HomeMy WebLinkAbout7.1 MuniElectricFeasStudyCITY CLERK FILE # 600-30
AGEN DA STATEMENT
CITY COUNCIL MEETING DATE: February 5, 2002
SUBJECT:
Consultant Services for Municipal Electric Utility Feasibility Study
Report Prepared by: Christopher L. Foss, Economic Development
Director
ATTACHMENTS:
RECOMMENDATION:
1. Resolution Approving Agreement with Consultant
2. Consultant Services Agreement
3. Budget Change Form
1. Adopt Resolution Approving Agreement with Environmental
Services Associates for Energy Consulting Services
2. Authorize the City Manager to sign on behalf of the City
3. Approve Budget Change.
FINANCIAL STATEMENT: The cost of the proposed study is $9,730. Funds were not
appropriated in the FY 2001-2002 budget for this study; however, the City did allocate a reserve of
$750,000 for energy projects. A budget change will be necessary.
DESCRIPTION: At its meeting of August 21, 2001, the City Council discussed the
possible role of the City of Dublin in meeting the present and future energy needs for the community. '
During the meeting, the City Council supported the goals of an energy policy that would: (1) Identify and
meet the City's present and future energy needs; and (2) Secure a consistent and affordable source of
power. With those goals in mind, Staff was directed to prepare a Request for Proposal (RFP) to secure the
services of an independent energy consultant that would help the City identify issues involving electric
production. The selected consultant will also assist Staff in the preparation of an RFP to be sent to
independent power producers to determine the level of interest and the potential for such a venture.
On October 2, 2001, the City Council approved the Request for Proposal (RFP) for a Municipal Electric
Utility Feasibility Study and directed Staff to issue the RFP to qualified consultants. The RFP was mailed
to thirty (30) consultants from throughout the United States. Following a review of the eight (8) RFP
submittals, staff convened the City Cotmcil subcommittee (comprised of Mayor Lockhart and Council
Member Oravetz) to review the proposals. As a result of that review, the subcommittee unanimously
recommended that an amended report by Environmental Services Associates (ESA) be forwarded for
ratification by the entire City Council.
H/cc-forms/agdastmt.doc
COPIES TO:
ITEM NO.
The proposal from ESA calls for the completion of a technical briefing paper addressing the current state .
of electrical energy in California and providing strategic recommendations relevant to the City. The study
will be completed in approximately three to four weeks at a cost not to exceed$ 9,730.
As part of the FY 2001-2001 budget, the City Council allocated $750,000 to reserves for energy projects.
The City Council will need to consider and approve a budget change in the amount of$ 9,730 transferring
this amount from the reserve to the Economic Development budget to cover the costs of the study.
RECOMMENDATION:
•
It is Staff's recommendation that the City Council adopt the Resolution approving the Consultant Services
Agreement with Environmental Services Associates and authorize the City Manager to sign on the City's
behalf. Staff would further recommend that the City Council approve the budget change in the amount of
$ 9,730 to pay for the cost of the Study.
•
•
/ e/r
• RESOLUTION NO. - 02
A RESOLUTION OF THE CITY COUNCIL
- OF THE CITY OF DUBLIN
* * * * * * * * *
APPROVING AGREEMENT WITH ENVIRONMENTAL SERVICES ASSOCIATES
TO CONDUCT MUNICIPAL ELECTRIC UTILITY FEASIBILITY STUDY
WHEREAS, the City issued a Request for Proposals to qualified energy consulting firms to
prepare a municipal electric utility feasibility study, and
WHEREAS, Environmental Services Associates was determined to be the most qualified
consultant;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
approve the agreement with Environmental Services Associates.
BE IT FURTHER RESOLVED that the City Manager is authorized to execute the agreement.
PASSED, APPROVED AND ADOPTED this 5th day of February, 2002.
AYES:
NOES:
ABSENT:
ABSTAIN:
Mayor-
ATTEST:
City Clerk . __
G:IChrislEnergylresolutionenergryconsultant12182001.doc m f — 1451/61 0
Attachment 1
STANDARD CONTRACTUAL SERVICES AGREEMENT
THIS AGREEMENT is made at Dublin, California, as of February 5, 2002, by and between the CITY
OF DUBLIN, a municipal Corporation ("CITY"), and Environmental Services Associates ("CONTRACTOR"),
who agree as follows:
1. SERVICES. Subject to the terms and conditions set forth in this Agreement, CONTRACTOR
shall provide to CITY the services described in Exhibit A. CONTRACTOR shall provide said services at the
time, place and in the manner specified in Exhibit A.
2. PAYMENT. CITY shall pay CONTRACTOR for services rendered pursuant to this Agreement
at the time and in the manner set forth in Exhibit B. The payments specified in Exhibit B shall be the only
payments to be made to CONTRACTOR for services rendered pursuant to this Agreement. CONTRACTOR
shall submit all billings for said services to CITY in the manner specified in Exhibit B; or, if no manner be
specified in Exhibit B, then according to the usual and customary procedures and practices which
CONTRACTOR uses for billing clients similar to CITY.
3. FACILITIES AND EQUIPMENT. Except as set forth in Exhibit. C, CONTRACTOR shall, at its
sole cost and expense, furnish all facilities and equipment, which may be required for furnishing services
pursuant to this Agreement. CITY shall furnish to CONTRACTOR only the facilities and equipment listed in
Exhibit C according to the terms and conditions set forth in Exhibit C.
4. GENERAL PROVISIONS. The general provisions set forth in Exhibit D are part of this
Agreement. In the event of any inconsistency between said general provisions and anyother terms or conditions
of this Agreement, the other term or condition shall control insofar as it is inconsistent with the general
provisions.
5. EXHIBITS. All exhibits referred to herein are attached hereto and are by this reference
incorporated herein.
6. CONTRACT ADMINISTRATION. This Agreement shall be administered by Richard C.
Ambrose ("ADMINISTRATOR"). All correspondence shall be directed to or through the ADMINISTRATOR
or his or her designee.
7. NOTICES. Any written notice to CONTRACTOR shall be sent to:
John E. Forsythe, AICP
Senior Project Manager
Environmental Science Associates
8950 Cai Center Drive, Suite 300
Sacramento, CA 95826
Any written notice to CITY shall be sent to:
City of Dublin
Attn: Richard Ambrose
P. O. Box 2340
Dublin, CA 94568
Executed as of the day first above stated:
Attest:
City Clerk
CITY OF DUBLIN
a municipal corporation
By
"CITY"
Attachment 2
Approved as to form:
City Attorney
"CONTRACTOR"
EXHIBIT A
SCOPE OF SERVICES
The scope of services for this contract is included as EXHIBIT A-1.
Exhibit A
Page 1 of 1 - --
4/1/90
e /v
•
•
Environmental -
• ,�•��, .' 4•; rJClenCe
RECEIVED
l CEI i7 CpppgKq
E
Associates
JAN 1 7 2002
CITY OF DUBLIN
January 16,2002 •
•
Mr. Chris Foss
Economic Development Director
City of Dublin
• 100 Civic Center Plaza Drive
Dublin, California 94568
SUBJECT: ' • Proposal for•a'Technical Briefing Paper on the State of Energy in California
Dear Mr.Foss:
Thank you for your continued interest in the services of Environmental Science Associates' (ESA's)Energy
and Information Utilities group. Pursuant to your request,we have prepared a revised proposal to the City of
Dublin(City) for a technical briefing paper addressing the current state of electrical energy in California and
providing strategic recommendations relevant to the City. The paper is intended to provide the City with
information on the condition of electric utility services in the state to allow the City to make informed
decisions regarding its own energy policy destiny.
SCOPE OF SERVICES
The following task list provides our understanding of the requirements of this project, as well as our
proposed approach to element.
Task
Provide Information on Current State of Electric Utility Industry, Current Trends, Legislation, Ongoing
Activities, Responses by Municipalities, and Related Information
• We will prepare a technical memorandum, and/or participate in'a technical workshop or roundtable
discussion,providing information to City staff and decision-makers regarding the following items
and how these topics relate to the City:
— We will provide an overview of AB 1890,passed in 1996, and the Restructuring of the Electric
Industry in California.
— We will summarize the energy crisis of 2000-2001 and Pacific Gas and Electric Company's
bankruptcy proceedings and potential impacts to the City's rate base.
— We will provide an overview of California's electric utility industry restructuring, merchant
power plants, and other recent developments in the utility industry potentially affecting the.City.
_ — Given existing regulatory and legislative constraints, we will evaluate potential ways which the
City can improve its existing electricity situation.
8950 Cal Center Drive,Suite 300 Sacramento,Califox EXHIBIT A-1 500 fax 564-4501 www.esassoc.com
Mr. Chris Foss
Economic Development Director
January 16, 2002
Page 2
- We will examine ongoing efforts by other communities and how these actions potentially could
be implemented in the City.
We will discuss the Possibility of purchasing bulk power from other wholesalers, including the
required elements necessary to allow the City to engage in such actions and potential contracting
options.
- We will describe in the technical memorandum a Variety of power buying options that, although
currently prohibited by state legislation, are potentially provided by local aggregation.
We will provide a technical memorandum describing the requirements of the formation of a
municipal utility in the City. While we do not propose to conduct a formal feasibility study
under this contract, the details and requirements of such a study will be delineated under this
task, and the relative pros and cons of forming a municipal utility will be established. All legal,
political, financial, and engineering requirements will be detailed.
We will identify policy-level options, Such as a General Plan energy element, which can be
prepared and adopted by the City to assist in controlling its own energy destiny while
maximizing its resources and encouraging conservation.
COST AND SCHEDULE
Table 1 reflects our cost estimate to prepare the briefing paper as described above. We will apply applicable
rates based on our standard rate schedule for 2001 (Table 2). Our proposed cost reflects a level of effort we
believe to be commensurate with the task and adequate for the City' s purposes. However, if the City prefers
-an analysis with more or less detail than we have proposed, we will be happy to re-examine this scope.
We.estimate that we can complete the report within a period of 3 to 4 weeks. If the City prefers to conduct a
workshop or meeting to discuss the report and its conclusions, this can be done either during the preparation
process or after the report is complete. We also should note that some information from and involvement of
City staff may be necessary, but we will clearly identify any informational or staff assistance needs on
contract authorization.
We look forWard to the opportunity to work with the City on this important project. If you have any
questions about our proposal or require additional information, please do not hesitate to call me at 916/564-
4500, or Dail Miller at 510/839-5066.
Sincerely,
Senior Project Manager
JEF/jet
P202039
Enclosures
Table 1. ESA's Cost Estimate for a Technical Briefing Paper on the State of Energy in California
Personnel Rate Hours Total
Project Director $140 10 $1,400
Project Manager $115 30 $3,450
Associate II $70 48 $3,360
Administrative Costs (copies,
correspondence, documents)
$300
Briefing Session (1)
$1,220
TOTAL $9,730
ESA Envlronmenta~
Science
Associates
Table 2. ESA's Fully Burdened Labor Billing Rates
Employee Category
Director / Principal III
Director / Principal II
Director / Principal I
Senior Project Manager / Technical Associate II
Project Manager / Technical Associate I
Senior Associate II
Senior Associate I
Associate III
Associate II
Associate I
Senior Administrative
Sr. Graphics I
Graphics
Admin II ! Admin III ! Production
Admin I / Clerical
Hourly Billing Rate
$150.00
$140.00
$125.00
$115.00
$100.00
$95.OO
$85.00
$70.00
$60.00
$50.00
$75.00
$65.00
$60.00
$60.00
$45.00
Postage / Overnight Mail
Courier Charges
Fax Charges
Phone Charges
Mileage
Other Direct Costs
Copying Charges
Actual cost + 15%
Actual cost + 15%
$2.00 per page plus actual phone costs
Actual cost + 15%
Standard mileage set by Federal
regulations
At actual cost + 15%
$0.05 each
EXHIBIT B (page 1 of 1)
PAYMENT SCHEDULE
CITY shall pay CONTRACTOR an amount not to exceed the total sum of Nine Thousand Seven Hundred Fifty
Dollars ($ 9,750) for services to be performed pursuant to this'Agreement. CONTRACTOR shall submit
invoices during the term of this Agreement based on the cost for services performed in accordance with the
folloWing schedule:
Monthly
but not more often than once a month; and provided further, in no event shall CITY pay CONTRACTOR a sum
exceeding 20% of the total sum due for services pursuant to this Agreement in any one month; and provided
further, CITY shall pay the last 20% of the total sum due pursuant to this Agreement within forty-five (45) days
after completion of the services and submittal to CITY, if all services due pursuant to this Agreement have been
satisfactorily performed.
The total sum stated above shall be the total, which CITY shall pay for the services to be rendered by
CONTRACTOR pursuant to this Agreement. CITY shall not pay any additional sum for any expense or cost
whatsoever incurred by CONTRACTOR in rendering services pursuant to this Agreement.
CITY shall make no payment for any extra, further or additional service pursuant to this Agreement
unless such extra service and the price therefor is agreed to in writing executed by the City Manager or other
designated official of CITY authorized to obligate CITY thereto prior to the time such extra service is rendered
and in no event shall such change order exceed twenty-five (25%) of the initial contract price.
The services to be provided under this Agreement may be terminated without cause at any point in time
in the sole and exclusive discretion of CITY. In this event, CITY shall compensate the CONTRACTOR for all
outstanding costs incurred as of the date of written notice thereof and shall terminate this Agreement.
CONTRACTOR shall maintain adequate logs and timesheets in order to verify costs incurred to date.
The CONTRACTOR is not authorized to perform any services or incur any costs whatsoever under the
terms of this Agreement until receipt of a fully executed Purchase Order from the Finance Department of the
City of Dublin.
EXHIBIT C - City Facilities
CITY shall furnish physical facilities such as desks, filing cabinets, and conference space, as may be
reasonably necessary for CONTRACTOR'S use while consulting with CITY employees and reviewing records
and the information in possession of CITY. The location, quantity, and time of furnishing said physical
facilities shall be in the sole discretion of CITY. In no event shall CITY be obligated to furnish any facility,
which may involve incumng any direct expense, including, but not limiting the generality of this exclusion,
long-distance telephone or other communication charges, vehicles, and reproduction facilities.
Exhibit C
Page 1 of 1
4/1/90
EXHIBIT D
GENERAL PROVISIONS
1. INDEPENDENT CONTRACTOR. At all times during the term of this Agreement,
CONTRACTOR shall be an independent contractor and shall not be an employee of CITY. CITY shall have the
fight to control CONTRACTOR only insofar as the results of CONTRACTOR'S services rendered pursuant to
this Agreement;'however, CITY shall not have the fight to control the means by which CONTRACTOR
accomplishes services rendered pursuant to this Agreement.
2. LICENSES: PERMITS: ETC. CONTRACTOR represents and warrants to CITY that he has all
licenses, permits, qualifications and approvals of whatsoever nature, which are legally required for
CONTRACTOR t.o practice his profession. CONTRACTOR represents and warrants to CITY that
CONTRACTOR shall, at his sole cost and expense, keep in effect at all times during the term of this Agreement
any licenses, permits, and approvals which are legally required for CONTRACTOR to practice his profession.
3. TIME. CONTRACTOR shall devote such time to the performance of services pursuant to this
Agreement as may be reasOnably necessary for satisfactory performance of CONTRACTOR'S obligations
pursuant to this Agreement.
4. INSURANCE REQUIREMENTS. CONTRACTOR shall procure and maintain for the duration
of the contract insurance against claims for injuries to persons or damages to property, which may arise from or
in connection with the performance of the work hereunder by the CONTRACTOR, his agents, representatives,
employees or subcontractors~ The cost of such insurance shall be included in the CONTRACTOR'S bid.
(a) Minimum Scope of Insurance. Coverage shall be at least as broad as:
1. Insurance Services Office form number GL 0002 (Ed. 1/73) covering comprehensive
General Liability and Insurance Services Office form number GL 0404 covering Broad Form Comprehensive
General Liability; or Insurance Services Office Commercial General Liability coverage ("occurrence" form CG
0001.)
2. Insurance Services Office form number CA 0001 (Ed. 1/78) covering Automobile
Liability, code 1 "any auto" and endorsement CA .0025.
3. Workers' Compensation Insurance as required by the Labor Code of the State of
California and Employers Liability Insurance.
(b) Minimum Limits of Insurance. CONTRACTOR shall maintain limits no less than:
1. General Liability: $1,000,000 combined single limit per occurrence for bodily injury,
personal injury and property damage. If commercial General Liability Insurance or other form with a general
aggregate limit is used, either the general aggregate limit shall apply separately to this project/location or the
general aggregate limit shall be twice the required occurrence limit.
2. Automobile Liability: $1,000,000 combined single limit per accident for bodily injury
and property damage.
3. Workers' Compensation and Employers Liability: Workers' Compensation limits as
required by the Labor Code of the State of California and Employers Liability limits of $1,000,000 per accident.
Exhibit D (Page 1 of )
4/1/90
(c) Deductibles and Self-Insured Retentions. Any deductibles or self-insured retentions must be
declared to and approved by the CITY. At the option of the CITY, either the insurer shall reduce or eliminate
such deductibles or self-insured retentions as respects the CITY, its officers, officials and employees; or the
CONTRACTOR shall procure a bond guaranteeing payment of losses and related investigations, claim
administration and defense expenses.
(d) Other Insurance Provisions. The policies are to contain, or be endorsed to contain, the following
provisions:
1. General Liability and Automobile Liability Coverages.
a. The CITY, its officers, officials, employees and volunteers are to be covered as
insureds as respects: liability arising out of activities performed by or on behalf of the CONTRACTOR;
products and completed operations of the CONTRACTOR, premises owned, occupied or used by the
CONTRACTOR, or automobiles owned, leased, hired or borrowed by the CONTRACTOR. The coverage shall
contain no special limitations on the scope of the protection afforded to the CITY, its officers, officials,
employees or volunteers.
b. The CONTRACTOR'S insurance coverage shall be primary insurance as respects
the CITY, its officers, officials, employees and volunteers. Any insurance or self-insurance maintained by the
CITY, its officers, officials, employees or volunteers shall be excess of the CONTRACTOR'S insurance and
shall not contribute with it.
c. Any failure to comply with reporting provisions of the policies shall not affect.
coverage provided to the CITY, its officers, officials, employees or volunteers.
d. The CONTRACTOR'S insurance shall apply separately to each insured against
whom claim is made or suit is brought, except with respect to the limits of the insurer's liability.
2. Workers' Compensation and Employers Liability Coyerage.
The insurer .shall agree to waive all rights of subrogation against the CITY, its officers,
officials, employees and volunteers for losses arising from work performed by the CONTRACTOR for the
CITY.
3. Professional Liability.
CONTRACTOR shall carry professional liability insurance in an amount deemed by the
CITY to adequately protect the CONTRACTOR against liability caused by negligent acts, errors or omissions
on the part of the CONTRACTOR in the course of performance of the services specified in this Agreement.
4. All Coverages.
Each insurance policy required by this clause shall be endorsed to state that coverage
shall not be suspended, voided, canceled by either party, reduced in coverage or in limits except after thirty (30)
days' prior written notice has been given to the CITY. (Note: Insurance companies will not do this)
(e) Acceptability of Insurers. Insurance is to be placed with insurers with a Bests' rating of no less
than A: VII.
(f) Verification of Coverage. CONTRACTOR shall furnish CITY with certificates of insurance and
with original endorsements effecting coverage required by this clause. The-certificates and endorsements for
each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf. The
certificates and endorsements are to be received and approved by the CITY before work commences. The CITY
reserves the right to require complete, certified copies of all required insurance policies, at any time.
(g) Subcontractors. CONTRACTOR shall include all subcontractors as insureds under its policies or
shall furnish separate certificates and endorsements for each subcontractor. All coverages for subcontractors
shall be subject to all of the requirements stated herein.
Exhibit D (Page 2 of 3)
4/1/90
/9
(h) The Risk Manager of CITY may approve a variation in those insurance requirements upon a
determination that the coverages, scope, limits and forms of such insurance are either not commercially
available or that the CITY's interests are otherwise fully protected.
5. CONTRACTOR NO AGENT. Except as CITY may specify in writing, CONTRACTOR shall' have no
authority, express or implied, to act on behalf of CITY in any capacity whatsoever as an agent.
CONTRACTOR shall have no authority, express or implied, pursuant to this Agreement to bind CITY to any -
obhgation whatsoever.
6. ASSIGNMENT PROI-I]~ITED. No party to this Agreement may assign any right or obligation pursuant
to this Agreement. Any attempted or purported assignment of any right or obligation pursuant to this
Agreement shall be void and of no effect.
7. PERSONNEL. CONTRACTOR shall assign only competent personnel to perform services pursuant to
this Agreement. In the event that CITY, in its sole discretion, at any time during the term of this Agreement,
desires the removal of any such persons, CONTRACTOR shall, immediately upon receiving notice from CITY
of such desire of CITY, cause the removal of such person or persons.
8. STANDARD OF PERFORMANCE. CONTRACTOR shall perform all services required pursuant to
this Agreement in the manner and according to the standards observed by a competent practitioner of the
profession in which CONTRACTOR is engaged in the geographical area in which CONTRACTOR practices
his profession. All instruments of Service of whatsoever nature which CONTRACTOR delivers to CITY
pursuant to this Agreement shall be prepared in a substantial, first class and workmanlike manner and conform
to the standards of quality normally observed by a person practicing in CONTRACTOR's profession.
9. HOLD HARMLESS AND RESPONSIBII,ITY OF CONTRACTORS. CONTRACTOR shall take all
responsibility for the work, shall bear all losses and damages directly or indirectly resulting to him, to any
subcontractor, to the CITY, to CITY officers and employees, or to parties designated by the CITY, on account
of the performance or character of the work, unforeseen difficulties, accidents, occurrences or other causes
predicated on active or passive negligence of the CONTRACTOR or any subcontractor. CONTRACTOR shall
indemnify, defend and hold harmless the CITY, its officers, officials, directors, employees and agents from and
against any or all loss, liability, expense, claim, costs (including costs of defense), suits, and damages of every
kind, nature and description directly or indirectly arising from the negligent performance of the work. This
paragraph shall not be construed to exempt the CITY, its employees and officers from its own fraud, willful
injury or violation of law whether willful or negligent. For purposes of Section 2782 of the Civil Code the
parties hereto recognize and agree that this agreement is not a construction contract. By execution of this
agreement CONTRACTOR acknowledges and agrees that he has read and understands the provisions hereof
and that this paragraph is a material element of consideration.
Approval of the insurance contracts does not relieve the CONTRACTOR or subcontractors from liability
under this paragraph.
10. GOVERNMENTAL REGULATIONS. To the extent that this Agreement may be funded by fiscal
assistance from another governmental entity, CONTRACTOR shall comply with all applicable rules and
regulations to which CITY is bound by the terms of such fiscal assistance program.
11. DOCUMENTS. All reports, data, maps, models, charts, studies, surveys, photographs, memoranda or
other written documents or materials prepared by CONTRACTOR pursuant to this Agreement shall become the
property of CITY upon completion of the work to be performed hereunder or upon termination of the
Agreement.
Exhibit D (Page 3 of 3)
CITY OF DUBLIN
BUDGET CHANGE FORM
CHANGE FORM #
New Appropriations (City Council Approval Required):
Budget Transfers:
_xxxx_ From Energy Project Reserve From Budgeted Contingent Reserve (1080-799.000)
Within Same Department Activity
From New Revenues Between Departments (City Council Approval Required)
Other
Name: Name: Contract Services - General $ 9,730.00
Account #: Account #: 001.90400.740.000
Name: Name:
Account #: Account #:
Name: Name: .
Account #: Account #:
Name: Name:
Account #: Account #:
Name: Name:
Account #:' Account #:
Fin Mgr/ASD: Y~".~ ~ ~, ~ Date:
Signature
REASON FOR BUDGET CHANGE ENTRY: The costs associated with the preparation of the Municipal
Electric Utility Feasibility Study were not budgeted for FY 2001-2002.
City Manager: Date:
Signature
Mayor: Date:
Signature
Posted By:
Signature
form~budgchng
Attachment 3
Date: