HomeMy WebLinkAbout5.10 Green Stormwater Infrastructure Project, CIP Nos. ST0121 and ST0517 - Approval of Plans and Specifications and Award of Contract to Suulutaaq, Inc.Agenda Item 5.10 DUBLIN CALIFORNIA STAFF REPORT CITY COUNCIL DATE: .Line 25, 2024 TO: Honorable Mayor and City Councilmembers FROM: Linda Smith, City Manager SU B.ECT: Green Stormwater Infrastructure Project, CIP Nos. ST0121 and ST0517 - Approval of Plans and Specifications and Award of Contract to Suulutaaq, Inc. Prepared by: Laurie Sucgang, Assistant Public Works Director/City Engineer EXECUTIVE SUMMARY: The City Council will consider approving the plans and specifications and awarding a construction contract to Suulutaaq, Inc. for the Green Stormwater Infrastructure Project. This project will install a bioretention basin for stormwater treatment and hydromodification management, including storm drainpipes, inlets, landscaping in the basin, asphalt trail, seating, and interpretive signage. The project will also remove and replace the existing sidewalk with a wider sidewalk along Amador Valley Boulevard, from the Iron Horse Regional Trail intersection and Stagecoach Road, as well as improve curb ramps and median refuge at the trail crossing. STAFF RECOMMENDATION: Adopt the Resolution Approving the Plans and Specifications and Awarding a Contract to Suulutaaq, Inc. for the Green Stormwater Infrastructure Project, CIP Nos. ST0121 and ST0517. FINANCIAL IMPACT: The bid submitted by Suulutaaq, Inc. is $2,501,546. Staff recommends a construction contingency of $250,000 (about 10%) to facilitate change orders for unforeseen construction issues, bringing the total potential construction cost to $2,751,546. Sufficient funds are available in the approved budgets for CIP Nos. ST0121 and ST0517. The bid includes two major components, Base Bid #1 Storm Drain and Bioretention Area, and Base Bid #2 Amador Valley Boulevard Improvements. Costs for Base Bid #1 are covered by CIP No. ST0121 Green Stormwater Infrastructure, which includes funding from a General Fund Designation as well as a reimbursement from Alameda County Transportation Commission (ACTC) in accordance with a cooperative agreement approved by the City Council on April 16, 2024 (Resolution 27-24). Per the agreement, ACTC will reimburse the City for 75% of the Base Bid Page 1 of 4 1 #1 construction costs. Costs for Base Bid #2 are covered by CIP No. ST0517, Citywide Bicycle and Pedestrian Improvements, which includes Transportation Development Act (TDA) Article 3 Pedestrian and Bicycle Project Funding and other transportation funding appropriated in the budget for CIP No. ST0517. DESCRIPTION: The 2022-2027 Capital Improvement Program (CIP) includes Green Stormwater Infrastructure, CIP No. ST0121, and Citywide Bicycle and Pedestrian Improvements, CIP No. ST0517. Green Stormwater Infrastructure, CIP No. ST0121, provides for planning, design, and construction of various citywide projects that will improve water quality and provide other environmental benefits in accordance with the Green Stormwater Infrastructure Plan, which was approved by the City Council on June 18, 2019. One of the projects included in this CIP is the Green Stormwater Infrastructure - Iron Horse Trail, South of Amador Valley Boulevard project (GSI Project) to treat stormwater runoff from the adjacent neighborhoods prior to discharge into South San Ramon Creek and Alamo Creek. The GSI Project is being done in cooperation with Alameda County Transportation Commission (ACTC). ACTC is the lead agency implementing their SR84 Expressway Widening and SR84/I-680 Interchange Improvements project, including the improvements to meet stormwater treatment and flow control requirements specified by the San Francisco Bay Regional Water Quality Control Board (RWQCB). Caltrans and the RWQCB have approved off -site stormwater flow control for the ACTC project. The City's GSI Project has been modified to accommodate the requirements of the ACTC project by incorporating changes to increase the tributary area of impervious surface and incorporate flow control. In exchange for accommodating the ACTC project requirements, the additional project costs will be reimbursed by ACTC. On February 7, 2023, the City Council approved a cooperative agreement with ACTC (Agreement No. A23-0012) for the preliminary engineering, environmental clearance and permitting, and final design. The agreement assigned responsibilities for each agency, including ACTC's responsibility to fund 75% of the costs associated with the first phase of the project. On April 16, 2024, the City Council approved a cooperative agreement with ACTC (Agreement No. A24-0014) for the construction phase of the combined project, which includes construction capital, construction management, and inspection. The agreement assigned responsibilities for each agency, including ACTC's responsibility to fund 75% of the costs for the construction phase of the project, which was estimated at $2,800,000. Staff will return to the City Council with subsequent agreements for the long-term operation and maintenance. Page 2 of 4 2 Citywide Bicycle and Pedestrian Improvements, CIP No. ST0517, provides for planning, design, and construction of various pedestrian and bicycle facilities throughout the City, including sidewalks and improvements related to the Americans with Disabilities Act (ADA). On June 4, 2024, the City Council approved a request to the Metropolitan Transportation Commission for the Allocation of Fiscal Year 2024-25 Transportation Development Act Article 3 (TDA) Pedestrian/Bicycle Project Funding for two projects, one of which is the pedestrian improvements along Amador Valley Boulevard that will be constructed with this project. Additional funding for the pedestrian improvements is provided by various transportation funds allocated in the approved CIP No. ST0517. The GSI Project will install a bioretention basin for stormwater treatment and hydromodification management, including storm drainpipes, inlets, landscaping in the basin, asphalt concrete trail, seating, and interpretive signage. The GSI Project will also remove the existing sidewalk and construct a wider sidewalk along Amador Valley Boulevard, from the Iron Horse Regional Trail intersection to Stagecoach Road, and will improve curb ramps and the median refuge at the trail crossing. Bid Process and Results The City of Dublin issued a bid package for the GSI Project on April 24, 2024. The bid package consisted of two required components, Base Bid #1 Storm Drain and Bioretention Area, and Base Bid #2 Amador Valley Boulevard Improvements. The required components together total 54 base bid items. An Additive Alternate component, consisting of two additive bid items, was also included in the bid package. The two additive -alternate items were for installation of empty conduit and pull boxes along Amador Valley Boulevard for potential future fiber optic communications for City use. Two sealed bids were received on May 30, 2024, with the base bids ranging from $2,501,546.00 to $2,792,997.60, and additive alternate bids ranging from $210,236.00 to $242,104.00. The lowest base bid, which is the total of Base Bid #1 Storm Drain and Bioretention Area and Base Bid #2 Amador Valley Boulevard Improvements, of $2,501,546.00 was submitted by Suulutaaq, Inc. A summary of the bids is provided as Attachment 4. Staff reviewed the bid results, checked references and necessary licenses, and recommends that the City Council award the construction contract to Suulutaaq, Inc. as the lowest responsive and responsible bidder. Staff is not recommending awarding the additive -alternate bid items because the low bid exceeds the engineer's estimate by approximately 13%, there are no near -term plan to install fiber optic lines in this location, and there is no funding currently approved or allocated in the City's operating or capital improvement plan budget for this work. To facilitate the approval of contract change orders and avoid construction delays, it is requested that the City Manager be authorized to approve change orders up to the contingency amount of $250,000. The resolution will authorize this change as it relates to the project. If the construction contract is awarded to Suulutaaq, Inc., Staff expects work to begin in late July 2024 and complete in late 2024. Page 3 of 4 3 Community Workforce Agreement On January 11, 2022, the City Council approved a Community Workforce Agreement (CWA) with the Building and Construction Trades Council of Alameda County and its Affiliated Local Unions. The CWA is applicable to public works projects valued at over $1,000,000, ensures that there are no labor issues related to said projects, and bolsters local efforts to connect residents with careers in the building and construction trades. The CWA includes a Local Hire Goal where 20% of all hours on a project are worked by Local Residents, which are defined as individuals that reside within Alameda County or within a 15-mile radius of City limits. The CWA also requires contractors to hire one new apprentice for the first $1,000,000 of construction costs, and an additional new apprentice for every $5,000,000 construction costs, based on the engineer's estimate. Apprentices must work a minimum of 10% of the total craft's work hours, but the CWA allows that apprentices may be deployed to another project to ensure the minimum number of hours are met. Staff worked with a consultant, Workforce Integrity and Training Solutions, to prepare bid documents and solicit bids for the GSI Project that comply with the provisions of the CWA. The provisions include the requirement that responsive bidders include an executed Agreement to be Bound to and by the CWA, and that all subcontractors of the successful bidder also execute the Agreement to be Bound within 14 days after Notice of Award. California Environmental Oualitv Act (CEOA) This project is exempt under Section 15301 (Class 1, Existing Facilities), Section 15302 (Class 2, Replacement or Reconstruction), Section 15303 (Class 3, New Construction or Conversion of Small Structures), and Section 15304 (Class 4, Minor Alterations to Land). STRATEGIC PLAN INITIATIVE: None. NOTICING REQUIREMENTS/PUBLIC OUTREACH: A courtesy copy of this report was sent to Suulutaaq, Inc. and Alameda County Transportation Commission's Independent Watchdog Committee. The City Council Agenda was posted. ATTACHMENTS: 1) Resolution Approving the Plans and Specifications and Awarding a Contract to Suulutaaq, Inc. for the Green Stormwater Infrastructure Project, CIP Nos. ST0121 and ST0517. 2) CIP Nos. ST0121 and ST0517 3) Location Map 4) Bid Results Page 4 of 4 4 Attachment I RESOLUTION NO. XX - 24 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN APPROVING THE PLANS AND SPECIFICATIONS AND AWARDING A CONTRACT TO SUULUTAAQ, INC. FOR THE GREEN STORMWATER INFRASTRUCTURE PROJECT, CIP NOS. ST0121 AND ST0517 WHEREAS, the design team has completed the plans and specifications for the Green Stormwater Infrastructure Project, CIP Nos. ST0121 and ST0517, (Project), which includes the installation of a bioretention basin for stormwater treatment and hydromodification management, including storm drain pipes, inlets, landscaping in the basin, asphalt trail, seating, interpretive signage, removal and replacement of sidewalk, curb and gutter along Amador Valley Boulevard, curb ramp upgrade and crossing improvements at the intersection of the Iron Horse Regional Trail; and WHEREAS, the City of Dublin did, on May 30, 2024, publicly open, examine, and declare all sealed bids for doing the work described in the approved plans and specifications for the Project, which plans and specifications are hereby expressly referred to for a description of said work and for all particulars relative to the proceedings under the request for bids; and WHEREAS, said bids were submitted to City Staff and Suulutaaq, Inc., was determined to be the lowest, responsive, and responsible bidder for doing said work. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin hereby approves the Plans and Specifications for the Project. BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby award the Contract for the Project to the lowest, responsive, and responsible bidder, Suulutaaq, Inc., at a base bid amount of two -million five -hundred one thousand five -hundred forty-six dollars and zero cents ($2,501,546.00), the particulars of which bids are on file in the Office of the Public Works Director. BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize the City Manager or designee to approve the Project contract change orders based on the appropriated funds designated for the Project up to the contingency amount of two -hundred fifty thousand dollars and zero cents ($250,000.00). BE IT FURTHER RESOLVED that the City Manager or designee is authorized to execute the Construction Agreement for the Project with Suulutaaq, Inc. and make any necessary non - substantive changes to carry out the intent of this Resolution. {Signatures on the following page} Reso. No. XX-24, Item 5.10, Adopted 06/25/2024 Page 1 of 2 5 PASSED, APPROVED AND ADOPTED this 25th day of June 2024, by the following vote: AYES: NOES: ABSENT: ABSTAIN: Mayor ATTEST: City Clerk Reso. No. XX-24, Item 5.10, Adopted 06/25/2024 Page 2 of 2 6 Attachment 2 Number ST0121 GREEN STORMWATER INFRASTRUCTURE Program STREETS PROJECT DESCRIPTION This project provides for the planning, design, and construction of various citywide projects that will improve water quality and provide other environmental benefits in accordance with the Green Stormwater Infrastructure (GSI) Plan, which was approved by the City Council on June 18, 2019. The GSI Plan and associated implementing projects, as well as trash load reduction requirements, are mandated by the Municipal Regional Stormwater Permit (MRP). Projects include: stormwater full trash capture device installation throughout the City, and construction of GSI along the Iron Horse Trail corridor, south of Amador Valley Boulevard. GSI planning and planning for the installation of trash capture devices began in FY2021-22. The installation of the trash capture devices is anticipated in FY2023-24. Construction of GSI along the Iron Horse Trail corridor, south of Amador Valley Boulevard, is anticipated in 2024. This project is funded by a General Fund Reserve set aside for this purpose. The City and Alameda CTC entered into a Cooperative Agreement on February 7, 2023 to partner on the design and environmental permitting phase for a bio-retention and hydromodification management facility along the Iron Horse Trail corridor, south of Amador Valley Boulevard, that satisfies a portion of the City's GSI requirement and Alameda CTC's project, SR84 Expressway Widening and SR84/I-680 Interchange Improvements. Alameda CTC's share of the costs is 75% of the total, which will be reimbursed to the City after expenditure. Both agencies will enter into a subsequent agreement for the construction phase. The "Other" funding is from Alameda County Transportation Commission. ANNUAL OPERATING IMPACT: To be determined. On -going operations and maintenance (O&M) expenditures for installed facilities are required, but may be equal to current maintenance expenditures, particularly for retrofit and replacement projects. For completely new projects, O&M costs are estimated at 1.3% of construction cost for parcel based GSI or regional stormwater controls, and 3.6% of construction costs for green street projects. Alameda CTC will enter into a long- term maintenance agreement with the City for the GSI along the Iron Horse Trail corridor, south of Amador Valley Boulevard, to account for the on -going maintenance costs of the portion of the facility that satisfies their project. MANAGING DEPARTMENT: Public Works 2022-2027 CAPI ROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 BUDGET 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 Salaries & Benefits 9200 Contract Services 9400 Improvements 9500 Miscellaneous $301 $96,039 $611,365 $235,688 $1,433,670 $900,000 $12,000 $96,340 $847,053 $2,333,670 $12,000 7071111111 $301 $2,153,074 $1,135,688 $3,289,063 FUNDING SOURCE PRIOR YEARS 2022-2023 BUDGET 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS General Fund 1101 Designation 9997 Other $301 $2,153,074 $2,153,375 $1,135,688 $1,135,688 TOTAL r $301 $2,153,074 ,135,688 3,289,063 ANNUAL OPERATING IMPACT CO Number ST0517 CITYWIDE BICYCLE AND PEDESTRIAN IMPROVEMENTS Program STREETS PROJECT DESCRIPTION This project includes planning, design, and construction of improvements to various pedestrian and bicycle facilities throughout the City, including pedestrian/bicycle bridges. This project includes design and construction of improvements recommended in the Bicycle and Pedestrian Plan. The project includes an update to the ADA Transition Plan. The plan update will include a review of City buildings, parks, and rights -of -way. The ADA Transition Plan update will be funded by General Fund. It is anticipated that the ADA Transition Plan update will be completed in 2023. An update of the Bicycle and Pedestrian Plan was adopted by City Council on January 10, 2023. ANNUAL OPERATING IMPACT: None MANAGING DEPARTMENT: Public Works 2022-2027 CAPITAL IMPROVEMENT PROGRAM ESTIMATED COSTS PRIOR YEARS 2022-2023 BUDGET 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS 9100 Salaries & Benefits 9200 Contract Services 9400 Improvements 9500 Miscellaneous $66,995 $64,185 $30,160 $30,160 $659,402 $398,948 $222,350 $302,350 $1,636,757 $1,145,899 $390,988 $390,988 $768 $29,190 $9,730 $9,730 $191,5001 $1,583,0501 $3,564,6321 $49,418 $5,388,600 FUNDING SOURCE PRIOR YEARS 2022-2023 BUDGET 2025-2026 2026-2027 FUTURE YEARS 1001 General Fund 2203 Transportation Development Act Measure B Sales Tax - Local Streets 2204 Fund $509,900 $100 Measure B Sales Tax - Bike & 2205 Pedestrian Fund $387,008 $365,992 $105,000 $105,000 $192,683 $17,317 $142,900 $963,000 $210,000 $510,000 $142,900 ca FUNDING SOURCE PRIOR 2022-2023 YEARS BUDGET 2023-2024 2024-2025 2025-2026 2026-2027 FUTURE YEARS TOTALS Measure BB Sales Tax - Local Streets 2214 Fund Measure BB Sales Tax - Bike & $911,600 $280,000 $280,000 $280,000 2215 Pedestrian Fund $219,830 $113,814 $268,228 $348,228 2212 Vehicle Registration Fee $726,000 2217 Measure BB Grants $135,000 $1,751,6001 $950,100 $726,000 $135,000 TOT $2,363,921 $1,638,223 $653,228 $733,228 $5,388,600 ANNUAL OPERATING IMPACT Attachment 3 CITY OF DUBLIN Green Stormwater Infrastructure Project CIP Nos. ST0121 and ST0517 TAMARACK DRIVE • JP SITES o. P P00 e i a"4/ 0/ /°VeuN e� �VARD VICINITY MAP NOT TO SCALE 0 0 cr DOUGHERTY 11 Attachment 4 CITY OF DUBLIN PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION BID SUMMARY Project Name: Green Stormwater Infrastructure Project Project No.: ST0121 Bid Date: May 30, 2024 BID # 1: BASE BID STORM DRAIN AND BIORETENTION AREA Suulutaq, Inc. Buhler Commercial ITEM DESCRIPTION Qty. UNIT Unit Cost Extension Unit Cost Extension 1 Mobilization 1 LS $165,074.00 $165,074.00 $42,951.00 $42,951.00 2 Traffic Control 1 LS $60,940.00 $60,940.00 $34,787.00 $34,787.00 3 Water Pullution Control Work 1 LS $23,761.00 $23,761.00 $12,499.00 $12,499.00 4 Clearing, Grubbing, and Tree Protection 27,000 SF $1.00 $27,000.00 $1.65 $44,550.00 5 Percolation Test Hole Overexcavation 10 CY $227.00 $2,270.00 $1,519.00 $15,190.00 6 Excavation, Grading and Disposal at Bioretention Area 6,280 CY $102.00 $640,560.00 $101.07 $634,719.60* 7 Engineered Fill 600 CY $83.00 $49,800.00 $164.00 $98,400.00 8 Topsoil 650 CY $110.00 $71,500.00 $120.00 $78,000.00 9 Remove Concrete Flatwork (Valley Gutter) 100 SF $32.00 $3,200.00 $293.00 $29,300.00 10 Remove Tree and Root Ball 3 EA $3,565.00 $10,695.00 $7,967.00 $23,901.00 11 Remove Fence and Gate 25 LF $50.00 $1,250.00 $259.00 $6,475.00 12 Concrete Valley Gutter 50 LF $162.00 $8,100.00 $215.00 $10,750.00 13 Remove and Replace Chain Link Fence 25 LF $116.00 $2,900.00 $346.00 $8,650.00 14 12" Corrugated Metal Pipe 26 LF $253.00 $6,578.00 $1,004.00 $26,104.00 15 15" Storm Drain Pipe, RCP 215 LF $146.00 $31,390.00 $376.00 $80,840.00 16 24" Storm Drain Pipe. HDPE 10 LF $617.00 $6,170.00 $1,846.00 $18,460.00 17 30" Storm Drain Pipe, HDPE 535 LF $239.00 $127,865.00 $683.00 $365,405.00 18 Storm Drain Inlet 4 EA $10,106.00 $40,424.00 $14,621.00 $58,484.00 19 Storm Drain Manhole 5 EA $17,942.00 $89,710.00 $19,247.00 $96,235.00 20 Storm Drain Manhole Type III 1 EA $24,256.00 $24,256.00 $27,638.00 $27,638.00 21 Connect to Existing Storm Drain 3 EA $5,252.00 $15,756.00 $5,980.00 $17,940.00 22 Bioretention Area 10,500 SF $24.00 $252,000.00 $17.00 $178,500.00 23 Impermeable Subsurface Liner 1,200 SY $20.00 $24,000.00 $30.00 $36,000.00 24 Planting - Shrubs 414 EA $217.00 $89,838.00 $236.00 $97,704.00 25 Landscaping Maintenance 1 LS $37,463.00 $37,463.00 $33,056.00 $33,056.00 26 Irrigation System 1 LS $46,321.00 $46,321.00 $51,609.00 $51,609.00 12 BASE BID # 1 STORM DRAIN AND BIORETENTION AREA TOTAL: BID # 2: BASE BID AMADOR VALLEY BOULEVARD IMPROVEMENTS 27 Mobilization 28 Traffic Control 29 Water Pullution Control Work 30 Clearing, Grubbing, and Tree Protection 31 Remove Concrete Flatwork 32 Remove Asphalt Flatwork 33 Remove Tree and Root Ball 34 Remove Fence and Gate 35 Remove Sign 36 Adjusting Appurtenances 37 Concrete Sidewalk 38 Concrete Driveway 39 Concrete Pedestrian Ramp 40 Concrete Curb and Gutter 41 Hot Mix Asphalt (3-inch) 42 Class II AB 43 Class II AB Shoulder 44 Remove and Replace Chain Link Fence and Gate 45 Fence (Two -Rail Wood Fence) 46 Removable Bollard 47 Interpretive Sign 48 Remove and Reinstall Trash Receptacle 49 Remove and Install Bench 50 Traffic Loop Detectors -Vehicles 51 Traffic Loop Detectors -Bicycles 52 Pedestrian Push Button 53 White Crosswalk Striping 54 Roadside Sign $1,858,821.00 $2,128,147.60** Suulutaq, Inc. Buhler Commercial 1 LS $66,477.00 $66,477.00 $56,557.00 $56,557.00 1 LS $59,060.00 $59,060.00 $45,673.00 $45,673.00 1 LS $4,542.00 $4,542.00 $10,175.00 $10,175.00 5,500 SF $2.50 $13,750.00 $9.00 $49,500.00 6,000 SF $3.00 $18,000.00 $5.00 $30,000.00 1,000 SF $11.00 $11,000.00 $8.00 $8,000.00 5 EA $9,867.00 $49,335.00 $1,823.00 $9,115.00 265 LF $24.00 $6,360.00 $14.00 $3,710.00 4 EA $145.00 $580.00 $961.00 $3,844.00 6 EA $1,993.00 $11,958.00 $3,152.00 $18,912.00 4,010 SF $17.00 $68,170.00 $15.00 $60,150.00 460 SF $37.00 $17,020.00 $33.00 $15,180.00 185 SF $95.00 $17,575.00 $66.00 $12,210.00 650 LF $138.00 $89,700.00 $57.00 $37,050.00 140 TON $402.00 $56,280.00 $455.00 $63,700.00 240 TON $136.00 $32,640.00 $180.00 $43,200.00 40 TON $240.00 $9,600.00 $427.00 $17,080.00 45 LF $29.00 $1,305.00 $355.00 $15,975.00 300 LF $23.00 $6,900.00 $95.00 $28,500.00 2 EA $3,214.00 $6,428.00 $8,044.00 $16,088.00 1 EA $6,925.00 $6,925.00 $4,027.00 $4,027.00 1 EA $1,757.00 $1,757.00 $4,312.00 $4,312.00 3 EA $4,180.00 $12,540.00 $2,782.00 $8,346.00 1 LS $48,174.00 $48,174.00 $59,619.00 $59,619.00 1 LS $4,227.00 $4,227.00 $12,679.00 $12,679.00 1 EA $11,522.00 $11,522.00 $15,060.00 $15,060.00 300 LF $29.00 $8,700.00 $39.00 $11,700.00 4 EA $550.00 $2,200.00 $1,122.00 $4,488.00 BASE BID # 2 AMADOR VALLEY BOULEVARD IMPROVEMENTS TOTAL: DETERMINATION OF LOW BID BID 1 + BID 2 $642,725.00 $664,850.00 Suulutaq, Inc. Buhler Commercial $ 2,501,546.00 $2,792,997.60** 13 ADDITIVE ALTERNATE A ITEM 55 Pull Boxes 56 Conduits, 6-2" HDPE DESCRIPTION TOTAL ADDITIVE ALTERNATE: APPARENT LOW BIDDER I Suulutaq, Inc. Buhler Commercial Qty. UNIT Unit Cost I Extension 12 EA $3,648.00 $43,776.00 820 LF $203.00 $166,460.00 $210,236.00 * Mathematical error "unit cost extension" ** Mathematical error "summation of bid items" Unit Cost $4,322.00 $232.00 Extension $51, 864.00 $190,240.00 $242,104.00 14