AGENDA STATEMENT
CITY COUNCIL MEETING DATE: March 16, 2004
SUBJECT: Public Hearing- An Ordinance of the City of Dublin Creating a
New Chapter 5.61 to the Dublin Municipal Code - Green
Building Practices for City Projects.
Adding this new Chapter will allow for a uniform approach in using
Green Building practices for City ProjeCts.
Report Prepared By: Joni L. Pattillo, Assistant City Manager
ATTACHMENTS: 1) Proposed Green Building Ordinance
2) City Council Agenda Statement without Attachments dated
February 17, 2004
RECOMMENDATION: 1) Open the Public Heating
2) Receive StafFs Presentation
...~,~~3) Receive Public Testimony
Question Staff and the Public
5)Close Pubhc Heating and Deliberate
6) Waive the reading and adopt the Ordinance adding new Chapter
5.61, Green Building Practices to the Dublin Municipal
Code
FINANCIAL STATEMENT: It is possible that this Ordinance will result in increased costs for
certain capital improvement projects. The precise costs are
unknown. It is estimated that City projects requiring LEEDTM silver
certification under the proposed Ordinance could experience cost
increases of up to 2% of the total project cOst and an additional
$20,000 to $40,000 for the LEEDTM application process. Another
potential outcome might be a need to adjust Development Fees
associated with Public Facilities to accommodate the estimated
increase of 2%. However, green buildings typically result in
significant life cycle savings, often exceeding the initial investment
by as much as ten times.
COPIES TO:
ITEM NO. ~
H/cc-forras/agdastmt. doc
DESCRIPTION:
City Council directed Staff at the March 2, 2004 City Council meeting to bring back the proposed Green
Building Ordinance, for its second reading and possible adoption. The proposed Ordinance contains the
City Councils' recommended changes from the February 17, 2004 City Council meeting which were to
incorporate the LEEDTM Silver rating, or a City-approved equivalent for all City building projects with the
estimated cost of construction of $3,000,000 or greater in value into the proposed Ordinance.
GREEN BUILDING DESCRIPTION:
Green building is a whole systems approach to the design, construction and operation of buildings - from
the early stages of development (e.g. recycling C&D debris) through the final finishes of the building (e.g.
using sustainable products).
Conventional design and construction methods can produce buildings that negatively impact the
environment as well as the health and productivity of the building occupants. These buildings can be
expensive to operate and contribute to excessive resource and energy consumption, waste generation, and
pollution.
By contrast, green building provides a means for mitigating the undesirable environmental impacts of
conventional building methods. This is accomplished by employing building materials and methods that
promote natural resource conservation, energy efficiency and good indoor air quality.
Although sustainability is a global issue, building plans are approved and constructed locally, and it is at
this level that cities may have the greatest impact. The adoption of the proposed Green Building
Ordinance will formalize the City of Dublin's green building practices and define a process for design,
construction and operation of certain city buildings. In addition, adoption of the Ordinance will further
demonstrate the City's commitment to environmental, economic, and social stewardship, yielding cost
savings to the City taxpayers through reduced operating costs for City facilities, providing healthier work
environments for employees, and contributing to increased conservation of natural resources.
COSTS AND BENEFITS OF GREEN BUILDING:
Fiscal Impact
The State of California recently released the most comprehensive analysis of the financial costs and
benefits of green building titled The Costs and Benefits of Green Building (October 2003). The study
reported that the average additional cost for substantial green building design was slightly less than 2% (of
the building's total design and construction cost), which translates to approximately $3-5/sf. This
conclusion was made after a survey of 33 LEEDTM buildings. The majority of the additional cost is
attributed to the increased architectural and engineering design time necessary to integrate sustainable
building methods into projects. The earlier green building gets incorporated into the design process, the
lower the cost.
Addressing each of these factors can minimize additional capital costs: · Identify projects to be LEEDTM certified at the establishment of the project budget
· Include LEEDTM requirements in RFQs and RFPs
· Use LEEDTM early in the design process
· Train project managers in LEEDTM management skills.
It is important to point out that the cost of green buildings will vary significantly depending on the specific
project goals. While there are many significant benefits that can be included in a project at no additional
cost (orientation, Iow VOC paints, recycled content carpet, etc.), some features will cost more. Estimates
for additional initial costs are as low as 0 to 2%. A LEEDTM Study conducted for the City of Portland
indicated that green building impact on the budget is small - from 2.2% extra cost to 0.3% savings.
The City of Seattle found that after a 3-year implementation period, the incremental cost for meeting
LEEDTM Silver dropped from 6% to 0.1% for small projects and from 4% to 0% for large projects.
While building to LEEDTM standards may result in additional funding for initial design and construction,
LEEDTM buildings are more economical than conventional buildings (i.e.: non green) over their lifetime.
Energy and water efficient buildings can reduce operating costs significantly. Use can be cut to less than
half of a conventional building. Additionally, healthy indoor environments can increase employee
productivity and reduce absenteeism.
The State report found that the 20-year Net Present Value of the life-cycle savings in energy, emissions,
water, waste, and commissioning for a LEEDTM Certified or Silver Building averaged $15.98/sf, while the
20-year Net Present Value for improved productivity and health is $36.89/sf.
The report concluded that a minimal upfront investment of about 2% of construction costs typically yields
life cycle savings of over ten times the initial investment. A recent article in the Wall Street Journal
supports the report's findings.
Other Costs/Benefits
In addition to potential project cost increases, other important green building considerations include the
possibility of limited product aVailability and material selection and longer project completion schedules.
The product market for green building materials, including recycled content products, while still
somewhat limited, has improved dramatically over the past several years. It is anticipated that the market
will continue to mature as more organizations adopt green building policies, resulting in even greater
choices for green building products. It is also important to note that LEEDTM is flexible and allows for
many options regarding which green building elements to incorporate in a given project. LEEDm is based
on a point system, so if it becomes apparent that a specific product is unavailable, points could be earned
by "greening'' other areas of the project.
True green building takes a holistic approach to a building and requires involvement from site planning
and conceptual design through construction. If a project is identified as a green building from the start, it
is more likely that the project would be completed in the same amount of time as a conventional project.
However, project delays can be more likely and more significant if the project is changed midway through
design. Project components such as site orientation, daylighting, Heating, Ventilations and Air
Conditioning (HVAC), windows etc. are integral components to designing an efficient building. If one of
these elements is changed, it could create the need for a major redesign because of how the components
are interrelated. Green building will require more discussion and goal setting at budget development stage
of the project in order minimize changes after the conceptual design has been approved.
While not as easily measurable as the life cycle savings, other green building benefits should be
considered including environmental (conserving of energy, water and other natural resources; improving
air and water quality and a reducing of solid waste) and community benefits (minimizing strain on local
infrastructure, strengthening established goals related to increase density, mixed use and transit-oriented
development, improving stormwater and erosion control, increasing bicycle and pedestrian access and
contributing to community health, vitality and aesthetics).
KEY ELEMENTS OF THE PROPOSED ORDINANCE:
Staff has developed an Ordinance (Attachment 1) that defines and sets thresholds for incorporating green
building practices in civic projects. The key elements of Dublin's proposed Civic Green Building
Ordinance are as follows:
· The Ordinance only covers city sponsored projects, defined as any new construction or renovation
primarily funded or sponsored by the City, conducted on City-owned property, or managed by City
personnel from design through construction. "City Project" or "Project" shall also include any
Buildings constructed for the City's use under a build-to-suit program or project.
All City building projects with the estimated cost of construction of $3,000,000 or greater in value
shall be designed to meet designated minimum LEEDTM Silver rating as specified in the
Ordinance, or a City-approved equivalent.
· All projects following the LEEDTM rating system shall be registered and certified by the U.S.
Green Building Council.
· TraditiOnal public works and parks projects or projects with the estimated cost of construction, ' of
$3,000,000 or less, shall not be required to achieve a LEEDTM rating.
· Within twelve (12) months of the effective date of this ordinance, the Green Building Compliance
Official shall submit proposed Operational Guidelines to the City Council containing
specifications necessary or appropriate to achieve compliance with the Green Building Practices
stated in this Chapter.
RECOMMENDATION:
Staff recommends that the City Council open the Public Hearing; receive Staff Presentation and
comments from the Public; question Staff and the Public; close the Public Hearing and deliberate; waive
the reading and adopt the Ordinance adding new Chapter 5.61 to the Dublin Municipal Code, Green
Building Practices for City Projects.
oRDINANCE NO. - 04
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF DUBLIN
AMENDING THE MUNICIPAL .CODE BY ADDING A NEW CHAPTER
5.61 MANDATING GREEN BUILDING PRACTICES FOR CITY
PROJECTS
The City Council of the City of Dublin does hereby ordain as follows:
SECTION I: ENACTMENT
The Municipal Code is hereby amended by adding Chapter 5.61 which shall read as
follows:
CHAPTER 5.61 GREEN BUILDING PRACTICES FOR CITY PROJECTS
Section 1. FINDINGS
The City Council of the City of Dublin hereby finds and declares that:
A. The design, construction, maintenance, and demolition of buildings and structures
within the City can have a sighificant impact on the City's environmental sustainability, resource
usage and efficiency, waste management, and the health and productivity of residents, workers,
and visitors.
B. "Green" building design, construction, and operation can have a significant
positive effect on energy and resource efficiency, waste and pollution generation, and the health
and productivity of a building's occupants over the life of the building.
C. Green building benefits are spread throughout the systems and features of the
building. Building "green" can include, among other things, the use of certified sustainable
wood products; aggressive use of high recycled content products; recycling of waste that occurs
during deconstruction, demolition, and construction; enhancement of indoor air quality by
selection and use of construction materials that do not have chemical emissions that are toxic or
irritating to building occupants; modification of heating,, ventilation, and air-conditioning
systems to provide energy efficiency and improved indoor air; use .of water conserving methods
and equipment; and installation of alternative energy methods for supplemental energy
production.
D. The U.S. Green Building Council, developer of the Leadership in Energy and
Environmental Design (LEEDTM) Commercial Green Building Rating System and LEEDT~
Reference Guide, has become a leader in promoting and guiding green building.
E. Requiring certain City projects to incorporate LEED'm green building measures is
necessary' and appropriate to achieve the benefits of green building.
A1-FACH M ENT 1
F. Green design, construction, and operation decisions made by the City in the
construction and remodeling of City buildings result in environmental benefits and cost savings
to the City over the life of the buildings. By calling on the City to include green building
measures in its own facilities, the City Council provides taxpayers a benefit through
environmentally friendly, cheaper to operate buildings and simultaneously helps to. develop
markets for recycled, recyclable, and environmentally sound materials.
G. It is critical to both the economic and environmental health of the City that the
City provides leadership to both the private and public sectors in the arena of energy efficiency
and "green" construction. The most immediate and meaningful way to do this is to include
energy efficiency and green building elements in as many public buildings as feasible.
H. It is in the public interest to address the appropriateness of mandating green
building requirements for private projects separately from, and subsequent to, applying such
requirements to City Projects. Accordingly, unless and until the City Council determines
otherwise, the provisions of this Chapter shall not apply to private sector development.
Section 2. DEFINITIONS
A. "Green Building Practices" means a whole-systems approach to the design,
construction, and operation of Buildings and Structures that helps mitigate the environmental,
economic, and social impacts of construction, demolition, and renovation. Green Building
Practices such as those described in the LEEDTM Rating System, recognizes the relationship
between natural and built environments and seeks to minimize the use of energy, water, and other
natural resources and provide a healthy productive environment.
B. "Building" means any Structure used or intended for supporting or sheltering any
use or occupancy as defined in the Dublin Building Code.
C. "Structure" means that which is built or constructed, an edifice or building of any
kind or any piece of work artificially built or composed of parts joined together in some definite
manner and permanently attached to the ground.
D. "City Project" or "Project" means new construction or renovation primarily
funded or sponsored by the City, conducted on City-owned property, or managed by City
personnel from design through construction. "City Project" or "Project" shall filso include any
buildings constructed for the City's use under a build-to-suit program or project. Traditional
Public Works Projects and Parks Projects are not considered "City Projects" for the purpose of
this Chapter.
E. "Construction" means the building of any building or structure or any portion
thereof.
F. "Renovation" means: (1) a structural change to the foundation, roof, floor, or
exterior of load-beating walls of a facility, or the extension of an existing facility to increase its
floor area; or (2) alteration of an existing facility, such as to significantly change its function,
even if such renovation does not include any structural change to the facility.
2
G. "Initiated" means officially identified and fully funded to offset all the costs
associated with the project as found in the City Capital Improvement Plan.
H. "Conditioned Space" means an enclosed space in a building that is provided with
a mechanical heating/cooling system as defined in the Dublin Building Code.
I. "Estimated Cost of Construction" means the total projected cost of completing a
proposed Project, including fees, design, construction and land.
J. '"LEED Accredited Professional~m'' means an experienced building industry
practitioner who has demonstrated his/her knowledge of integrated design and his/her capacity to
facilitate the LEEDTM certification process on the LEEDTM Professional Accreditation exam. The
exam, administered by the U.S. Green Building Council, tests an individual's understanding of
green building practices and principles, and familiarity with LEEDTM requirements, resources,
and processes.
K. "LEED Rating Systemxw'' means the most recent version of the' Leadership in
Energy and Environmental Design (LEEDTM) Commercial Green Building Rating SystemTM, or
other related LEEDTM Rating System, approved by the U.S. Green Building Council, as
applicable to the Project.
L. "Traditional Public Works Projects" means heavy construction projects, such as
pump stations, flood control improvements, roads, bridges, as well as traffic lights, sidewalks,
bike paths and associated infrastructure on City-owned and maintained property.
M. "Parks and Recreation Projects" means landscape construction projects, such as
sports facilities, play grounds, trails, as well as sports lighting, parking, restrooms and associated
infrastructure on City-owned and maintained property.
N. "The Green Building Compliance Official" means the person who is authorized
and responsible for enforcing this Chapter for any given City project, as designated by the City
Manager.
Section 3. MANDATORY GREEN BUILDING PRACTICES
A. City Projects: All City Projects initiated on or after March 16, 2004, with the
Estimated Cost of Construction of $3,000,000 or greater, shall meet:
"Silver" rating under the LEEDTM Rating System, or a City-approved equivalent.
All projects following the LEED rating system shall be registered and certified by the
U.S. Green Building Council. The Green Building Compliance Official or his/her designee shall
undertake such registration and application for certification.
B. All City Projects initiated on or after March 16, 2004, with the Estimated Cost of
Construction of $3,000,000 or less shall be designed and constructed using as many green
practices as appropriate to the project as specified in the Operational Guidelines. These Projects
shall not be required to be registered and certified by the U.S. Green BUilding Council. The
Green Building Compliance Official or his/her designee shall be responsible for verifying the
appropriate green building componeffts.
C. Traditional Public Works and Parks Projects: The Green Building Compliance Official
shall promptly undertake research to identify suitable mechanisms for applying Green Building
Practices to Traditional Public Works and Parks and Recreation Projects. Within twelve (12)
months of the effective date of this ordinance, the Green Building Compliance Official shall
submit proposed Operational Guidelines to the City Council requiring the application of
appropriate Green Building Practices to Traditional Public Works and Parks and Recreation
Projects.
D. Exemptions: If a City Project has unique circumstances that make compliance with
this Chapter infeasible, the Green Building Compliance Official may grant an exemption as set
forth in the Operational Guidelines.
Section 4. STANDARDS FOR COMPLIANCE
A. The Green Building Compliance Official shall be responsible for the development and
maintenance of Operational Guidelines which contain specifications necessary or appropriate to
achieve compliance with the Green Building Practices stated in this Chapter. The Operational
Guidelines shall be proposed [or promulgated] after securing and reviewing comments from
affected City Departments.
B. The Operational Guidelines proposed [or promulgated] by the Green Building
Compliance Official under this section shall provide for at least the following:
1. Criteria to escalate or lower the $3,000,000 threshold contained in this
Chapter;
2. The incorporation of the Green Building Practices of this Chapter into the
appropriate design and construction contract documents prepared for the
applicable City Projects and Traditional Public Works and Parks Projects;
3. Guidelines specifying how contractor bids or responses to Requests for
Proposals must indicate plans for meeting all applicable LEEDTM or Traditional
Public Works and Parks and Recreation Green Building criteria required under
this Chapter. . All. projects following the LEED rating system shall be required to
have a LEEDTM Accredited Professional on the Project team;
4. Guidelines specifying how green and sustainable practices and products
will be incorporated in the operation and maintenance of City projects;
5. Guidelines specifying how the Green Building Compliance Official will
administer and monitor compliance with the Green Building Practices set forth in
this Chapter and with any rules or regulationd promulgated thereunder, and make
recommendations to the City Council concerning the granting of waivers or
exemptions from the requirements of this Chapter, including Certification of City
Projects.
4
Section 5. UNUSUAL CIRCUMSTANCES
Compliance with the provisions of this Chapter may be waived in unusual circumstances
where the City Council has, by resolution, found and determined that the public interest would
not be served by complying with such provisions.
SECTION 1I: 'SEVERAB[LITY
If any chapter, section, subsection, subdivision, paragraph, sentence, clause or phrase of
this Ordinance, or any part thereof, is for any reason held to be unconstitutional, invalid, or
ineffective by any court of competent jurisdiction, such decision shall not affect the validity or
effectiveness of the remaining portions of this Ordinance or any part thereof. The City CounCil
hereby declares that it would have passed each chapter, section, subsection, subdivision,
paragraph, sentence, clause, and phrase of this Ordinance irrespective of the fact that one or more
chapters, sections, subsections, subdivisions, paragraphs, sentences, clauses, or phrases be
declared unconstitutional, invalid, or effective. To this end, the provisions of this Ordinance are
declared to be severable.
SECTION llI: EFFECTIVE DATE
This ordinance shall take effect and be in force thirty (30) days from and after the date of
passage. The City Clerk of the City of Dublin shall cause the Ordinance to be posted in at least
three (3) public places in the City of Dublin in accordance with Section 36933 of the
Government Code' of the State of California.
PASSED AND APPROVED AND ADOPTED by the City Council of the City of Dublin,
on this __ day of ,2004, by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
MayOr
ATTEST:
City Clerk
CITY CLERK
File #
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: FebruarY 17, 2004
SUBJECT: Civic Green Building Ordinance
Report Prepared By: Joni Pattillo, Assistant City Manager
ATTACttMENTS: 1) LEED: Good.for BusNess, Good for the Environment
2) LEEDTM Rating System
3) State Study: Costs & Benefits of Green Building, Execpt~ve
summary
4) Seattle Project Cost Graph
5) Wall Street Journal: Green-Building Benefits Outstrip Extra
Costs
6) Comp0xison of Green Building Ordinances in the Bay ~ea
7) Proposed City of Dublin Green Building Ordinance
' !
RECOMMENDATION:/1) ' Provide commems and direction to Sm_ffregardin~ theI
proposed Green B~fild~ Or~nm~ce with specific d~re~tion
' regarding the desked level of LEEDTM certification.
2) Direct Staffto malce thc appropriate modifications to ~e
Ordinance, if any, and present ~e Ordinance for ks fi~t'
readin§ ~t fl~e next Coux~ciI Meeting.
FINANCIAL STATEMENT: .... It is possible that this Ordinance will .result in increased costs .for ....
certain capital improvement projects. The precise costs are unlmown and will partially depend 9n the
desired level of certification selected by the City Council. It is estimated that City projects re~luiring
LEEDTM silver certification under the proposed Ordinance could experience cost increases of up to12% of
the total project cost and an additional $20,000 to $40,000 for the LEEDTM application process. ~other
potential outcome might be a need to adjust Development Fees associated with Public Facilities to.
accommodate the estimated increase of 2%..However, green buildings typically result in significhnt life
cycle savings, often exceeding the initial investment by as much as ten times,
DESCRIPTION:
As part of its 2003-2004 Goals and. Objectives, the City Council directed Sta. ffto prepare a green btilding
ordinance. This report provides a description and analysis of green building as well as a comprehen:, 'rye
account of the development and key components of the City's proposed green building Ordinance. ~
COPIES TO: ~.,
ATTACHMENT
H/cc-formslagdastmt. doc ....... ~'--
GREEN BUILDING DESCRIPTION: .
Green building is a whole systems aPPr0ach to the design, Constructi°n and operation of buildings- ~,,from
the early stages of development (e.g. recycling C&D debris) through the final finishes of the buildin~ ('e.g.
using sustainable products).
Conventional design and consU'uction methods can produce buildings that negatively impact the i
envirOnment as well as the health and productivity of the building occupants. These buildings can b~
waste generation, and
expensive to operate and contribute to excessive resource and energy consumption, '
pollution.
By contrast, green building provides a means for mitigating the undesirable environmental impacts if
conventional building methods. This is accomplished by employing building materials and~methodd:~, that
promote natural resource conservation, energy efficiency and good indoor air quality. ~ .
Although sustainability is a global issue, building plans are approved and constructed locally, and it Is at
this level that cities may have the greatest impact. The adoption of the proposed Green Building
Ordinance will formalize the C~ty of Dubhn green building practices and define a process for des/
construCtiOn and operation of certain city buildings. In addition, adoption of the Ordinance will fur aer
'demonstrate the City's commitment to environmental, economic,' and social stewardship, yielding cz,st
savings to the City taxpayers through reduced operating costs for City facilities, providing healthier ~ork
environments for employees, and contributing to increased conservation of natural resources.
U.S. Green BUilding Council and LEEDTM
The United States Green Building Council (USGBC) is a national nonprofit organization that was f~rmed
in 1993 Its owin membership includes representation from organizations across the building industry,
including architecture and engineering firms, builders, manufacturers, government agencies, real estate
developers, universities, and others. USGBC develops industry standards, design practices and greeN
building education. It is the developer and administrator of the Leadership in Energy and Environmental
Design (LEEDT~r) Green BUilding Rating System. A description of the LEEDTM rating system is included
in the article LEED: Good for Busines& Good for'the Environment (Attachment 1). The complete
LEEDTM rating system is also included as Attachment 2.
LEEDTM was developed t° define "green building" by providing a standard for measurement. The
LEEDTM Rating System defines "green building" as a building that is designed to minimize envirorr nental'
impacts in the following ways:
1. Sustainable Sites - i.e. building with access to mass transit and reducing stormwater mn-off
2. Water Efficiency- i.e. water efficient landscaping
3. Energy and Atmosphere - i.e. reducing energy consumption in the buildings .
4. Materials and Resources - i.e. designing for the storage and collection ofrecyclables ani
construction and demolition waste management
5. Indoor Environmental Quality- i.e. reducing the quantity of indoor air contaminants, such as
Volatile Organic CompoUnds (VOC), and increasing daylighting in the buildings
·
LEEDTM uses existing, proven technologies to guide commercial, public and.instituti°nal. . . buildings, ii. ~ is
now the most widely used green building rating system nationally. Many jurisdictions ~ncludmg Alameda
County, Berkeley, Pleasanton, San Jose, San Francisco, San Mateo County, Santa Monica, Portland,' and
Seattle have developed their green building programs using LEEDTM as a standard or guide.
Several projects in Alameda County, including: me'Alameda County Hall of Justice and the Alamed~
County jUVenile Detention Center, Pleasanton Fire Station, Berkeley Fire Station, and two Universit~ of
California Student Housing projects, are being designed using LEED~r~ as a standard. LEED
performance-based, with four levels of certification (Certified, Silver, Gold and Platinum). Certification
is solelY perfOrmed bY USGBC.
COSTS AND BENEFITS OF GREEN BUILDING:
Fiscal ImRact
The State of California recently released the most comprehensive analysis of the financial costs and
benefits of green building titled The Costs and Benefits of Green Building (October 2003) (Attachm.l.ent 3).
The stUdy reported that the average additional cost for substantial green building design was slightl~ less
than 2% (of the building's total design and construction cost), which translates to approximately $3-~5/sf.
'This conclusion was made after a survey of 33 LEED~ buildings.' The majority of the additional c6, st is
attributed to the increased architectural and engineering design time necessary to integrate sustainable
building methods into projects. The earlier green building gets ine°rPorated into the design proeess~ the
loWer the cost.
Addressing each of these factors can minimize additional capital costs:
Identify projects to be LEEDTM Certified at the establishm_en~.0fthe project budget
Include LEEDTM requirements in RFQs and RFPs
Use LEEDTM early in the design process
"· Train project managers in LEEDan~ management skills.
It is imp°rtant to Point out that the cost of green buildings will vary significantly depending on the s ~eeifie
project goals. While there are many significant benefits that can be included in aproject at no additional
cost (orientation, low VOC paints, recycled content carpet, etc.), some features w111 cost. more. Es_ti~n. ates
for additional initial costs are as !ow as 0.to 2%..A'LEED~ Study conducted for the C~ty of Portla~d
indicated that green building impact on the budget is small - from 2.2% extra cost to 0.3% savings.
The City of seattle found that after a 3-Year implementation period, the incremental cost for meeting
LEEDX~a'Silver dropped from 6% to 0.1% for small projects and from 4% to none for large projects!
(Attachment 4).
While building to LEEDTM standards may result in additional funding for initial design and construe~tiOn,
LEED~ buildings are more economical than conventional buildings (i.e.: non green) over their lifetime.
Energy and water efficient buildings can reduce operating costs significantly. Use can be cut to less than
half of a conventional building. Additionally, healthy indoor environments can increase employee
productivity and reduce absenteeism.
The State report found that the 20-year Net Present Value of the life-cycle savings in energy, emissi)ns,
water, waste, and commissioning for a'LEEDTM Certified or Silver Building averaged $15.98/sf, w~ le the
20-year Net Present Value for improved productivity and health is $36.89/sf.
The report cOncluded that a minimal upfront investment of about 2% of construction costs typicallyiyields
life cycle savings of over ten times the initial investment. A recent article in the Wall Street Journal'
supports the report's findings (Attachment 5).
In addition to potential project cost increases, other important green building considerations incl~de the
poSSibility of limited product avaitabilit~ and material selection.and longer project completion sched~ules.
The product market for green building materials, including 'recycled content Products, whi. still
somewhat limited, has improved dramatically over the past several years. It is anticipated that the ,market
will continue to mature as more organizations adopt green building policies, resulting in even greater
choices for green building products. It is also important to note that LEEDTM is flexible and allo~vs for
many options regarding which green building elements to incorporate in a given project. LEEDTM is~ based
on a point system, so if it becomes apparent that a SPecific product is unavailable, points could be ~amedi J
by "greening" other areas of the project.
True green building takes a holistic approach to a building and requires involvement from site planning
and conceptual design through construction. I~ a project is identified as a green building from the gtart, it
is more likely that the project would be completed in the same amount of time as a conventional project.
. ro'ect dela s can 'be more likely and more significant if the project is changed midway through
However j y ~ . ~
desi f~rPexam le Project components such as site orientation, daylighting, Heating, Ventitatmns and
gn p . ·
Air Conditioning (HVAC), windows etc. are integral components to designing an efficienX building.. If one
of these elements is changed, it could create the need for a major redesign because of how the comp.'Onents
are interrelated. Green building will require more discussion and goal setting at budget development stage
of the project in order minimize changes after the conceptual design has been approved.
While not as easily measurable as the life cycle savings, other green building benefits sho~d be
cOnsidered including environmental (conserving of energy, water and other natural resources; imp~roving
air and water quality and a reducing of solid waste) and community benefits (minimizing strain o,n local
.. infrastructure, strengthening established goals related to increase density, mixed use and transit-orientedl
development, improving stormwater and erosion control} increasing bicycle and pedestrian acc?s and
contributing to Community health, vitality and aesthetics).
ACCOMPLISltMENTS ~ PROCESS: . '
The following section Provides a brief history of the city's efforts related to green building includin~ the
steps leading to the development of the proposed green building Ordinance.
Construction and Demolition Ordinance . .
On February 15, 2000, the Dublin City Council adopted a Construction and DemolitiOn Ordinar~ee, the
first of its kind in Alameda County, which was based on a model developed by the Alameda County
Waste Management Authority (ACWMA). The purpose of the Ordinance is to require maximum ~easible
· recycling at new 'construction sites, and salvage· and reconstruction for remodeling and de~.,.olition
projects.
The City's Ordinance has been used as a model for other jurisdictions throughout the State and is,one of
the few that includes.a performance security requirement. The Ordinance has been eXtremely sucCessful
and has had a dramatic impact on the City's diversion rate. In 1999, the City had a diversion rate {f 33%.
Thanks in large part to the success of the Ordinance; the City's diversion rate for 2001 was 50%.
Fire Stations 17 and 18 Construction Grant Award for Utilizing Green Building Jl~ractices
'The City of Dublin Was awarded $100,000 by the' ACWMA that was equally divided for the constr~ction
of the two fire stations to incorporate green building materials and practices.
The City of Dublin and Eden Housing, t? developer of the.C.ity.of.D.u~blin?,,.Aff~°rd.a~ble, S~eni?r, ,Houiing
project, were selected through a competitave process to pammpate in me lvxum-ramny Axxorttame
Housing Green Building Design Assistance Program from ACWMA. A $5,000 grant was awarded
help subsidize Eden Housing's participation in the development, of Multi-Family Green Building i
Guidelines.
City of DUblin's Housing Element
Included in the City's State-approved Housing Element of the General Plan is a policy on the promoiion
of energy efficiency in new projects. The elements that support this policy are:
"' .Continue to implement the City's Construction and Demolition Recycling Ordinance;
- Continue to provide on-site training for City Building and Planning Staff on !Green
Building techniques.
- Continue to review proposed developments for solar access, site design techniques, ahd use
of landscaping that can increase energy efficiency and reduce lifetime energy costs.x~ 'thout
significantly increasing hoUsing productions costs.
- Provide access to information on energy conservation and financial incentives (tax credit,
.utility rebates, 'etc.) through public information to be provided at the City's public c ~6unter,
on the.City's Web site, at public libraries and community centers.
Training and Educational :Opportunities
· ..The City, in cooperation with the'ACWMA, has coordinated several green building workshops to e~ducate
Staff and developers on Green Building practices. The workshOps have included a recent Tri-~alley
Builders workShop on Green Building Initiatives and a Tri-Valley Building Inspectors Workshop on
Green Points. Additionally, several Staff members have attended the LEEDTM. ~aining
inspecting
program, i
Green Building }York Group ~ . . ·
The process of developing a green building ordinance began with the fo..rmatton of a green b~d~n~ wo.r,k
group comprised of Staff members from Community Development, Public Works, Parks aha tzommumty
Services, and the City Manager's Office as well as Staff and consultants from the ACWMA. Th~ group
began by reviewing several green building ordinances from Bay area jurisdictions including the ,:City of
Pleasanton and Alameda County and the ACWMA Civic Green Building Model Ordinance. A :.matrix
comparing the various ordinances is included as Attachment-6 ....
PROPOSED CIVIC GREEN BUILDING ORDINANCE:
Staffhas developcd an ordinance (Attachment 7) that defines and sets thresho!ds £or incorporath~g ~reen
building practices in civic projects. The key elements of Dublin's proposed Civic Green Building i
Ordinance are as follows:
· The Ordinance only covers City sponsored projects, defined, as any new construction or renovation~ ..
nmanly' ' fun. ded or sponsored by_ the City, conducted., on City-owned. property,, or managed, by! C~ty
~ersOnnel from design throUgh construction. "C~ty Project" or '~Project" shall also melu~e any
Buildings constructed for the City's use under a build-to-suit program or project.
· All City building projects with the estimated'cost of construction of $3,000,000 or greater i~ value |
shall be designed to meet a designated minimum LEEDTM rating as specified in the Ordin~ ~ce, or
a City-approved equivalent. Staffhas included three options for the. Council to consider:
LEEDTM "Certified"
· LEEDTM "Silver'
· LEEDTM "Certified", and strive for LEEDTM "Silver"
· All projects following the LEEDTM rating system shall be registered and certified by the U.S
Green Building Council.. '
· Traditional public works and parks projects or proj. ects with the.estimated ,cost of constmctiOn of
$3,000,000 Or less shall not be required to achieVe a'LEEDTM rating.
· Within twelve (12) months of the effective date of this ordinance, the Green Building Comp!iance
Official shall submit proposed Operational Guidelines to the City Council containing
specifications necessary or appropriate to achieve compliance with the Green Building Pracfi, ces
stated in this Chapter.
DISCUSSION OF KEY ELEMENTS ,
An explanation of the work group's discussions and decisions related to the key components liof the
Ordinance is provided below.
Building types.
The work group quickly realized that there were two separate elements of a green building progran~l: civic
buildings and private development. The'work group concluded that it should first focus on develop~ing an
ordinance that would apply to civic buildings such as upcoming Emerald Glen Park Recreation ~Center.
Once completed, the City could investigate options for private development. One of the most co ,m,,¢ellmg
reasons for developing an ordinance limited to civic buildings, was the'idea that the City should "~ead by
example." If the City is ever to' require developers to incorporate, green building practices. ~, their
developments, the work group felt that it was important that the City first impose a similar, ~f no~ more
aggressive requirement on itself.
AdditionallY, the ACWMA Model Ordinance was developed for civic buildings and it was agreed that the
model Ordinance would be used as a starting point for developing the City's Ordinance. The A( ZqMA
also.has a design assistance and grant program in place to assist member agencies in implementin green
building practices and incorporating sustainable products into public facilities.
LEED XM Certification Rating
The proposed Ordinance is based on LEEDTM because Staff believes the. nationally recognized L] ~ED~a
rating system to be the most comprehensive rating system available and it is the standard used b~ other
jurisdictions in the Bay Area. The proposed Ordinance includes three options for the Council to e~nsider
regarding the level of LEEDTM certification that will be required for City Projects.
LEEDTM is a design rating system with 69 possible points· For ·classification as a LEEDTM b.~ilding,
buildings must satisfy seven prerequisites and a minimum number of points for the desired 1,evel of
certification. Four levels of green building certification are aWarded based on the total number i~credits
earned in each of six Categories: Sustainable sites, Water Efficiency, Energy and Atmosphere, Mhterials
and Resources, Indoor Environmental Quality and Innovation and Design Process. To achi,'eve a
"Certified" rating, projects must meet all of the prerequisites and earn a minimum of 26 points, lwith a
minimum of 33 required for "Silver", 39 for "gold', and 52 for "platinum".
'The comparison of ordinances matrix indicates the requirements for various jurisdictions, i MoStl2f~[~
jurisdictions require either a certified or silver rating. Staff believes that a certified rating cohld be
achieved with a few modifications to existing procedures such as. hii'ing" an architect that .is L~EDTM
certified. Several of the City's recent projects, while not measured or certified using the LEEDTM
standard, would most likely have come close to achieving a certified rating.
In order to achieve.a silver rating, more effoi't would need to be devoted to the project during the ~deslgn
phase and more green building elements would need to be included. Many Of the points in thel rating
system can be earned at little or no cost. However the more points that are required, the more like[Iy that
the green bUilding components assodiated with the those, incremental points will add to the cost[of the
project. It is impossible to predict the exact fiscal impact of achieving a certain LEEDm rating, hqwever
studies cited pre~riously ih the Staffreport indicate that a silver rating ~ould be achieved with lesslthan a
2% cOst increase.
The proposed Ordinance includes three LEED?M certification options for the Council to co,~sider:
Certified; Silver; or minimum certified and strive for Silver. staff requests direction f~om th.e C~ouncil
regarding the desired level of certification required for City projects. ! ·
Threshold ' ·
The LEEDm rating system was developed and is intended for large new. construction andI major
renovation projects. With this understanding, Staff completed a thorough analysis of the City's Capital
Improvement Program in order to .determine the ,min.'imm. threshold tha~ shog!d, be..met..in, order.t0 ~equire
LEEDx~a certification. Staff wanted to establish a threshold that would capture all of the major City
projects that would be appropriate to require a LEEDa~ certification. The analysis revealed !that a
threshold of $3. million would accomplish this goal. The proposed Ordinance states that all City ~rojects
with the estimated cost .of construction of $3 million or greater in value shall be designed to meet a
designated minimum LEEDTM rating. The current projects that wOUld require LEEDTM certifieatiofi under
the proposed Ordinance include the following:
· Emerald Glen Park Aquatic Center
· Emerald Glen Park Recreation Center
· Emerald. Glen Park Community Center
· Community Theater
There are many City projects with an estimated construction cost .of less than $3 million, however none
would be appropriate for LEED?~ certification due to the nature and size of the projects. Additionally,
there are many park and street projects that are over $3 million but would not require LEEDTM
certification under the proposed Ordinance because .they do not fit in the Ordinance's 'definil[ion of
construction and would not be appropriate for LEED
Ot~erational Green Building Practice Gttidelines
All City projects not-required to achieve LEEDz~v~ certification, whether due to the value threshold o~r the
nature of the project will be required to incorporate Green Building Practices in the project. Upon
adoption of the Ordinance, Staffwill work to develop an Operational Green Building Practice Guidelines
that will specify appropriate green building practices for all City projects that do not qualify for LEEDTM
certification, i
Additionally, The Operational Green Building PraCtice Guidelines will include important implementation
assistance for Staff regarding items such as the development of criteria to escalate or lower the $3 million
dollar threshold, appropriate language for projects specifications and requeSt for qualificati°ns, add how
the Green Building Compliance Official will administer and monitor compliance with the OrdinanCe. The
Orctinance requires the Guidelines to be developed within twelve months of adoption of the Ordinmce.
NEXT STEPS
Once the work related to. civic projects is completed, the recommended next steps if the Council desires to
have the Green Building program to be expanded to included private development it should identi~ this
an item for consideration during the upcoming Goals and Objectives Process.
REcoMMENDATiON: ·
Staff recommends that the City Council review'the proposed Ordinance and attached documents. and~.
provide comments to Staff with specific directions regarding'the' desired level of LEEDTM certificatitbn. It
is recommended that the Council. then direct Staffio make the appropriate modifications to the Ordinance.
for presentation and first reading at the next City Council Meeting.