HomeMy WebLinkAbout5.6 Annual Street Resurfacing (July 2023 Slurry Seal) Project, CIP No. ST0117 –Acceptance of Workr DUBLIN CALIFORNIA STAFF REPORT CITY COUNCIL Agenda Item 5.6 DATE: October 15, 2024 TO: Honorable Mayor and City Councilmembers FROM: Colleen Tribby, City Manager SU B.ECT: Annual Street Resurfacing (July 2023 Slurry Seal) Project, CIP No. ST0117 - Acceptance of Work Prepared by: Michael Boitnott, Capital Improvement Program Manager EXECUTIVE SUMMARY: The City Council will consider the acceptance of the Annual Street Resurfacing (July 2023 Slurry Seal) Project. The project included localized repair of failed asphalt concrete pavement, slurry seal, and pavement delineation on 46 street segments. STAFF RECOMMENDATION: Adopt the Resolution Accepting the Annual Street Resurfacing (July 2023 Slurry Seal) Project, CIP No. ST0117. FINANCIAL IMPACT: The Annual Street Resurfacing (2023 Slurry Seal) Project is complete, and the project cost was as follows: Project Funding Source (FY 2023-24) State Gas Tax Fund $600,920 Measure BB Sales Tax Local Streets Fund $575,000 Road Maintenance & Rehab Account (RMRA) $1,123,961 Total Funding $2,299,881 Page 1 of 2 1 Estimated Expenditures Construction Contract with Change Orders Contract Services, Design, Salary, and Testing $794,375 $348,126 Total Expenditures $1,142,501 Estimated Project Balance $1,157,380 Upon the City Council's acceptance of the project, the remaining budget will be retained within the Annual Street Resurfacing Project for use on other 2024 resurfacing projects. DESCRIPTION: On August 15, 2023, the City Council awarded a construction contract in the amount of $706,586.60 to American Asphalt Repair & Resurfacing Co., Inc. for the Annual Street Resurfacing (July 2023 Slurry Seal) Project, CIP No. ST0117. The slurry seal program provides for the preventative maintenance of our local streets and roads. As streets begin showing wear and stress cracks, it is important to seal the cracks to keep water from getting under the street pavement. Slurry seal is a preventative maintenance technique used to prolong the life of asphalt concrete surfacing. The material consists of a sand/oil mixture, which seals cracks and provides a new uniform wearing surface. The 2023 project included localized repair of failed asphalt concrete pavement, slurry seal, and pavement delineation on 46 street segments as shown on the Location Map (Attachment 2). The total project included approximately 1.57 million square feet of slurry seal, 23,322 square feet of pavement "Hot Mix Asphalt" dig out repairs, and 2,850 square feet of resurfacing. Staff has determined that the project is complete and recommends that the City Council accept the project and begin the warranty period. The estimated remaining project budget of $1,157,380 will be retained within the Annual Street Resurfacing Project budget. STRATEGIC PLAN INITIATIVE: None. NOTICING REQUIREMENTS/PUBLIC OUTREACH: The City Council Agenda was posted, and a copy of this report was sent to American Asphalt Repair & Resurfacing Co., Inc. ATTACHMENTS: 1) Resolution Accepting the Annual Street Resurfacing (July 2023 Slurry Seal) Project, CIP No. ST0117 2) July 2023 Slurry Seal, Project Location Map 3) CIP No. ST0117 Page 2 of 2 2 Attachment I RESOLUTION NO. XX - 24 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN ACCEPTING THE ANNUAL STREET RESURFACING (JULY 2023 SLURRY SEAL) PROJECT, CIP NO. ST0117 WHEREAS, on August 15, 2023, the City of Dublin entered into a Construction Contract with American Asphalt Repair & Resurfacing Co., Inc. for the Annual Street Resurfacing (July 2023 Slurry Seal) Project, that slurry coated 46 street segments; and WHEREAS, said improvements have been completed in accordance with plans and specifications, and any approved modifications thereof, to the satisfaction of the City Engineer of the City of Dublin; and WHEREAS, as a condition of the contract, American Asphalt Repair & Resurfacing Co., Inc. is required to warranty the improvements for a period of one year following the completion of the work and maintain a maintenance bond in the amount of 10% of the final contract value. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby accept the Annual Street Resurfacing (July 2023 Slurry Seal) Project, CIP No. ST0117 and authorize Staff to file a Notice of Completion with Alameda County. BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize the City Manager, or designee, to release the retention, if after 35 days of filing the Notice of Completion there are no subcontractor claims. BE IT FURTHER RESOLVED that the City Council of the City of Dublin does hereby authorize the City Manager, or designee, to release the maintenance bond at the end of the one-year warranty period. {Signatures on the following page} Reso. No. XX-24, Item X.X, Adopted 10/15/2024 Page 1 of 2 3 Attachment I PASSED, APPROVED AND ADOPTED this 15th day of October 2024, by the following vote: AYES: NOES: ABSENT: ABSTAIN: Mayor ATTEST: City Clerk Reso. No. XX-24, Item X.X, Adopted 10/15/2024 Page 2 of 2 4 Attachment 2 Annual Street Resurfacing "July 2023 Slurry Seal" Project No. ST0117 Location Map 5 Attachment 3 Number — STO 117 i ANNUAL STREET RESURFACING Program — STREETS PROJECT DESCRIPTION This project provides for the design and construction of a variety of pavement resurfacing treatments, from slurry seal to major rehabilitation and reconstruction of streets and resurfacing of bridge decks. The project also includes installation of new or upgrades of existing ADA curb ramps on roads that are reconstructed or receive an asphalt concrete overlay. Streets are selected for improvements based on the City's Pavement Management System to optimize the pavement condition in relation to the available budget. The City owns and maintains approximately 148 centerline miles of streets. The Metropolitan Transportation Commission groups Pavement Condition Index (PCI) ratings into the following categories: 80-100 Very Good -Excellent; 70-79 Good, 60-69 Fair, 50-59 At Risk, 25-49 Poor, and 0-24 Failed. The City of Dublin is rated very good with a three-year moving average PCI of 80. PROJECT TIMELINE: The project is currently in various stages of design or construction. Improvements are typically constructed each year between spring and fall. ANNUAL OPERATING IMPACT: None. 2024-2029 CAPITAL IMPROVEMENT PROGRAM PRIOR FUTURE ESTIMATED COSTS YEARS 2024-2025 2025-2026 2026-2027 2027-2028 2028-2029 YEARS TOTALS 9100 — Salaries & Benefits $227,235 $167,500 $167,500 $167,500 $167,500 $167,500 $1,064,735 9200 — Contract Services $2,509,344 $775,000 $775,000 $775,000 $775,000 $775,000 $6,384,344 9400 — Improvements $12,737,648 $3,550,000 $3,550,000 $3,550,000 $3,550,000 $3,550,000 $30,487,648 9500 — Miscellaneous $56,311 $7,500 $7,500 $7,500 $7,500 $7,500 $93,811 TOTAL $15,530,538 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $38,030,538 Streets Five -Year Capital Improvement Program 2024-2029 66 6 FUNDING SOURCE PRIOR YEARS 2024-2025 2025-2026 2026-2027 2027-2028 2028-2029 FUTURE YEARS TOTALS 1001 — General Fund $467,999 $1,250,000 $2,086,900 $1,750,000 $1,850,000 $1,850,000 $9,254,899 2201 — State Gas Tax $5,289,941 $700,000 $413,100 $750,000 $650,000 $650,000 $8,453,041 2204 — Measure B Sales Tax — Local Streets Fund (ACTC) $1,784,999 $1,784,999 2205 — Measure B Sales Tax — Bike & Pedestrian Fund (ACTC) $300,000 $300,000 2214 — Measure BB Sales Tax — Local Streets Fund (ACTC) $2,831,020 $200,000 $3,031,020 2215 — Measure BB Sales Tax — Bike & Pedestrian Fund (ACTC) $304,500 $304,500 2216 — Measure B Grants $82,500 $82,500 2220 — Road Maint. & Rehab. Account (RMRA) $4,263,599 $2,350,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $14,263,599 2304 — Local Recycling Programs $160,000 $160,000 4309 — Miti! ation Contributions TOTAL $45,980 $15,530,538 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $4,500,000 $45,980 $38,030,538 Streets Five -Year Capital Improvement Program 2024-2029 67 7