305E-34D4-413D-AAE9-4A320D786947
Alameda CTC Agreement No. A24-0014
2
F. City and Alameda CTC entered into Alameda CTC Agreement No. A23-0012 effective as
of March 15, 2023 for the preliminary engineering, environmental clearance and
permitting, and final design phases for the City Project, as modified to accommodate the
requirements of the Alameda CTC Project related to stormwater treatment and flow
control.
G. City and Alameda CTC now desire to enter into an agreement for the construction phase,
which includes costs associated with the construction contract and construction
management and inspection services, of the City Project, as modified to accommodate the
requirements of the Alameda CTC Project related to stormwater treatment and flow
control,
H. The current construction estimate for the City Project is $2,800,000, which includes
$2,366,700 for construction capital and $433,300 for construction management and
inspection services. The parties agree that Alameda CTC shall be responsible for 75% of
these costs, given the relative complexity and demands of the stormwater treatment and
flow control elements of the Alameda CTC Project as compared to the City Project
without such elements.
NOW, THEREFORE, THE PARTIES DO HEREBY AGREE AS FOLLOWS:
SECTION I
ALAMEDA CTC AGREES:
A. To fund 75% of $2,800,000, or $2,100,000, for the construction capital, construction
management and inspection costs for the City Project, as modified to accommodate the
requirements of the Alameda CTC Project related to stormwater treatment and flow control.
B. To remit payment to City within thirty (30) days of receipt of an invoice from City for
reimbursement of City’s consultant or contractor costs incurred in performing the
construction, construction management and inspection work for the City Project, as modified
to accommodate the requirements of the Alameda CTC Project related to stormwater
treatment and flow control.
C. To review and provide comments on necessary documents produced during the construction
phase, such as requests for information (RFIs), submittals, and potential change orders, to
ensure consistency with the mitigation requirements, and provide comments thereon to City
within fourteen (14) days after receipt thereof.
D. To assist in obtaining the review and approval from Caltrans and RWQCB, as necessary, for
any documents produced during the construction phase that may require review and/or
approval from such agencies.
DocuSign Envelope ID: 7823305E-34D4-413D-AAE9-4A320D786947
Alameda CTC Agreement No. A24-0014
3
E. To enter into an agreement with the City for the long-term maintenance and establish
Alameda CTC funding for the City Project, as modified to accommodate the requirements
of the Alameda CTC Project related to stormwater treatment and flow control. The long-
term maintenance agreement shall include various compliance requirements of the 401
Certification issued by the RWQCB.
SECTION II
CITY AGREES:
A. To oversee and complete construction, construction management and inspection for the City
Project, as modified to accommodate the requirements of the Alameda CTC Project related
to stormwater treatment and flow control.
B. To inform Alameda CTC of progress and key findings as they are developed and seek input
during construction, construction management and inspection.
C. To invoice Alameda CTC for reimbursement of City’s consultant and contractor costs
incurred in performing the construction, construction management and inspection. City shall
include supporting documentation such as invoices from the construction contractor for the
construction work and timesheets for consultant staff performing construction management
and inspection.
D. To respond to comments provided by Alameda CTC, RWQCB, and Caltrans on draft
documents.
F. To enter into a long-term maintenance agreement with Alameda CTC to establish Alameda
CTC funding for the City Project, as modified to accommodate the requirements of the
Alameda CTC Project related to stormwater treatment and flow control. The long-term
maintenance agreement shall include various compliance requirements of the 401
Certification issued by the RWQCB.
E. City shall require the professional consultant(s), subconsultants, contractors and
subcontractors performing the work required hereunder to name Alameda CTC, its
governing body, officers, employees and consultants as additional insureds on the same
terms as City is so named on all insurance required by City for the City Project.
SECTION III
IT IS MUTUALLY AGREED:
A. This Agreement constitutes the entire agreement between the parties regarding the subject
matter hereof and any oral discussions or written or oral agreements with respect thereto
preceding the effective date of this Agreement are superseded hereby, with the exception
DocuSign Envelope ID: 7823305E-34D4-413D-AAE9-4A320D786947
Alameda CTC Agreement No. A24-0014
4
of Alameda CTC Agreement No. A23-0012. No amendment, alteration or variation of the
terms of this Agreement shall be valid unless made in writing and signed by the parties
hereto, and no oral understanding or agreement not incorporated herein shall be binding on
any of the parties hereto.
B. Alameda CTC and the City each render their services under this Agreement as independent
agencies. None of the agents or employees of either shall be deemed agents or employees
of the other.
C. Any notice given under this Agreement shall be in writing and shall be deemed given if
delivered personally or mailed by registered or certified mail or commercial overnight
courier, return receipt or confirmation of delivery requested, to the parties at the following
addresses (or at such other address for a party as shall be specified by like notice):
If to City:
If to Alameda CTC:
Linda Smith, City Manager
City of Dublin
100 Civic Plaza
Dublin, CA 94568
linda.smith@dublin.ca.gov
Tess Lengyel, Executive Director
Alameda County Transportation Commission
1111 Broadway, Suite 800
Oakland, CA 94607
tlengyel@alamedactc.org
[signatures on following page]
DocuSign Envelope ID: 7823305E-34D4-413D-AAE9-4A320D786947
Alameda CTC Agreement No. A24-0014
5
In witness whereof, the parties hereto have executed this Agreement by their duly authorized
officers.
CITY OF DUBLIN ALAMEDA COUNTY
TRANSPORTATION COMMISSION
By: By:
Linda Smith D’Ambrosio Tess Lengyel
City Manager Executive Director
Date: Date:
Approved as to form: Recommended for Approval:
By By:
John Bakker Gary Huisingh
City Attorney Deputy Executive Director of Projects
Reviewed as to Budget/Financial Controls:
By: ______________________________
Patricia Reavey
Deputy Executive Director of Finance and
Administration
Approved as to form and procedure:
By:
Fennemore Wendel
Legal Counsel for Alameda CTC
5597834.2