HomeMy WebLinkAbout5.6 Hexcel Redevelopment (PLPA-2022-00038)Agenda Item 5.6
STAFF REPORT
DUBLIN CITY COUNCIL
CALIFORNIA
DATE:
TO:
FROM:
SU B,JECT:
October 1, 2024
Honorable Mayor and City Councilmembers
Linda Smith, City Manager
Hexcel Redevelopment (PLPA-2022-00038)
Prepared by: Gaspare Annibale, Associate Planner
EXECUTIVE SUMMARY:
On March 19, 2024 and September 17, 2024, the City Council held a public hearing to consider the
Hexcel Redevelopment project, which includes the redevelopment of an 8.81-acre site located at
11711 Dublin Boulevard. The project would demolish the existing 62,175-square-foot former
Hexcel research and development building and construct a new 125,532-square-foot light
industrial building to appeal to advanced manufacturing and life science uses with 217 parking
stalls and related site improvements. Requested approvals include certification of a Final
Environmental Impact Report, a Planned Development Rezone with a Stage 1 and Stage 2
Development Plan, Site Development Review Permit, and Heritage Tree Removal Permit. The City
Council certified the Final Environmental Impact Report, introduced the Planned Development
Zoning Ordinance and adopted a Resolution approving the Site Development Review Permit and
Heritage Tree Removal Permit. The City Council is now being asked to waive the second reading
and adopt the Ordinance approving the Planned Development Rezone for the Hexcel
Redevelopment project.
STAFF RECOMMENDATION:
Waive the reading and adopt the Ordinance Amending the Zoning Map and Approving a
Planned Development Zoning District With a Stage 1 and Stage 2 Development Plan for the Hexcel
Redevelopment project.
FINANCIAL IMPACT:
The cost associated with processing the project application is borne by the Applicant.
Page 1 of 3
1
DESCRIPTION:
Background
Overton Moore Properties is proposing to demolish the existing 62,175-square-foot former Hexcel
research and development building located 11711 Dublin Boulevard and construct a new
125,532-square-foot light industrial building to appeal to advanced manufacturing and life science
uses. Requested approvals include a Planned Development Rezone with a Stage 1 and Stage 2
Development Plan, Site Development Review Permit, and Heritage Tree Removal Permit.
Figure 1. Project Location
The City Council held public hearings to consider the proposed project on March 19, 2024 and on
September 17, 2024. Please refer to Attachments 2 and 3 for a complete discussion of the
proposed project. On September 17, 2024, the City Council adopted Resolution No. 105-24
certifying the Final Environmental Impact Report, waived the first reading and introduced an
Ordinance amending the zoning map and approving the Planned Development Zoning District
with a Stage 1 and Stage 2 Development Plan, and adopted Resolution No. 106-24 approving a Site
Development Review Permit and Heritage Tree Removal Permit.
The City Council is now being asked to waive the second reading and adopt the Ordinance
(Attachment 1) amending the Zoning Map and approving a Planned Development Zoning District
with a Stage 1 and Stage 2 Development Plan.
ENVIRONMENTAL DETERMINATION:
On May 15, 2023, the City issued a Notice of Preparation for an Environmental Impact Report
(EIR) and held a public scoping meeting on May 25, 2023. The City received three letters
regarding the scope of the EIR. Subsequently, a Draft EIR was prepared for the proposed project
and circulated for a 45-day public review period from August 21, 2023, to October 5, 2023. The
City received three comment letters during the public review period. In addition, a fourth letter
was received after the public review period. Responses were prepared for each of the comments
received by the City. The Draft EIR, comments and associated responses, and changes and
clarifications to the Draft EIR constitute the Final EIR. On September 17, 2024, the City Council
Page 2 of 3
2
adopted Resolution No. 105-24 certifying the Final Environmental Impact Report.
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
The City Council Agenda was posted.
ATTACHMENTS:
1) Ordinance Amending the Zoning Map and Approving a Planned Development Zoning District
with Stage 1 and Stage 2 Development Plan for the Hexcel Redevelopment Project
2) City Council Staff Report dated March 19, 2024, without attachments
3) City Council Staff Report dated September 17, 2024, without attachments
Page 3 of 3
3
Attachment I
ORDINANCE NO. XX — 24
AN ORDINANCE OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AMENDING THE ZONING MAP AND APPROVING A PLANNED DEVELOPMENT ZONING
DISTRICT WITH A STAGE 1 AND STAGE 2 DEVELOPMENT PLAN FOR THE HEXCEL
REDEVELOPMENT PROJECT
PLPA 2022-00038
(APNS 941-1560-009-01 AND 941-1560-003-04)
The Dublin City Council does ordain as follows:
SECTION 1. RECITALS
A. The property owner, Overton Moore Properties, proposes to redevelop an 8.81-acre site
located at 11711 Dublin Boulevard. The project would demolish the existing 62,175-square-
foot Hexcel research and development building and construct a new 125,532-square-foot light
industrial building to appeal to advanced manufacturing and life science uses with 217 parking
stalls and related site improvements. Requested approvals include a Planned Development
Rezone Stage 1 and Stage 2 Development Plan, Site Development Review Permit and
Heritage Tree Removal Permit. These planning and implementing actions are collectively
known as the "Hexcel Redevelopment Project" or the "Project."
B. The Project site includes two parcels totaling approximately 8.81 acres located north of the I-
580, south of Dublin Boulevard and residential and commercial uses, east of existing office
buildings, and west of the U.S. Bank Branch, Dublin Heritage Park and Museums and Dublin
Pioneer Cemetery.
C. The Project site has a General Plan and Dublin Village Historic Area Specific Plan land use
designation of Business Park/Industrial.
D. The Project site is subject to zoning, where one half of the site is zoned Planned Development
(Alameda County Ordinance No. 80-60) and the other half is zoned M-1 (Light Industrial).
E. The proposed Project is consistent with the Business Park/Industrial land use designation but
requires a Planned Development Rezone to accommodate the Project.
F. The California Environmental Quality Act (CEQA), together with the CEQA Guidelines and City
of Dublin CEQA Guidelines and Procedures require that certain projects be reviewed for
environmental impacts and that environmental documents be prepared.
G. Pursuant to the requirements of CEQA, the CEQA Guidelines and City of Dublin CEQA
Guidelines and Procedures, the City prepared a Draft Environmental Impact Report (EIR)
dated August 2023, and a Final EIR dated November 2023, for the proposed Project, which
reflects the City's independent judgment and analysis of the potential environmental impacts
of the Project.
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 1 of 8
4
H. The Draft EIR identified potentially significant impacts to air quality, biological resources,
cultural and tribal resources, energy, geology and soils, and hazards and hazardous materials,
most of which can be substantially reduced through mitigation measures.
I. The Draft EIR was circulated for 45 days for public comment from August 21, 2023, to October
5, 2023. Comments received on the Draft EIR were responded to in the Final EIR dated
November 2023. The Draft EIR, comments and associated responses, and changes and
clarifications to the Draft EIR constitute the Final EIR.
J.
Following a properly noticed public hearing on December 12, 2023, the Planning Commission
adopted Resolution No. 23-11, recommending that the City Council certify the Final EIR and
adopt required CEQA Findings, and approve a Planned Development Zoning District with a
Stage 1 and Stage 2 Development Plan, Site Development Review Permit and Heritage Tree
Removal Permit, which Resolution is incorporated herein by reference and available for review
at City Hall during normal business hours.
K. On March 19, 2024, the City Council held a properly noticed public hearing on the Project,
including the Planned Development Rezone Stage 1 and Stage 2 Development Plan, Site
Development Review Permit and Heritage Tree Removal Permit at which time all interested
parties had the opportunity to be heard, and continued the proposed project to a date
uncertain.
L. A Staff Report dated September 17, 2024, and incorporated herein by reference, described
and analyzed the proposed Project, including the Planned Development Rezone Stage 1 and
Stage 2 Development Plan, Site Development Review Permit, Heritage Tree Removal Permit
and Final EIR, for the City Council.
M. On September 17, 2024, the City Council held a properly noticed public hearing on the Project,
including the Planned Development Rezone Stage 1 and Stage 2 Development Plan, Site
Development Review Permit and Heritage Tree Removal Permit at which time all interested
parties had the opportunity to be heard.
N. The City Council considered the Final EIR prepared for the Project, and all above referenced
reports, recommendations, and testimony prior to taking action on the Project.
O. On September 17, 2024, the City Council adopted Resolution No. 105-24 certifying the Final
EIR and adopting CEQA Findings, a Statement of Overriding Considerations and a Mitigation
Monitoring and Reporting Program for the Project.
P. The City Council did hear and use independent judgment and considered all said reports,
recommendations, and testimony herein above set forth.
SECTION 2: FINDINGS
A. Pursuant to Section 8.32.070 of the Dublin Municipal Code (DMC), the City Council finds as
follows.
1. The Hexcel Redevelopment Project ("the Project") PD-Planned Development Zoning
meets the purpose and intent of DMC Chapter 8.32, in that it provides a comprehensive
development plan that will be consistent with the General Plan and Dublin Village Historic
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 2 of 8 5
Area Specific Plan, and protects the integrity and character of the area by creating a
desirable use of land that is sensitive to surrounding land uses by virtue of the layout and
design of the site plan. The Project is planned comprehensively and will follow development
standards tailored to the specific needs of the site. These standards will address issues
such as building setbacks, architecture, landscaping and grading. The proposed building
will blend with the natural features unique to the site through design and planning. The
Applicant proposes an outdoor seating area and sufficient landscaping within new bi-
retention areas and the new parking lot, along the site perimeter and the frontage of the
building facade, which are consistent with the provisions and regulations for development
set forth therein.
2. Development of the Project under the PD-Planned Development Zoning will be harmonious
and compatible with existing and future development in the surrounding area, in that the
proposed Project would redevelop an existing developed site with a light industrial building
catering to advanced manufacturing and life science uses, which is consistent with the
General Plan and Dublin Village Historic Area Specific Plan.
B. Pursuant to DMC Sections 8.120.050 A and B, the City Council finds as follows.
1. The PD-Planned Development Zoning for the Project will be harmonious and compatible
with existing and potential development in the surrounding area, in that the proposed
Project would redevelop an existing developed site with a light industrial building catering
to advanced manufacturing and life science uses and has taken into account adjacent land
uses.
2. The Project site is physically suitable for the type and intensity of the zoning district being
proposed, in that the site is flat with existing access provided from Dublin Boulevard and is
served by existing public utilities. The Project site conditions were documented in the EIR
prepared for the Project, and the environmental impacts that have been identified will be
mitigated to the greatest degree possible. There are no major physical or topographic
constraints and, thus, the site is physically suitable for the type and intensity of uses
proposed through the PD-Planned Development Zoning.
3. The PD-Planned Development Zoning will not adversely affect the health or safety of
persons residing or working in the vicinity, or be detrimental to the public health, safety and
welfare, in that the Project will comply with all applicable development regulations and
standards and will implement all adopted mitigation measures. In order to ensure adequate
emergency vehicle access to all portions of the site, access is provided to the site from
Dublin Boulevard.
4. The PD-Planned Development Zoning is consistent with and in conformance with the
Dublin General Plan and the Dublin Village Historic Area Specific Plan, in that the proposed
light industrial building is consistent with the existing Business Park/Industrial land use
designation for the site, which allows non -retail businesses such as research, limited
manufacturing and distribution activities, and administrative offices. The Project complies
with this designation as it will provide for an attractive facility that appeals to advanced
manufacturing and life science uses that will not generate nuisances related to emissions,
noise, odors, or glare.
C. Pursuant to CEQA, the City Council certified a Final EIR via Resolution No. xx-24 on
September 17, 2024, prior to approving the Project.
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 3 of 8
6
SECTION 3: ZONING MAP AMENDMENT
Pursuant to DMC Chapter 8.32, Title 8 of the City of Dublin Municipal Code, the City of Dublin
Zoning Map is amended to rezone the property described below to a Planned Development
Zoning District and supersedes the previously adopted Planned Development Zoning (Alameda
County Ordinance No. 80-60) and M-1 Zoning (Light Industrial):
8.81 acres located north of the 1-580, south of Dublin Boulevard, east of existing office
buildings, and west of the U.S. Bank Branch, Dublin Heritage Park and Museums and
Dublin Pioneer Cemetery, which includes the following Assessor's Parcel Numbers: 941-
1560-009-01 AND 941-1560-003-04 ("the Property").
A map of the rezoning area is shown below:
SECTION 4. APPROVAL OF STAGE 1 AND 2 DEVELOPMENT PLAN
The regulations for the use, development, improvement, and maintenance of the Property are set
forth in the following Stage 1 and Stage 2 Development Plan for the entire 8.81-acre Project area,
which is hereby approved. Any amendments to the Stage 1/Stage 2 Development Plan shall be
in accordance with DMC Section 8.32.080 or its successors.
Stage 1 and Stage 2 Development Plan
This is a Stage 1 and Stage 2 Development Plan pursuant to DMC Chapter 8.32. This
Development Plan meets all the requirements for both a Stage 1 and Stage 2 Development Plan
and is adopted as part of the PD-Planned Development rezoning for the Hexcel Redevelopment
Project (PLPA-2022-00005).
The Planned Development zoning district and this Stage 1 and Stage 2 Development Plan
provides flexibility to encourage innovative development while ensuring that the goals, policies,
and action programs of the General Plan and provisions of DMC Chapter 8.32 are satisfied.
1. Statement of Uses
Parcel 1
Permitted Uses (as defined by the Zoning Ordinance):
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 4 of 8
7
Industrial — Light (Warehouse and Distribution uses involving heavy truck traffic are not
permitted)
Office — Professional/Administrative
Similar and related uses as determined by the Director of Community Development
Conditional Uses:
None
Accessory Uses:
Uses which are necessarily and customarily associated with, and are appropriate,
incidental, and subordinate to the principal uses as determined by the Director of
Community Development
Parcel 2
No development or uses are permitted on Parcel 2.
2. Stage 1 and Stage 2 Site Plan
The Stage 1 and Stage 2 Site Plan is shown below.
TABULATION
33,866 F.
1�
amyucl Kra
1- Effirt9r
1— I 1 —
T9TAL 9UILL IN9 AREA
125,53 SF.
LNT 9 T TI UNR C
2 ,947 B.F. 29,966 S
u KIM
MEM
SITE PLAN GENERAL NOT.
SITE PLAN GENERAL NO
DUBLIN
BOULEVARD
LP
•
Project
11711
DUBLIN BLVD.
Con•
sultants:
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 5 of 8 8
3. Development Regulations
The following Development Standards apply to Parcel 1 only. No development is permitted
on Parcel 2.
Floor Area Ratio
0.33
Maximum Building
Height:
40 feet
Maximum lot coverage
31
Parking Spaces
Office: Up to 7,500 square feet - 1 per 250
square feet
7,501 to 40,000 square feet - 1 per 300 square
feet
40,001+ square feet - 1 per 350 square feet
Industrial — Light: 1 per 400 square feet of
general purpose area, plus 1 per 1,000 square
feet of warehouse or distribution area
Parking Stall Dimensions
Standards
Per Dublin Municipal Code Chapter 8.76 (Off -
Street Parking and Loading Regulations)
Minimum Setbacks
10' front (along Dublin Boulevard)
10' side (along west and east property lines)
20' rear (along south property line)
Signage
Per Dublin Municipal Code Chapter 8.84 (Sign
Regulations)
4. Phasing Plan. The Project will be built in one phase, first beginning with demolition, and
followed by site preparation/grading, trench and foundation, exterior building construction,
interior building construction and paving/landscaping.
5. General Plan and Specific Plan Consistency. The Project is consistent with the General
Plan and Dublin Village Historic Area Specific Plan land use designation of Business
Park/Industrial, which allows non -retail businesses such as research, limited manufacturing
and distribution activities, and administrative offices. In addition, the proposed Project design
will provide for an attractive building that appeals to advanced manufacturing and life science
uses that will not generate heavy truck traffic and nuisances related to emissions, noise, odors,
or glare and is consistent with the floor area ratio of 0.30 to 0.40 allowed in the Business
Park/Industrial land use designation.
6. Inclusionary Zoning Regulations. The proposed Project is an industrial use type and is not
subject to the Inclusionary Zoning Regulations (DMC Chapter 8.68) for the provision of
affordable housing because the regulations apply only to residential development projects of
20 units or more.
7. Architectural Standards. The Project's architectural style utilizes a historic industrial
adaptive reuse design approach that is industrial in nature and is unique to light industrial,
advanced manufacturing and life science uses.
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 6 of 8 9
The architectural design of the Project shall reflect the following standards:
• Incorporate features such as channel canopies and different wall planes and horizontal
and vertical reveals to break down the building form into more human scale volumes.
• Use varying colors, brick veneer, heights, low slope/flat roof construction, light fixtures,
and landscaping to enhance the building detail at the pedestrian level.
• Colors shall be neutral in nature, while bright/harsh primary colors shall be avoided.
• Lighter building color applications for portions of the facade shall be used to provide
interest.
• Provide outdoor space for tenants, which allows for gathering and socializing, with
landscaping, outdoor seating, enhanced paving treatment, and other features to
provide an appropriate urban scale for the development.
8. Preliminary Landscaping Plan. The conceptual landscape design of the Project shall reflect
the following standards:
• Provide plentiful green space and natural habitat that utilizes a native and climate -
adaptive planting palette to Dublin's Historic Area and is considered moderate or low
water use.
• Provide a generous landscape buffer along the perimeter of the project site to soften
the main street frontage, rear and sides of the building, and reduce the mass of the
building onto adjacent properties.
• As shown on the Preliminary Landscape Plan, preserve existing trees where possible
along the site perimeter to further enhance the landscape buffer and better integrate
the new development into the surrounding community.
• Utilize plants that provide a year-round vegetated landscape with seasonality, color,
and interest for an attractive visual environment.
9. Aerial Photo.
10. Applicable Requirements of Dublin Zoning Ordinance. Except as specifically provided in
this Stage 1 and Stage 2 Development Plan, the use, development, improvement, and
maintenance of the property shall be subject to the regulations of the closest comparable
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 7 of 8 10
zoning district as determined by the Community Development Director and the Dublin Zoning
Ordinance. No development shall occur on this property until a Site Development Review
Permit has been approved.
SECTION 5. SEVERABILITY
The provisions of this Ordinance are severable and if any provision, clause, sentence, word or
part thereof is held illegal, invalid, unconstitutional, or inapplicable to any person or
circumstances, such illegality, invalidity, unconstitutionality, or inapplicability shall not affect or
impair any of the remaining provisions, clauses, sentences, sections, words or parts thereof of
the ordinance or their applicability to other persons or circumstances.
SECTION 6. EFFECTIVE DATE
This Ordinance shall take effect thirty (30) days following its adoption.
SECTION 7. POSTING OF ORDINANCE
The City Clerk of the City of Dublin shall cause this Ordinance to be posted in at least three (3)
public spaces in the City of Dublin in accordance with Section 36933 of the Government Code of
the State of California.
PASSED, APPROVED AND ADOPTED this 1st day of October 2024, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Mayor
ATTEST:
City Clerk
Ord. No. XX-24, Item X.X, Adopted XX/XX/2024 Page 8 of 8
11
Attachment 2
IF
STAFF REPORT
DUBLIN CITY COUNCIL
CALIFORNIA
Agenda Item 6.1
DATE:
TO:
FROM:
SU B,JECT:
March 19, 2024
Honorable Mayor and City Councilmembers
Linda Smith, City Manager
Hexcel Redevelopment (PLPA-2022-00038)
Prepared by: Gaspare Annibale, Associate Planner
EXECUTIVE SUMMARY:
The City Council will consider the Hexcel Redevelopment project, which includes the
redevelopment of an 8.81-acre site located at 11711 Dublin Boulevard. The project would
demolish the existing 62,175-square-foot Hexcel research and development building and
construct a new 125,304-square-foot light industrial building to appeal to advanced
manufacturing and life science uses with 217 parking stalls and related site improvements.
Requested approvals include a Planned Development Rezone with a related Stage 1 and Stage 2
Development Plan, Site Development Review Permit, and Heritage Tree Removal Permit. The City
Council will also consider certification of the Final Environmental Impact Report.
STAFF RECOMMENDATION:
Conduct a public hearing, deliberate, and take the following actions: 1) adopt the Resolution
Certifying an Environmental Impact Report and Adopting Environmental Impact Findings,
Findings Regarding Alternatives, a Statement of Overriding Considerations and a Mitigation
Monitoring and Reporting Program for the Hexcel Redevelopment Project; 2) waive the reading
and INTRODUCE the Ordinance Amending the Zoning Map and Approving a Planned Development
Zoning District with Stage 1 and Stage 2 Development Plan for the Hexcel Redevelopment Project;
and 3) adopt the Resolution Approving a Site Development Review Permit and Heritage Tree
Removal Permit for the Hexcel Redevelopment Project.
FINANCIAL IMPACT:
The cost associated with processing the project application is borne by the Applicant.
Page 1 of 16
12
DESCRIPTION:
Background
Overton Moore Properties is proposing to demolish the existing 62,175-square-foot Hexcel
research and development building located 11711 Dublin Boulevard and construct a new
125,304-square-foot light industrial building to appeal to advanced manufacturing and life science
uses. The project site includes two parcels totaling 8.81 acres and is located in the Dublin Village
Historic Area Specific Plan (Figure 1). Please refer to Table 1 below for surrounding uses. The
project site has a General Plan land use designation of Business Park/Industrial and one half of the
site is zoned Planned Development (Alameda County Ordinance No. 80-60) and the other half is
zoned M-1 (Light Industrial).
Figure 1. Project Location
Table 1. Surrounding Land Uses
Location
Zoning
General Plan Land Use
Current Use of the
Property
North
Single Family
Residential (R-1) &
Commercial Office (C-
0)
Single Family
Residential &
Retail/Office
Single
Family/Briarhill
Cabana Club & Dublin
Office Building
South
I-580
I-580
I-580
East
Retail Commercial (C-
1) & Agriculture (A)
Parks/Public
Recreation
U.S. Bank Branch,
Dublin Heritage Park
and Museums, and
Dublin Pioneer
Cemetery
West
Planned Development
(PD)
Retail/Office
DeSilva Gates Office
Buildings
On July 10, 1980, the Alameda County Board of Supervisors adopted Ordinance No. 80-60, which
rezoned the western half of the project site and the two commercial properties west of the project
site Light Industrial to Planned Development (PD). The PD zoning allows for Commercial Office
Page 2 of 16
13
(C-0) with some uses requiring a conditional use permit, such as a research and development
laboratory. But the PD zoning does not permit the light industrial/warehousing uses being
proposed.
On August 1, 2006, the City Council adopted the Dublin Village Historic Area Specific Plan
(Resolution No. 149-06). The Specific Plan provides guidelines for future development within the
area to be sensitive to its historic past and to preserve and enhance the area's historical, cultural,
and archaeological resources.
Proposed Project
The proposed project would redevelop Parcel 1 of the project site by demolishing the existing
62,175-square-foot Hexcel research and development building and constructing a new 125,304-
square-foot, light industrial, concrete tilt -up building designed to appeal to advanced
manufacturing and life science uses. Parcel 2, which is undeveloped and contains dense riparian
vegetation, mature trees, and a portion of Dublin Creek, is not proposed for development.
The proposed building would include 18,000 square feet of office, 30,000 square feet of light
industrial, and 77,304 square feet of warehouse (accessory to the light industrial). There would be
119,304 square feet on the ground floor and 6,000 square feet of mezzanine office space on the
second floor. The proposed building could accommodate up to four tenants, with each unit
providing office space and loading docks. The project would construct new site improvements
including a new trash enclosure, 217 on -site parking spaces, and associated site, frontage, and
landscape improvements. There are 89 existing trees on Parcel 1, of which 65 trees would be
removed, including one of four Heritage trees. Refer to Figure 2 for the proposed site plan and
Attachment 9 for the Project Plans. Requested approvals include a PD Rezone Stage 1 and Stage 2
Development Plan, Site Development Review Permit and Heritage Tree Removal Permit.
Page 3 of 16
14
Figure 2. Proposed Site Plan
TABULATOR
4
AERIAL MAP
R
N
4
DUBLIN
B L V
u.e.udu.e.0..0 _a_ lila
TOTALI BULDNO AR?B
1R5.304 S. .
II 1
UNITT 1 LNrr B T
33.528 .F.$2�.699 S.F.
Alt 1
1
T 1 T t
R
D
J
A
4'
•L
II II
• t-innnriniirinn 11
HI II IIII II 111110 I H 1 ,I.
29.906 S{F.
I u thrill lino H i u li
25.971 S.F.
al =ME
iliiuiii11111i
MALL SRL FLAB
A
Analysis
Planned Development Rezone
To accommodate the proposed project, the applicant has requested a PD Rezone with a related
Stage 1 and Stage 2 Development Plan. Dublin Municipal Code (DMC) Chapter 8.32 establishes the
intent, purpose and requirements of PD zoning districts. The proposed PD would establish a
detailed Development Plan for the site, including permitted and conditionally permitted uses, the
overall development density and intensity (e.g., floor area ratio, building height, setbacks, etc.),
parking requirements, and design guidelines. "Industrial -Light" and "Office -
Professional/Administrative" uses as defined by the Dublin Zoning Ordinance would be the only
uses allowed by the PD on Parcel 1. Warehouse and Distribution uses involving heavy truck traffic
are not permitted. No development would be allowed on Parcel 2. Table 2 provides an overview of
the proposed development standards for the project. The Ordinance providing the details of the
proposed PD zoning district is included as Attachment 7.
Page 4of16
15
Table 2. Development Standards
Floor Area Ratio
0.33
Maximum Building Height
40 feet
Maximum Lot Coverage
31%
Parking Spaces
Office: Up to 7,500 square feet, 1 per 250
square feet; 7,501 to 40,000 square feet, 1 per
300 square feet
Industrial - Light: 1 per 400 square feet of
general purpose area, plus 1 per 1,000 square
feet of warehouse or distribution area
Parking Stall Dimension Standards
Per Dublin Municipal Code Chapter 8.76 (Off -
Street Parking and Loading Regulations)
Minimum Setbacks
10' front (along Dublin Boulevard)
10' side (along west and east property lines)
20' rear (along south property line)
Signs
Per to Dublin Municipal Code Chapter 8.84
(Sign Regulations)
Site Development Review Permit
The following is a summary of key components of the project associated with the Site
Development Review Permit.
Site Design and Access: The project site would be accessed from two existing driveways on Dublin
Boulevard. The main driveway is located at the intersection of Dublin Boulevard and Hansen Drive
and the secondary driveway is located at the northeastern corner of the project site (east of
Hansen Drive adjacent to the U.S. Bank Branch entrance). Both driveways would provide access to
all parking areas on -site and to the loading docks at the rear of the building. The loading docks
would be screened from public view on Dublin Boulevard by the building and from the I-580 by
new and existing landscaping on the south side of the project site. The project site also provides
access to the adjacent office buildings to the west.
The existing sidewalk along the property frontage would be extended into the project site and
provide direct access to an outdoor seating area at the main building entrance. This would create a
strong relationship between the street and the building and enhance the project's connectivity to
the surrounding area.
Architecture: The project's architectural style utilizes a contemporary design approach with
muted taupe and earth tones to soften the building and allow it to blend more naturally with the
landscape and color schemes commonly used in the vernacular of the late 19th century buildings
in the Dublin Village Historic Area Specific Plan. The exterior employs simple details with clean
lines in keeping with the simple shapes used on the historic buildings and mimicking the historic
wood siding used on adjacent projects. The massing of the building is broken up using reveals,
paint color changes and articulation, allowing the scale to visually appear pedestrian -oriented.
This is further enhanced with pronounced trellis awnings along the windows and contrast color
Page 5 of 16
16
blocking at the roofline.
At the tenant locations and in the mezzanine areas, windows and glazing reflect a stronger vertical
orientation with simple frames. The building would have two-story glazing at the proposed office
spaces on the north, east and northwestern elevations, primarily along Dublin Boulevard,
maximizing natural light into the office and mezzanine spaces and providing distinct office
entrances for multiple tenants. Additionally, the stone monument and lighting standards reflect a
similar design employed in other areas of the Historic Area. Refer to Figure 3 for the proposed
building perspective.
Figure 3. Proposed Building Perspective
Landscaping: The project site would provide approximately 99,106 square feet of new landscape
area, including a new parking lot, site perimeter, building facade, and bio-retention landscaping.
Approximately 14,350 square feet of landscaping would be provided within the parking lot,
15,390 square feet would be provided along the perimeter of the project site, 6,680 square feet
would be incorporated into the walkways and outdoor seating area, and 13,936 square feet
provided within the bio-retention areas at the north, southeastern and western portions of the
project site. The remaining landscape square footage includes existing landscaping that is to
remain. Existing landscaping west of the main driveway and new landscaping east of the main
driveway would provide a landscape buffer along Dublin Boulevard to help soften the project
frontage. Furthermore, along the southern boundary of the project site, all existing landscaping
would remain within Parcel 2, which provides a buffer from the I-580 and helps soften the project
design at the rear of the building.
The landscape plan features a low water usage plant palette, including a variety of drought
tolerant trees, shrubs and ground cover to provide visual interest in texture and color while
conserving natural resources. Native plants are utilized to encourage biodiversity in conjunction
with the existing riparian vegetation and Dublin Creek on Parcel 2. New plant screening that
matches the plant pallet found in the Historic Area is provided in the setback along Dublin
Page 6of16
17
Boulevard to minimize any undesirable visual impacts. Refer to Figure 4 for the proposed plant
pallet.
Figure 4. Proposed Plant Pallet
The landscape edge along the eastern property line provides for new shrubbery and trees to
screen the project from the adjacent properties. The existing landscaping on the adjacent property
to the east would provide a visual separation between the project site and the U.S. Bank Branch,
Dublin Heritage Park and Museums and Pioneer Cemetery. Refer to Figure 5 for the proposed
building perspective view from the Dublin Pioneer Cemetery. A condition of approval has been
provided to ensure this landscaping is protected during grading/ construction activities. Large
shade trees would be provided within the parking lot to provide a cooler environment, and reduce
urban heat island effect. The landscape design preserves the existing Heritage trees on -site and
incorporates them into the site design.
Page 7 of 16
18
Figure 5. Proposed Building Perspective View from Dublin Pioneer Cemetery
There are 89 existing trees on Parcel 1, of which 65 trees are proposed to be removed, including
one of the four Heritage Trees as further discussed below. A total of 85 trees would be planted on
Parcel 1. On Parcel 2, there are 108 trees, including 19 Heritage Trees, all of which would be
preserved.
Heritage Tree Removal Permit
A Heritage Tree Removal Permit is required for any oak, bay, cypress, maple, redwood, buckeye
and sycamore tree with a trunk or main stem 24 inches or greater in diameter measured four feet
six inches above natural grade. There are four Heritage Trees on Parcel 1 and 19 on parcel 2 for a
total of 23 heritage trees. One of the four Heritage Trees on Parcel 1 is proposed to be removed.
That tree is a sycamore tree measuring 28.2 inches in diameter, which conflicts with the location
of the proposed building. The Arborist Report is included as Attachment 10.
CONSISTENCY WITH THE GENERAL PLAN, SPECIFIC PLAN AND ZONING
ORDINANCE:
The proposed project is consistent with the General Plan and Dublin Village Historic Area Specific
Plan. The proposed project would provide space for light industrial uses that would cater to
advanced manufacturing and life science tenants consistent with the Business/Industrial land use
designation. Warehouse and distribution uses that would involve heavy truck traffic are not
permitted. The proposed floor -area ratio (FAR) of 0.33 is within the FAR of 0.30 to 0.40 allowed in
the Business Park/Industrial land use designation.
Page 8 of 16
19
The Dublin Village Specific Plan provides discretion in applying various provisions in the design
guidelines to specific projects. It is not anticipated that each guideline will apply equally to every
project. In some cases, one or more of the guidelines may be relaxed to facilitate compliance with a
more important or appropriate guideline for that project. In reviewing the proposed project, staff
believes the intent and spirit of the design guidelines have been followed and the project respects
its surroundings and honors the heritage and desired character of the area while balancing the
economic development benefits this project would bring to Dublin.
ENVIRONMENTAL DETERMINATION:
Pursuant to the requirements of the California Environmental Quality Act (CEQA), the City
prepared an Environmental Impact Report (EIR) for the proposed project. On May 15, 2023, the
City issued a Notice of Preparation for an EIR and held a public scoping meeting on May 25, 2023.
The City received three letters regarding the scope of the EIR. Subsequently, a Draft EIR was
prepared for the proposed project and circulated for a 45-day public review period from August
21, 2023, to October 5, 2023. The City received three comment letters during the public review
period. In addition, a fourth letter was received after the public review period. Responses have
been prepared for each of the comments received by the City. The Draft EIR, comments and
associated responses, and changes and clarifications to the Draft EIR constitute the Final EIR
(Attachment 2).
The environmental document prepared for the project is a Focused EIR that evaluates potential
impacts of a limited number of environmental issue areas that the City determined to be
significant (CEQA Guidelines Section 15063(c)(3)). After preparation of an Initial Study
(Appendix A of Draft EIR, Attachment 6), the City determined that the proposed project would
have significant or potentially significant impacts in the following topic areas that require further
analysis and are, therefore, discussed in the Draft EIR:
• Air Quality
• Biological Resources
• Cultural Resources*
• Energy
• Geology and Soils
• Hazards and Hazardous Materials
• Tribal Cultural Resources
The Draft EIR concludes that the proposed project would have a significant and unavoidable
impact on Cultural Resources (noted above with *). The remaining topic areas have mitigation
measures that have been prepared to reduce impacts in these areas to a level that is less than
significant.
The information and analysis presented in the Initial Study provides substantial evidence for the
conclusion, for all the topic areas listed below, that: 1) CEQA standards triggering preparation of
further environmental review do not exist for those topics; and 2) impacts under these topics
would result in no impact or be less than significant.
Page 9of16
20
• Aesthetics
• Agricultural and Forestry Resources
• Greenhouse Gas Emissions
• Hydrology and Water Quality
• Land Use and Planning
• Mineral Resources
• Noise
• Population and Housing
• Public Services
• Recreation
• Transportation
• Utilities and Service Systems
• Wildfire
There were no impacts identified for the topic area listed above and, therefore, no mitigation is
required. An overview of all topic areas is provided below.
Aesthetics
There were no potentially significant impacts identified for aesthetics and, therefore, no
mitigation is required.
Agricultural and Forestry Resources
There were no potentially significant impacts identified for agricultural and forestry resources
and, therefore, no mitigation is required.
Air Quality
Demolition activities and construction of the proposed project would involve the use of offroad
equipment, haul trucks, and worker commute trips that would generate short-term criteria air
pollutant emissions. Operation of the proposed project would generate long-term
emissions associated with daily employee vehicle trips, building energy consumption,
reapplication of architectural coatings, use of consumer products, and maintenance/testing of
the fire pump. However, construction -related emissions of the proposed project would not exceed
the thresholds of significance recommended by the Bay Area Air Quality Management District
(BAAQMD). The proposed project would implement BAAQMD's Basic Construction Mitigation
Measures as noted in Mitigation Measure AQ-1 and be subject to BAAQMD Rules and Regulations
for controlling fugitive dust emissions, which would reduce fugitive dust emissions during
demolition and construction. Further, the proposed project would result in a net reduction of
emissions compared to existing conditions and would not exceed BAAQMD thresholds of
significance. The proposed project would not conflict with or obstruct implementation of the
applicable air quality plan, and construction and operation of the proposed project would not
result in a cumulatively considerable net increase of any criteria pollutant for which the region is
non -attainment under an applicable federal or state ambient air quality standard. Therefore, this
impact would be less than significant with mitigation.
Page 10 of 16
21
Biological Resources
The project would involve the removal of approximately 65 trees which could be used by birds
during the nesting season. If a tree containing an active nest were to be removed during
construction, such removal would result in nest destruction and failure. Due to this potential for
loss of nests and due to potential disturbance of nesting birds from noise and vibration during
project construction, the impact to nesting birds would be potentially significant. However,
nesting bird avoidance measures would be implemented as a mitigation measure to protect
nesting birds; therefore, impacts to candidate, sensitive, or special status species would be
reduced to less than significant with mitigation.
Further, the riparian corridor associated with Dublin Creek on Parcel 2 could be used as foraging
habitat for common bats. As such, trees that would be removed as part of the project outside of
riparian areas may provide suitable day or night roosting habitat for bat species. Given the
availability of alternative natural habitat for hibernaculum in the vicinity of the project and based
on planned tree replacement, impacts on the habitat for bats are not expected to be significant.
However, if construction were to remove trees containing bats during the maternity or winter
season, bat mortality could occur, and the impact on common bat species would be potentially
significant. Implementation of roosting bat surveys and avoidance as a mitigation measure would
ensure that impacts to wildlife movement, migration, or nursery sites would be reduced to less
than significant with mitigation.
Cultural Resources
A historical resource evaluation was prepared for the existing Hexcel research and development
building to assess its eligibility for listing in the California Register of Historical Resources (CRHR).
The building was determined to be eligible for listing in the CRHR under Criterion 1 because it is
significant at the national level for its associations within the Man in Space historic context
published by the National Park Service and is, therefore, considered a historical resource for the
purposes of CEQA.
The significance of a historical resource is considered to be "materially impaired" when a
project demolishes or materially alters the physical characteristics that justify the
determination of a historical resources' significance. Because the proposed project would
result in the demolition of the existing Hexcel building, the impact would be significant and
unavoidable.
CEQA requires that all feasible mitigation must be completed even if it does not mitigate project
impacts below a level of significance. Therefore, the following mitigation measures would still be
implemented as part of the project, even though they would not fully offset the loss of the
resource, and the impact would remain significant and unavoidable:
• Historic American Buildings Survey (HABS) Recordation: applicant shall document the
Hexcel Corporation R&D facility prior to demolition consisting of a historical report and
photographs.
• Interpretive Displays: applicant shall install permanent interpretive displays or signage as
prepared by an architectural historian for public exhibition detailing the history and
Page 11 of 16
22
significance of the Hexcel Corporation R&D facility.
Further, based on the existence of archeological resources within and adjacent to the project area,
there is a high probability of encountering historic -period archeological resources during ground
disturbance at the project site, particularly within those portions of the property closest to St.
Raymond's Church and Pioneer Cemetery, and a high probability of identifying Native American
archeological resources, particularly within a 150-meter (493 foot) corridor centered on Dublin
Creek. The possibility of encountering buried archaeological resources in the project area outside
of the High Archeological Probability Area remains a concern as well, and per the mitigation
measures in the Dublin Village Historic Area Specific Plan and associated Initial Study/Mitigated
Negative Declaration, requires mitigation to avoid adverse impact. Therefore, the project would be
required to implement archaeological and tribal monitoring and produce an archaeological testing
plan and treatment and monitoring plan prior to the start of construction. Inadvertent discovery
protocols would also be implemented should precontact or historic -age resources be discovered.
Together these mitigation measures would reduce the potential impact on archeological and
buried resources to less than significant with mitigation.
Energy
The proposed construction activities would increase energy consumption for the duration of
project construction in the form of fossil fuels (e.g., gasoline, diesel fuel). However, the operation
of the proposed project would result in a net reduction in energy consumption, primarily related
to improved building energy standards and eliminating natural gas infrastructure. Energy
consumption associated with the construction and operation of the proposed project would not be
inefficient, wasteful, or unnecessary with the implementation of basic construction emission
control practices per the air quality mitigation measures. Therefore, this impact would be less
than significant with mitigation.
Geology and Soils
The project site is composed of artificial fill to depths ranging from 1.5 - 5 feet, with native Contra
Costa Group sediments below the fill. Most grading and earthmoving activities at the project site
would extend to a maximum depth of two to three feet below the ground surface and, therefore,
would generally be confined to the artificial fill material, which is not paleontologically sensitive.
However, in areas where the artificial fill only extends to 1.5 feet, excavation and grading would
encounter the native Contra Costa Group materials, which are of high paleontological sensitivity.
Furthermore, excavation to a maximum depth of approximately twelve feet would occur at the
proposed on -site stormwater drainage pumps, which would also encounter the paleontologically
sensitive Contra Costa Group materials. Therefore, project -related earthmoving activities could
result in accidental damage to or destruction of unique paleontological resources, and this impact
would be potentially significant. To minimize the potential for destruction of or damage to
previously unknown unique, scientifically important paleontological resources during
earthmoving activities at the project site, the applicant would be required to retain a qualified
archaeologist or paleontologist to provide the necessary information to all construction personnel
regarding the procedure for encountering fossil fuels. Construction work would immediately
cease within 150 feet of the find and a recovery plan would be developed to record and undergo
appropriate curation. Therefore, with the implementation of these mitigation measures
construction -related impacts to unique paleontological resources would be less than significant
Page 12 of 16
23
with mitigation.
Greenhouse Gas Emissions
There were no potentially significant impacts identified for greenhouse gas emissions and,
therefore, no mitigation is required.
Hazards and Hazardous Materials
It has been recommended that a subsurface investigation be completed in the vicinity of the on -
site areas for chemical use, storage, and handling to assess whether a release occurred in the past.
If soil or groundwater has been previously contaminated at levels that exceed regulatory
thresholds, this would represent a significant human health and environmental
hazard because excavation work would be required during construction that could release
these hazardous materials. Furthermore, demolition of the existing building could expose
workers and the environment to hazardous materials such as lead paint and/or asbestos.
Therefore, these construction -related impacts are considered potentially significant and require
mitigation. Prior to earthmoving activities, a Phase II Environmental Site Assessment must be
completed and the building must be sampled for lead paint and/or asbestos. With the
implementation of these mitigation measures, potential construction -related impacts from
accidental exposure to hazardous materials would be less than significant with mitigation.
Hydrology and Water Quality
There were no potentially significant impacts identified for hydrology and water quality and,
therefore, no mitigation is required.
Land Use Planning
There were no potentially significant impacts identified for land use planning and, therefore, no
mitigation is required.
Mineral Resources
There were no potentially significant impacts identified for mineral resources and, therefore, no
mitigation is required.
Noise
There were no potentially significant impacts identified for noise and, therefore, no mitigation is
required.
Population and Housing
There were no potentially significant impacts identified for population and housing and, therefore,
no mitigation is required.
Public Services
There were no potentially significant impacts identified for public services and, therefore, no
mitigation is required.
Recreation
There were no potentially significant impacts identified for recreation and, therefore, no
Page 13 of 16
24
mitigation is required.
Transportation
There were no potentially significant impacts identified for transportation and, therefore, no
mitigation is required.
Tribal Cultural Resources
The proposed project would include excavation of the parking lot to the south of the existing
Hexcel building, which is adjacent to the marked boundary of the Pioneer Cemetery. Marked grave
sites in the cemetery are within five feet of the property line shared with the project site. Historic
documents suggest that the cemetery was larger than the currently marked boundary.
Additionally, there is anecdotal evidence that the cemetery location was first used by the Ohlone
and may also include burials of Native American and Mexican farm laborers who worked for Jose
Maria Amador, interred prior to formal consecration of the cemetery in 1859. It is likely that the
cemetery extends beneath the Hexcel parking lot, and possible that the cemetery includes Native
American human remains. If so, the impact on tribal cultural resources would be potentially
significant during earthmoving and excavation activities. Inadvertent/unanticipated discovery
protocols would be implemented, ensuring tribal cultural resources encountered during
construction would be treated in a culturally appropriate manner in consultation with Tribal
Representatives and, therefore, the impact on tribal cultural resources would be less than
significant with mitigation.
Utilities and Service Systems
There were no potentially significant impacts identified for utilities and service systems and,
therefore, no mitigation is required.
Wildfire
There were no potentially significant impacts identified for wildfire and, therefore, no mitigation
is required.
The City Council resolution certifying the Final Environmental Impact Report is included as
Attachment 1. To approve the project, the City Council must make findings regarding significant
impacts and mitigation measures (Attachment 3), findings concerning infeasibility of alternatives
and potential additional mitigation measures (Attachment 4), and will need to adopt a Statement
of Overriding Considerations (SOC) (Attachment 5) that identifies all environmental impacts that
cannot be mitigated and explains why the benefits of the project outweigh its unavoidable
environmental impacts. The Mitigation Monitoring and Reporting Program is included as
Attachment 6. The SOC is required in order to approve the project, if desired by a majority of the
City Council.
PLANNING COMMISSION REVIEW:
On December 12, 2023, the Planning Commission held a public hearing to consider the proposed
project. Two members of the public addressed the Commission regarding the project. After closing
the public hearing and deliberating, the Planning Commission voted 3-2 to recommend approval
of the Hexcel Redevelopment Project and adopted Resolution No. 23-11 (Attachment 11). In their
Page 14 of 16
25
motion, the Planning Commission recommended that the Applicant consider incorporating more
design elements found in the Dublin Village Historic Area Specific Plan area.
Since the Planning Commission meeting, the Applicant has made the following changes to the
project plans to address the Commission's comments:
• Revised building colors to include muted earth tones to soften the building allowing it to
blend more naturally with the landscape and the color schemes used on buildings in the
Historic Area.
• Modified the windows and glazing to reflect a stronger vertical orientation with simple
frames in keeping with the Historic Area.
• Provided more pronounced trellis awnings along windows.
• Added a contrast color at the top of the building to reduce the massing.
• Integrated stone monumentation within the landscape area near the front of the building,
which is similar to what can be found in the Historic Area.
• Incorporated light standards that reflect a similar design employed in other areas of the
Historic Area.
• Matched the plant pallet found in the Historic Area along the project frontage.
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
Two City -led Community Meetings were held on October 25 and 26, 2023, to provide Dublin
residents with information about the proposed Hexcel Redevelopment project. Staff provided a
presentation that included an overview of the City's development review process and the
proposed project. Questions were asked about the project's impact on infrastructure capacity and
the general contractor that would be used for the project. Comments were also provided regarding
the EIR and project design.
In accordance with State law, a public notice was mailed to all property owners and occupants
within 300 feet of the proposed project to advertise the project and upcoming public hearing. A
public notice was also published in the East Bay Times and posted at several locations throughout
the City. A Planning Application sign was posted on the project site and the project was also
included on the City's Development Projects webpage. A copy of this Staff Report has been
provided to the applicant.
ATTACHMENTS:
1) Attachment 1- Resolution Certifying an Environmental Impact Report and Adopting
Environmental Impact Findings, Findings Regarding Alternatives, a Statement of Overriding
Considerations and a Mitigation Monitoring and Reporting Program for the Hexcel
Redevelopment Project
Page 15 of 16
26
2) Attachment 2 - Exhibit A to the Resolution - Final Environmental Impact Report
3) Attachment 3 - Exhibit B to the Resolution - Findings Concerning Significant Impacts and
Mitigation Measures
4) Attachment 4 - Exhibit C to the Resolution - Findings Concerning Infeasibility of Alternatives
and Potential Additional Mitigation Measures
5) Attachment 5 - Exhibit D to the Resolution - Statement of Overriding Considerations
6) Attachment 6 - Exhibit E to the Resolution - Mitigation Monitoring and Reporting Program
7) Attachment 7 - Ordinance Amending the Zoning Map and Approving a Planned Development
Zoning District with Stage 1 and Stage 2 Development Plan for the Hexcel Redevelopment
Project
8) Attachment 8 - Resolution Approving a Site Development Review Permit and Heritage Tree
Removal Permit for the Hexcel Redevelopment Project
9) Attachment 9 - Exhibit A to the Resolution - Hexcel Redevelopment Project Plans
10) Attachment 10 - Arborist Report
11) Attachment 11 - Planning Commission Resolution No. 23-11
Page 16 of 16
27
Attachment 3
IP
�ls
STAFF REPORT
DUBLIN CITY COUNCIL
CALIFORNIA
Agenda Item 6.1
DATE:
TO:
FROM:
SUBJECT:
September 17, 2024
Honorable Mayor and City Councilmembers
Linda Smith, City Manager
Hexcel Redevelopment (PLPA-2022-00038)
Prepared by.• Gaspare Annibale, Associate Planner
EXECUTIVE SUMMARY:
The City Council will consider the Hexcel Redevelopment Project, which redevelops an 8.81-acre
site located at 11711 Dublin Boulevard. The project would demolish the existing 62,175-square-
foot former Hexcel research and development building and construct a new 125,532-square-foot
light industrial building with 217 parking stalls and related site improvements. The project was
first presented to the City Council on March 19, 2024, and the City Council continued the project to
a date uncertain so the Applicant could address City Council comments related to the overall
project design, compatibility with the Dublin Village Historic Area Specific Plan, and landscape
buffer to adjacent properties. The Applicant has since revised the project design and landscaping
in response to comments. Requested approvals include a Planned Development Rezone with a
related Stage 1 and Stage 2 Development Plan, Site Development Review Permit, and Heritage
Tree Removal Permit. The City Council will also consider certification of the Final Environmental
Impact Report.
STAFF RECOMMENDATION:
Conduct a public hearing, deliberate, and take the following actions: 1) adopt the Resolution
Certifying an Environmental Impact Report and Adopting Environmental Impact Findings,
Findings Regarding Alternatives, a Statement of Overriding Considerations, and a Mitigation
Monitoring and Reporting Program for the Hexcel Redevelopment Project; 2) waive the reading
and INTRODUCE the Ordinance Amending the Zoning Map and Approving a Planned Development
Zoning District with Related Stage 1 and Stage 2 Development Plans for the Hexcel Redevelopment
Project; and 3) adopt the Resolution Approving a Site Development Review Permit and Heritage
Tree Removal Permit for the Hexcel Redevelopment Project.
FINANCIAL IMPACT:
The cost associated with processing the project application is borne by the Applicant.
Page 1 of 7
28
DESCRIPTION:
Background
Overton Moore Properties is proposing to demolish the existing 62,175-square-foot Hexcel
research and development building located 11711 Dublin Boulevard and construct a new
125,304-square-foot light industrial building to appeal to advanced manufacturing and life science
uses. Requested approvals include a PD Rezone Stage 1 and Stage 2 Development Plan, Site
Development Review Permit, and Heritage Tree Removal Permit.
Figure 1. Project Location
On March 19, 2024, the City Council held a public hearing to consider the Hexcel Redevelopment
Project. At the meeting, the City Council raised concerns with the project design and compatibility
with the Dublin Village Historic Area Specific Plan, and landscape screening to buffer uses to the
north and east of the project site. At the conclusion of the discussion, the City Council continued
the project to a date uncertain in order to provide time for the applicant to address these
concerns.
Revisions to the Project
Since the March City Council meeting, the Applicant has made the following changes to the project
to address the City Council's comments and concerns, and these changes have been incorporated
into the Site Development Review Permit:
• Revised the project design with the use of brick veneer and muted taupe and earth tones to
complement the brick and soften the building. The massing of the building is broken up
using reveals, paint color, material changes, and articulation, allowing the scale to reflect a
pedestrian orientation. The exterior employs channel canopies with hanging rod details
above the entrances inspired by historical industrial buildings, black channel trim around
the storefront system featuring gray glazing carrying the theme of the canopy, brick
wainscot flanking the main entrances and storefront glazing, accent paint to match the
brick color and provide continuity across building facades, and recessed arch details
inspired by historical brick arched windows. At the tenant locations and in the mezzanine
areas, windows and glazing reflect a stronger vertical orientation with simple frames. The
Page 2 of 7
29
building would have two-story glazing at the proposed office spaces on the north, east and
northwestern elevations, primarily along Dublin Boulevard, maximizing natural light into
the office and mezzanine spaces and providing distinct office entrances for multiple
tenants.
• Added a wood fencing element at the entrance to tie with Heritage Park, including a wood
arbor, fences flanking the main entrance, and stone bases.
• Refined the landscape plan to better match the existing landscape around Heritage Park.
• Added more trees and shrubbery and modified the shrubbery to a fast-growing species to
provide additional screening from Dublin Boulevard at the north and from Heritage Park to
the east.
• Included a stone monument commemorative plaque and located it at the northeast corner
of site to provide high visibility.
With this revised design the applicant proposes a slightly larger and taller building, 228 square
feet larger and six inches taller. The planned development zoning limits the floor area ratio
(FAR) to 0.33 and the maximum building height to 40 feet. Even with the minimal increase in
the building area, the project would still meet the allowable FAR of 0.33. The new building
height (40'6") is inclusive of the parapet, which is an architectural feature. Per the Dublin
Municipal Code (DMC), architectural features may be a maximum of 15 percent higher than the
height limit of the applicable zone, therefore, the new building design complies with the
allowable height limit.
Figure 3. Proposed Building Perspective
Existing landscaping west of the main driveway and new landscaping east of the main driveway
would provide a landscape buffer along Dublin Boulevard to help soften the project frontage.
Furthermore, along the southern boundary of the project site, all existing landscaping would
remain within Parcel 2, which provides a buffer from Interstate-580 and the rear of the building.
Large shade trees in the parking lot area would provide shade and reduce the urban heat island
effect. The landscape design preserves the existing heritage trees on site and incorporates them
into the site design. New landscape screening which includes 48 trees and matches the plant pallet
Page 3 of 7
30
found in the Historic Area is provided along Dublin Boulevard to screen and soften the building
from public view. This includes preserving the existing trees and planting 38 new trees ranging
from 15 feet to 70 feet tall at maturity and new fast-growing shrubbery. Figures 4 and 5 below are
renderings of the landscaping.
Figure 4. Proposed Dublin Boulevard Frontage Landscaping
Figure 5. Proposed Parking Lot Landscaping
The landscaping along the eastern property line provides new shrubbery and trees to screen the
project from the adjacent properties. A total of 18 trees would be provided east of the proposed
building, which includes one existing Chinese elm tree to remain and 17 new trees ranging in
height from 30 feet to 50 feet at maturity. Shrubbery eight feet in height at maturity would also be
planted to further buffer the site in addition to the existing landscaping on the adjacent property
to the east between the project site and the Dublin Heritage Park and Museums and Pioneer
Cemetery. A condition of approval has been provided to ensure this landscaping is protected
during grading/construction activities.
Specifically, the new landscaping southeast of the proposed building would provide screening
Page 4 of 7
31
from the Dublin Pioneer Cemetery and the dense tree canopy on the cemetery property. In
addition to the shrubbery noted above, 14 new trees would be planted in this area to screen the
building from view of the cemetery. Figure 6 shows the proposed building perspective view from
the Dublin Pioneer Cemetery.
Figure 6. Proposed Project Site View from Dublin Pioneer Cemetery
The draft Ordinance amending the Zoning Map and approving Planned Development Zoning with
related Stage 1 and 2 Development Plans is included as Attachment 7. The Resolution approving
the Site Development Review Permit and Heritage Tree Removal Permit is included as Attachment
8, with the Project Plans (Attachment 9) and the Arborist Report (Attachment 10). A complete
discussion of the project is provided in the Staff Report of March 19, 2024 (Attachment 12).
ENVIRONMENTAL DETERMINATION:
Pursuant to the requirements of the California Environmental Quality Act (CEQA), the City
prepared an Environmental Impact Report (EIR) for the proposed project. On May 15, 2023, the
City issued a Notice of Preparation for an EIR and held a public scoping meeting on May 25, 2023.
The City received three letters regarding the scope of the EIR. Subsequently, a Draft EIR was
prepared for the proposed project and circulated for a 45-day public review period from August
21, 2023 to October 5, 2023. The City received three comment letters during the public review
Page 5 of 7
32
period. In addition, a fourth letter was received after the public review period. Responses have
been prepared for each of the comments received by the City. The Draft EIR, comments and
associated responses, and changes and clarifications to the Draft EIR constitute the Final EIR
(Attachment 2).
The environmental document prepared for the project is a Focused EIR that evaluates potential
impacts of a limited number of environmental issue areas that the City determined to be
significant (CEQA Guidelines Section 15063(c)(3)). After preparation of an Initial Study, the City
determined that the proposed project would have significant or potentially significant impacts in
the following topic areas that require further analysis and are therefore discussed in the Draft EIR:
• Air Quality
• Biological Resources
• Cultural Resources*
• Energy
• Geology and Soils
• Hazards and Hazardous Materials
• Tribal Cultural Resources
The Draft EIR concludes that the proposed project would have a significant and unavoidable
impact on Cultural Resources (noted above with *). The remaining topic areas have mitigation
measures that have been prepared to reduce impacts in these areas to a level that is less than
significant. Attachment 12 provides an overview of all topic areas.
After the EIR was prepared for the project, the applicant revised the architecture and landscape
plan and increased the size of the building by 228 square feet and increased the height by six
inches in response to City Council concerns, as discussed above. These changes would not affect
any of the conclusions in the Initial Study and EIR because they are related to visual changes that
would result in making the proposed building blend in better with the surrounding Historic Area.
The minimal increase in the footprint and height would not substantially change the visual
appearance or bulk/scale of the building such that the initial study conclusions regarding
aesthetics would be affected. The minimal increase to the size of the building would not
substantially change the required excavation and grading. The proposed changes would not result
in any additional or more severe impacts from what was already analyzed, and no new mitigation
measures are required.
The City Council resolution certifying the Final Environmental Impact Report is included as
Attachment 1. To approve the project, the City Council must make findings regarding significant
impacts and mitigation measures (Attachment 3), make findings concerning infeasibility of
alternatives and potential additional mitigation measures (Attachment 4), and adopt a Statement
of Overriding Considerations (SOC) (Attachment 5) that identifies all environmental impacts that
cannot be mitigated and explains why the benefits of the project outweigh its unavoidable
environmental impacts. The Mitigation Monitoring and Reporting Program is included as
Attachment 6.
Page 6 of 7
33
STRATEGIC PLAN INITIATIVE:
None.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
Two City -led Community Meetings were held on October 25 and 26, 2023, to provide Dublin
residents with information about the proposed Hexcel Redevelopment project. Staff provided a
presentation that included an overview of the City's development review process and the
proposed project. Questions were asked about the project's impact on infrastructure capacity and
the general contractor that would be used for the project. Comments were also provided regarding
the EIR and project design.
In accordance with State law, a public notice was mailed to all property owners and occupants
within 300 feet of the proposed project to advertise the project and upcoming public hearing. A
public notice was also published in the East Bay Times and posted at several locations throughout
the City. A Planning Application sign was posted on the project site and the project was also
included on the City's Development Projects webpage. A copy of this Staff Report has been
provided to the applicant.
ATTACHMENTS:
1) Resolution Certifying an Environmental Impact Report and Adopting Environmental Impact
Findings, Findings Regarding Alternatives, a Statement of Overriding Considerations, and a
Mitigation Monitoring and Reporting Program for the Hexcel Redevelopment Project
2) Exhibit A to the Resolution - Final Environmental Impact Report
3) Exhibit B to the Resolution - Findings Concerning Significant Impacts and Mitigation
Measures
4) Exhibit C to the Resolution - Findings Concerning Infeasibility of Alternatives and Potential
Additional Mitigation Measures
5) Exhibit D to the Resolution - Statement of Overriding Considerations
6) Exhibit E to the Resolution - Mitigation Monitoring and Reporting Program
7) Ordinance Amending the Zoning Map and Approving a Planned Development Zoning District
with Stage 1 and Stage 2 Development Plan for the Hexcel Redevelopment Project
8) Resolution Approving a Site Development Review Permit and Heritage Tree Removal Permit
for the Hexcel Redevelopment Project
9) Exhibit A to the Resolution - Hexcel Redevelopment Project Plans
10) Arborist Report
11) Planning Commission Resolution No. 23-11
12) March 19, 2024 Staff Report (without attachments)
Page 7 of 7
34