HomeMy WebLinkAbout5.15 Civic Center Rehabilitation Project CIP No. GI0122 – Acceptance of Workr
DUBLIN
CALIFORNIA
STAFF REPORT
CITY COUNCIL
Agenda Item 5.15
9DATE: August 20, 2024
TO: Honorable Mayor and City Councilmembers
FROM: Linda Smith, City Manager
SU B.ECT: Civic Center Rehabilitation Project CIP No. GI0122 - Acceptance of Work
Prepared by: Michael Boitnott, Capital Improvement Program Manager
EXECUTIVE SUMMARY:
The City Council will consider the acceptance of the Civic Center Rehabilitation Project. The
project converted three existing spaces on the second floor of City Hall into six spaces to better
address current staffing and operational needs.
STAFF RECOMMENDATION:
Adopt the Resolution Accepting the Civic Center Rehabilitation Project, CIP No. GI0122.
FINANCIAL IMPACT:
The Civic Center Rehabilitation Project is complete, and the project funding and costs were as
follows:
Project Funding Source
General Fund Designated Reserves
Total Funding
Estimated Expenditures
$2,236,730.00
$2,236,730.00
Construction Contract with Change Orders
Furniture, Fixtures, and Equipment (FF&E)
Contract Services, Design, Salary, and Testing
$331,491.48
$26,000.00
$142,508.52
Total Expenditures $500,000.00
Estimated Project Balance $1,736,730
Upon the City Council's acceptance of the project, the remaining budget will be retained within the
Civic Center Rehabilitation Project CIP No. GI0122 to fund other renovation and rehabilitation
Page 1 of 2
1
projects in the Civic Center.
DESCRIPTION:
On November 7, 2023, the City Council awarded a construction contract in the amount of
$298,702 to C. Overaa & Co. for the Civic Center Rehabilitation Project, CIP No. GI0122. During
construction, change orders were issued which resulted in the final construction contract amount
of $331,491.48.
This project provided for various improvements to the Civic Center, reconfiguring three existing
spaces into six spaces on the second floor of City Hall. The existing file room was divided into two
spaces that can be configured as either offices or smaller meeting rooms. An existing conference
room was reconfigured into an office and a small meeting space. The existing storage room was
converted into a copier and printer alcove.
Staff has determined that the project is complete and recommends that the City Council accept the
project.
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
The City Council Agenda was posted. A courtesy copy of this report was sent to C. Overaa & Co.
ATTACHMENTS:
1) Resolution Accepting the Civic Center Rehabilitation Project, CIP No. GI0122
2) CIP No. GI0122
Page 2 of 2
2
Attachment I
RESOLUTION NO. XX - 24
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
ACCEPTING THE CIVIC CENTER REHABILITATION PROJECT, CIP NO. GI0122
WHEREAS, on November 7, 2023, the City of Dublin entered into a Construction
Contract with C. Overaa & Co. for the Civic Center Rehabilitation Project, with improvements
that converted three existing spaces on the second floor of City Hall into six spaces; and
WHEREAS, said improvements have been completed in accordance with plans and
specifications, and any approved modifications thereof, to the satisfaction of the City Engineer
of the City of Dublin; and
WHEREAS, as a condition of the contract, C. Overaa & Co. is required to warranty the
improvements for a period of one year following the completion of the work and maintain a
maintenance bond in the amount of 10% of the final contract value.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby accept the Civic Center Rehabilitation Project, CIP No. G10122 and authorize Staff to file
a Notice of Completion with Alameda County.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager, or designee, to release the retention, if after 35 days of filing the
Notice of Completion there are no subcontractor claims.
BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby
authorize the City Manager, or designee, to release the maintenance bond at the end of the
one-year warranty period.
PASSED, APPROVED AND ADOPTED this 20th day of August 2024, by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Mayor
ATTEST:
City Clerk
Reso. No. XX-24, Item X.X, Adopted 08/20/2024 Page 1 of 1
3
Attachment 2
Number — GI0122
•
ICIVIC CENTER REHABILITATION Program — GENERAL IMPROVEMENTS
PROJECT DESCRIPTION
This project provides for the planning, design, and construction of various rehabilitation and renovation projects at the Civic Center. Projects may include: renovation
of all restrooms, showers, kitchenettes, and the employee break room; modifications to conference rooms; lighting and ceiling replacement; site improvements to the
parking lot area and surrounding walkways of the Civic Center; plaza and landscaping improvements; building security evaluation and upgrades; repainting; and
Americans with Disabilities Act (ADA) and Code upgrades. Interior repainting in select areas was completed during construction of the Civic Center HVAC and Roof
Replacement project, and minor parking lot and walkway improvements are anticipated to be designed and constructed in conjunction with the Dublin Arts Center
project. This project also includes the partitioning of three spaces into six on the second floor of the Civic Center.
This project is funded by General Fund Reserves. Other potential funding sources for the building security upgrades may include Federal and State public safety grants.
PROJECT TIMELINE: The project is currently in various stages of design or construction.
ANNUAL OPERATING IMPACT: None.
2024-2029 CAPITAL IMPROVEMENT PROGRAM
ESTIMATED COSTS
PRIOR
FUTURE
YEARS 2024-2025 2025-2026 2026-2027 2027-2028 2028-2029 YEARS TOTALS
9100 — Salaries & Benefits
$80,140
$80,140
9200 — Contract Services
$511,590
$100,000
$611,590
9400 — Improvements
9500 — Miscellaneous
$1,425,000
$15,000
$100,000
$5,000
$1,525,000
$20,000
TOTAL
$2 031 730 $205 000
$2 236 730
FUNDING SOURCE
PRIOR
FUTURE
YEARS 2024-2025 2025-2026 2026-2027 2027-2028 2028-2029 YEARS
TOTALS
1101 — General Fund Designated
Reserves
$2,031,730
$205,000
$2,236,730
TOTAL
$2,031,730
$205,000
$2,236,730
4