HomeMy WebLinkAbout4.16 G&O and CIP Status Report
CITY CLERK
File # D[]~~-[~]O]
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: September 19,2006
SUBJECT:
Fiscal Year 2006-2007 Goals & Objectives Status Report & CIP
Schedule
Prepared by: Richard C. Ambrose, City Manager
ATTACHMENTS:
1.
2.
Goals & Objectives Status Report
Capital Improvement Program Schedule
RECOMMENDATION:
/J}J.0
! 'I Receive the Report
FINANCIAL STATEMENT: None
DESCRIPTION:
On June 13,2006, the City Council adopted the Goals & Objectives Program for Fiscal Year 2006-2007.
In order to keep the City Council abreast of Staff progress towards the objectives assigned by the City
Council, Staff has prepared a bi-monthly status report for the period ending August 31, 2006. As of that
date, a total of 8 of 96 objectives (7%) have been completed. With respect to high priority objectives, a
total of8 out of84 (10%) have been completed.
In June 2006, the City Council approved a Five Year Capital Improvement Program (CIP) Update for
Fiscal Years 2004-2009 and appropriated funds for Fiscal Year 2006-2007. The attached CIP schedule
lists 48 projects that received funding in Fiscal Year 2006-2007. The schedule shows the status for each
project and also identifies an estimated start and completion date. The schedule only includes a time frame
for those projects that are funded in Fiscal Year 2006-2007. Subsequent phases and future projects
included in the Five Year CIP, but not funded in Fiscal Year 2006-2007, are not listed on the schedule. An
additional schedule has been included in this update, which provides more detailed information for the
Eastern Dublin Arterial Street Improvements project.
RECOMMENDATION:
Staff recommends that the City Council receive the report.
COPIES TO:
HI cc- fo rm sl agdastmt.doc
ITEM NO. ~& \ b
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
MASTER
:i
~
i
=+
-3.:...
(S"'
# COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS
PRIORITY RESPONSIBLE GOAL START COMPLETION
I. GENERAL GOVERNMENT
A. ADM1NISTRA liON
1. High Pattillo 2005 Conduct programming study for Civic Center. Sept 2005 Nov 2006 UNDERWAY; Staff reviewing documents
associated with programming study.
2. High Pattillo/Silver 2006 Prepare and implement mandatory ethics training for legislative Oct 2006 Feb 2007 UNDERWAY; First of two trainings will occur
bodies. Oct 2006 and second in Feb 2007.
3. High Ambrose/Silver 2006 Conduct comprehensive update to City's Municipal Code August 2006 June 2008 UNDERWAY
4. High Rankin 2006 Develop Technology Master Plan for City of Dublin Sept 2006 Mar 2007 UNDERWAY; Scheduled to release RFP in
Organization. September and award contract by November;
Report to be completed by February 2007.
5. High Pattillo 2006 Develop comprehensive community-wide diversity plan. Jul 2006 Apr 2007 UNDERWAY
ADDITIONAL OBJECTIVES (ADMINISTRATION)
B. F1NANCE
1. High Rankin 2001 Evaluate the need to replace the City's accounting system. Sept 2006 June 2007 UNDERWAY; Scheduled to release RFP in
September; A ward contract December; Report to
be completed by March 2007.
ADDITIONAL OBJECTIVES (FINANCE)
1. Ambrose 2005 Undertake Voter Opinion Research to determine community Dec 2005 TBD NO PROGRESS; Project deferred due to
support for tax increase for Recreation! Aquatic Complex and evaluation of other financing alternatives; See
Dublin Historic Park. Objective III A. 2.
C. INTERGOVERNMENl AL RELATIONS
High Ram 2003 Work with cities in the Tri Valley Area to develop and maintain July 2005 June 2007 UNDERWAY; Clearing House opened in
affordable housing opportunities, and publicize and coordinate September 2005; Permanent executive director
the regions housing needs. selected.
High Ram 2004 Participate in Tri Valley Vision Project. July 2003 Ongoing UNDERWAY; Staff continues to work with the
Tri-Valley Business Council on the Preserving
Prosperity Project as well as other issues of
regional significance.
\)
~)
p
~~~,
,~I
~/
Page 1
l)'\
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHL Y REPORT AS OF 08-31-06
# COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS
PRIORITY RESPONSIBLE GOAL START COMPLETION
ADDITIONAL OBJECTIVES (INTERGOVERNMENTAL RELATIONS)
D. PUBLIC RELATIONS
1. High Carter 2006 Produce a City wide Newsletter. Aug 2006 Nov 2006 UNDERWAY
2. High Carter 2005 Plan and implement 25tn Year Cityhood Celebration. Feb 2006 Feb 2007 UNDERWAY; Status report to Council
September 2006.
3. High Holman 2006 Evaluate the need to improve the Citizen and Organization of July 2006 Oct 2006 UNDERWAY; Council Ad Hoc Committee met;
the Year Programs Report scheduled to go to Council in October
2006.
4. High Carter 2006 Include City calendar in 25th Year Celebration July 2006 Nov 2006 NEARLY COMPLETE
ADDITIONAL OBJECTIVES (PUBLIC RELATIONS)
E. CONTRACT ADMIN1STRA TION
1. High Thuman 2006 Crossing Guards Contract Evaluation. Feb 2007 May 2007 NO PROGRESS
2. High Ram 2006 Building & Safety Contract Evaluation. Feb 2007 May 2007 NO PROGRESS
3. High Pattillo 2006 Fire Service Contract Evaluation. Feb 2007 May 2007 NO PROGRESS
ADDITIONAL OBJECTIVES (CONTRACT ADMINISTRATION)
II. COMMUNITY DEVELOPMENT
A. PLANNING
1. High Ram/Lowart 2002 Develop Historic District Master Plan for Dublin Blvd/Donlon June 2003 Aug 2006 COMPLETE
property and implement Specific Plan, if required.
2. High Ram 2004 Implement residential planned development and investigate Dec 2002 TBD UNDERWAY; Building permits issues for EAR,
opportunities to create a new village in Eastern Dublin Transit DR Horton and Avalon Bay; Metropolitan in plan
Center. check; Village Green in plan check.
3. High Ram/Lowart 2003 Complete General Plan Amendment on Dimanto Property. TBD TBD UNDERWAY; No application submitted.
4. High Ram 2003 Complete GP A Study on the Transportation Corridor Right-of- Jan 2006 Mar 2007 UNDERWAY
Way.
5. High Ram 2003 Complete Review of Moller annexation and General Plan July 2004 Feb 2007 UNDERWAY; EIR and DSRSD water analysis
Specific Plan Amendments. underway.
6. High Ram 2001 Complete Parks Reserve Forces Training Area (Camp Parks) TBD TBD UNDERWAY; Waiting for Army to select Master
General Plan and Specific Plan Amendments. Developer.
Page 2
.~
~
~
---
(f\
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
# COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED
PRIORITY RESPONSIBLE GOAL START COMPLETION
7. High Ram 2006 Prepare Community Design Element of General Plan Aug 2006 July 2007
8. High Ram 2006 Update Downtown, West Dublin BART and San Ramon Dec 2006 Mar 2008
Specific Plans into one comprehensive Plan that addresses the
entire Downtown Area.
9. High Ram 2002 Complete Scarlett Court Specific Plan. Sept 2006 Feb 2007
10.
High
Ram
2006
11.
High
Ram
2006
12. Medium Ram 1996
13. Medium Ram 1996
ADDITIONAL OBJECTIVES (PLANNING
1. Ram 2006
STATUS
UNDERWAY; Request for Proposals sent to
consulting firms, estimate contract award in
October 2006.
NO PROGRESS; Waiting to start after
Community Design Element is underway.
Complete review of Redgewick Annexation of General Plan and TBD
Specific Plan Amendments.
Hold study session with Planning Commission to discuss how Feb 2007
Dublin Blvd will look and feel from Schaefer Road to Fallon
Road.
Update City's General Plan.
Develo City Com rehensive Telecommunications Policy.
TBD
UNDERWAY; Proposals received from
consultants for design work, estimate contract
award in September 2006; Land Use analysis
postponed until Camp Parks planning completes.
NO PROGRESS; Developer is not ready to
submit proposal.
NO PROGRESS
June 2007
NO PROGRESS
NO PROGRESS
Update Historic Village Area Specific Plan by adding properties
to the Specific Plan area.
NO PROGRESS
3.
High
Ram
2006
4.
High
Ram
2006
5.
Medium
2003
Ram
1m lement First Time Homeowner Program
Complete evaluation of the potential renovation!redevelopment
ofthe Arroyo Vista Housing site.
UNDERWAY; Pro am to begin in October 2006.
UNDERWAY; Developer team selected for
redevelopment of site; Staff working with HOD for
disposal of HUD property as well as securing
Section 8 vouchers.
UNDERWAY; Attending meetings on
development ofRHNA methodology.
Work with ABAG to ensure that the Regional Housing Needs Jun 2006
Allocation process addresses City of Dublin housing needs in an
equitable manner
Process five (5) First Time Homebuyer Loans and make Oct 2006
progress report to City Council.
Revise Density Bonus Ordinance Jul 2003
Jun 2008
Jun 2007
NO PROGRESS
Sept 2006
UNDERWAY; Study sessions are being held with
Planning Commission.
Page 3
\>-1
C)
~
-..
\J\
I. Prepare Universal Design Ordinances for adoption as an
amendment to Building Code Requirements.
2. High Shreeve 2006 Conduct study to determine amount of construction taking place Sep 2006
without building permits to determine if an enhanced building
permit compliance program is needed.
3. Hi h Shreeve 2006 1m lement real-time electronic field ins ection system. Jun 2007
ADDITIONAL OBJECTIVES (BUILDING & SAFETY)
# COUNCIL PERSON
PRIORITY RESPONSIBLE
ADDITIONAL OBJECTIVES (HOUSING)
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
PROPOSED OBJECTIVE FOR ACCOMPLISHING
GOAL
ESTIMATED
START
ESTIMATED
COMPLETION
STATUS
Jun 2007
UNDERWAY
Jun 2008
NO PROGRESS
Develop Geologic Hazard Abatement District (GHAD)
standards for the formation of the Schaefer Ranch and Fallon
Villa e GHADs.
ADDITIONAL OBJECTIVES ENGINEERING)
2.
High
2006
Foss
3.
High
Foss
2003
Work with property owner of Ralph's Grocery store to identify
replacement alternatives.
Sept 2006
COMPLETE; New tenant to be 99 Ranch Market;
Lease executed; 99 Ranch is preparing to take
possession of the premises; Expected to open by
May 2007.
UNDERWAY; City Council to hear request to
amend Downtown Specific Plan to allow
additional development on site.
UNDERWAY; Staff is processing building
permits and is working with potential tenants for a
new 17,500 s.f. retail building.
Work with Dublin Honda on development options for Amador July 2006
Plaza site.
June 2007
Work with Dublin Place Shopping Center to facilitate new July 2003
improvements to the Center.
June 2007
Page 4
~..
C'>
"",:..
{'"
..i t,
\
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
#
COUNCIL
PRIORITY
High
PERSON
RESPONSIBLE
Foss
YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING
GOAL
Work with Dublin Chamber of Commerce to create a program
to recognize Dublin businesses through events in local papers,
City Newsletters, websites, etc.
ECONOMIC DEVELOPMENT
2006
ESTIMATED
START
Sept 2006
ESTIMATED
COMPLETION
June 2007
STATUS
4.
NO PROGRESS
1. Lowart 2005 Undertake development of design and construction documents Apr 2005 UNDERWAY; Design development complete;
for new Community Center at Shannon Park. Construction documents in ro ess.
2. High Ambrose/Lowart 2005 Undertake development of design and construction documents TBD NO PROGRESS; Pending evaluation of
for new Recreation Center/Aquatic Center Complex at Emerald public/private partnership.
Glen Park.
3. High Lowart 2006 Conduct in-depth community needs assessment and opinion Sept 2006 Dec 2007 UNDERWAY; Draft RFP to be presented to
survey of Department programs and services, and develop a Council Oct 2006.
Strategic Plan for Department programs and services.
4. High Lowart 2006 Prepare an update to the Parks and Recreation Master Plan. COMPLETE
5. High Lowart 2006 Develop and implement four (4) family-oriented July 2006 June 2007 UNDERWAY; Dates have been set for all events;
programs/events. First will be Outdoor Movie night in September at
Emerald Glen Park; Remaining events will be
durin spnn and early summer 2007.
6. Medium Lowart 2004 Work with EBRPD to complete negotiations for land acquisition Dec 2002 TBD NO PROGRESS; Property owner not interested in
in the western hills for an en S ace Area. selling land at this time.
7. Medium Lowart 2004 Identify and secure sources of funding for land acquisition in the July 2004 TBD UNDERWAY; Although property owner not
western hills for an Open Space Area. interested in selling land at this time; Altamont
Open Space funding available.
8. Medium Lowart 2004 Upon completion of land acquisition in the western hills, TBD NO PROGRESS
complete an Open Space Master Plan and appropriate CEQA
documents.
9. Medium Lowart 2004 Closely monitor development projects Citywide to identify July 2004 TBD UNDERWAY
otential sites for a unique aSSlVe ark/recreation facility.
10. Medium Lowart/Thuman 2006 Explore the feasibility of establishing a Police Activities League TBD NO PROGRESS
(PAL) program in partnership with Dublin Police Services. If
feasible, establish PAL non-profit organization and Board of
Directors.
Page 5 U\
~
, )
.
(j'1
\
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
#
COUNCIL PERSON YEAR
PRIORITY RESPONSIBLE
Medium Lowart 2004
ESTIMATED
START
TBD
ESTIMATED
COMPLETION
STATUS
NO PROGRESS; Dependent on School District.
11.
Undertake a site master plan, programming and financial
feasibility study for the Dublin Historic Park including DHP A
land/cemetery feasibility study.
2. High Lowart 2005 Coordinate grand re-opening of Murray Schoolhouse to COMPLETE
commemorate the 150th anniversary of the Schoolhouse upon
com 1etion of the exhibit restoration ro" ect.
3. High Lowart 2004 Work with Ulferts on the installation of public art as a condition COMPLETE
of ro"ect a roval.
4. High Lowart 2002 Work with Dublin Fine Arts Foundation to complete Art in the Sept 2002 Sept 2007 UNDERWAY; Recommended for approval by the
Parks projects for Bray Commons Neighborhood Park. Heritage & Cultural Arts Commission and Parks
& Community Services Commission; Presentation
to City Council September 2006.
5. High Lowart 2004 Work with the developer to locate significant works of art in July 2004 TBD NO PROGRESS; Proposed artwork for Village
two key places of the Dublin Transit Center, the Village Green Green deferred by Council until 25% occupancy
Center and the "Iron Horse" Plaza. of Site B; No occupancy to date; Iron Horse Plaza
timeline TBD.
6. High Lowart 2006 Facilitate the selection of public art as a condition of approval July 2006 Jun 2007 UNDERWAY
for five (5) private development projects which currently have
land use entitlements.
7. High Lowart 2006 Research and submit new application for Murray Schoolhouse Aug 2006 Dec 2006 UNDERWAY; New application to be submitted
to be laced on the National Register of Historic Places. by December 2006.
8. High Lowart 2006 Pursue accreditation for the Heritage Center through the Sept 2006 Mar 2008 UNDERWAY; Phase I Museum Assessment
American Association of Museums. Program completed April 2006; Phase II
application for Public Dimension assessment due
by February 2007; (Process takes approximately
one year to complete from application submittal
date).
9. High Lowart 2006 Develop a Teen Apprentice Camp for the youth at the Heritage Mar 2007 Aug 2007 NO PROGRESS
Center.
Page 6 is',,
(J.
l>
0"\
#
COUNCIL PERSON YEAR
PRIORITY RESPONSIBLE
High Lowart 2006
10.
11.
High
Lowart
2006
12.
High
Lowart
2006
13.
14.
High
Medium
Lowart
Lowart
2006
2004
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
PROPOSED OBJECTIVE FOR ACCOMPLISHING
GOAL
Develop a year-round Children's Theatre program.
Submit application for California Cultural Historic Endowment
grant for Dublin Historic Park Project.
Coordinate one (1) new visual arts exhibit at the Civic Center,
Senior Center, or Library.
Expand program activities and hours of Heritage Center.
Work with BART to incorporate high quality artwork as part of
the West Dublin BART Station Project.
15. Medium Lowart 2004 Implement Phase II of the Downtown Public Art/Bus Shelter
Project.
ADDITIONAL OBJECTIVES HERITAGE & CULTURAL ARTS
ESTIMATED
START
June 2006
ESTIMATED
COMPLETION
June 2007
STATUS
Jan 2006
TBD
UNDERWAY; Two summer theatre camps
completed in July/August 2006; Children's
Musical Theatre program offered in Fall 2006 at
Nielsen School.
NO PROGRESS; Application details have not
been released by the State.
NO PROGRESS
Jan 2006
June 2007
July 2004
TBD
COMPLETE
UNDERWAY; Design will include area for
Public Art; Developer has no funding available to
include Public Art in project.
NO PROGRESS; Not funded in Fiscal Year
2006/2007.
Jul 2006
Jun 2007
UNDERWAY; Continued contact with Ford
Motor and "Driving Skills for Life" Program.
UNDERWAY; Awaiting space/facilities
expansion evaluation prior to proceeding.
UNDERWAY; Relationship developed with
Construction Industry Crime Prevention Program
(CCIP); Preliminary discussions with Livermore
and Pleasanton Police.
UNDERWAY; Curriculum review in progress.
1. High Thuman 2004 Develop a teen driver safety/education program. Aug 2004 Jan 2007
2. High Thuman 2006 Formalize volunteer program to enhance community/police Aug 2005 Jun 2007
interaction and to support police operations.
3. High Thuman 2006 Explore the feasibility of a multi-jurisdictional enforcement Aug 2006 June 2007
team to help reduce commercial burglaries in the Tri- Valley
with a focus on construction related theft.
4. High Thuman 2006 Partner with the Dublin Unified School District to provide a safe Sept 2006 May 2007
school environment by conducting classroom safety training for
teachers.
5. High Thuman 2006 Increase DUI awareness and education through the performance Aug 2006 June 2007
of three (3) DUI Checkpoints, pending the award ofOTS grant
funding.
Page 7
UNDERWAY; OTS Grant was not awarded; DUI
Checkpoints will be completed with assistance of
other agencies; No dates set.
~
+-,
,..
~
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
#
COUNCIL
PROPOSED OBJECTIVE FOR ACCOMPLISHING
GOAL
ESTIMATED
START
ESTIMATED
COMPLETION
STATUS
2006 Conduct open houses at each fire station with emphasis on self Sept 2006 Mar 2007 UNDERWAY; Scheduled for October for all Fire
preparedness for disasters. Stations; Open house scheduled for St. Patrick's
Day pancake breakfast.
2. High Pattillo 2006 Conduct fire safety outreach for businesses relative to Sep 2006 Jun 2007 UNDERWAY; Curriculum being reviewed.
emergency preparedness.
3. High Pattillo 2005 Implement the Auto-Pulse Resuscitation System and present July 2005 Jun 2007 UNDERWAY; Awaiting results from County
data and recommendations on the effectiveness of the system. Medical Directors special study.
2.
3.
High
High
Carter
Carter
Identify and secure location for more adequate Emergency
Operations Center.
2006 Conduct City Council Disaster Training.
2006 Conduct citywide disaster exercise.
Nov 2005
Jun 2007
UNDERWAY; Consultant selected to conduct
programming study for Maintenance/EOC facility.
Training to be scheduled in January 2007.
Exercise is scheduled in April 2007 in conjunction
with other County disaster exercise.
COMPLETE
Sep 2006
Sep 2006
Jan 2007
Apr 2007
4.
High
Pattillo
2004 Provide "Train the Trainer" course and materials to Dublin
Unified School District for school disaster training.
DISASTER PREPAREDNESS
Jul 2005
July 2006
Page 8
\;)()
<;,;
~
'-.
\1"
\
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
# COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS
PRIORITY RESPONSIBLE GOAL START COMPLETION
E. WASTE MANAGEMENT
1. High Carter 2006 Conduct audit of exclusive and non-exclusive solid waste Nov 2006 May 2007 NO PROGRESS
franchisees to ensure accurate diversion reporting and
remittance of franchise fees.
2. High Morton/Lowart 2006 Install recycled water at Civic Center. Apr 2006 Jun 2007 UNDERWAY; Working with DSRSD to discuss
feasibility.
ADDITIONAL OBJECTIVES (WASTE MANAGEMENT)
V. TRANSPORTATION
A. MAINTENANCE
1. High Morton 2004 Examine potential funding sources for design and construction Nov 2005 Jun 2007 UNDERWAY; Consultant selected to conduct
of a maintenance yard and secure a site if funding becomes programming study.
available
2. High Morton/Rankin 2006 Complete Building Management Study Jul 2006 Jun 2007 UNDERWAY; Consultant selection Oct 2006.
3. High Morton 2006 Implement five (5) new community volunteer projects. Jul 2006 Jun 2007 UNDERWAY
ADDITIONAL OBJECTIVES (MAINTENANCE)
B. TRANSPORTATION
1. High Morton 2004 Participate in Tri-Valley Triangle Analysis to prioritize 1-580,1- July 2005 Oct 2006 UNDERWAY
680 and Route 84 transportation improvements.
2. High Morton 2004 Update Tri-Valley Transportation Development Fee Nexus July 2005 Dec 2006 UNDERWAY
Study together with the other (6) six agencies in the TVTC.
3. High Morton 2004 Work with EBRPD and the City of Pleasant on to conduct a July 2005 Oct 2006 UNDERWAY; Council presentation scheduled
preliminary engineering study and identify funding sources to for October 2006.
facilitate the connection of Alamo Canal Trail under 1-580 to
Pleasanton trails.
4. High Morton 2001 Work with ACTIA for the implementation of the Measure B July 2005 Dec 2006 UNDERWAY
transportation project along the Scarlett Drive corridor between
Dublin Blvd. and Dougherty Road.
Page 9
~
~
'....')
~
ADOPTED 2006-2007 GOALS & OBJECTIVES
BIMONTHLY REPORT AS OF 08-31-06
# COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS
PRIORITY RESPONSIBLE GOAL START COMPLETION
5. High Morton 2004 Utilize new CCT A traffic model to work with Livermore, Oct 2005 Feb 2007 UNDERWAY
Pleasanton, Alameda County and the Tri-Valley Transportation
Council to examine configurations of streets parallel to 1-580
(i.e., Dublin Blvd. /North Canyons Parkway, Stoneridge
Drive/Jack London Blvd.) and make
recommendations/advocacy.
6. High Morton 2002 Work with Pleasanton and Livermore to develop a cost sharing Sept 2005 June 2007 UNDERWAY; City Attorney drafting agreement.
agreement for the ultimate improvement of the
1-580/Fallon Road Interchange.
7. High Morton 2006 Work with LA VTA and BART to improve connectivity between July 2006 Sept 2006 NEARLY COMPLETE; Bus service started Aug
the City Park-and-Ride lot and the BART Station. 2006; Sign installation underway.
8. High Morton 2004 As part of the GP A for Parks RFT A, evaluate alternatives for a Feb 2006 TBD NO PROGRESS
Central Parkway extension to Dougherty Road and interface
options to the planned Scarlett Drive Extension.
9. High Morton 2004 Develop a City-wide Bicycle Master Plan including bicycle July 2005 Nov 2006 NEARLY COMPLETE
access to parks and open space areas.
10 High Morton 2005 Prepare global transportation plan for City (multi-modal). April 2007 June 2007 NO PROGRESS
ADDITIONAL OBJECTIVES (TRANSPORTATION)
-.........
\:J
~
Page 10
.,
'-..
~
CITY OF DUBLIN
FY 2006-2007 CIP STATUS AS OF 8/31/2006
GENERAL
10 Number Project Name
1 93135 CTV Studio Remodel
Status
UNDERWAY; CTV is negotiating space needs with
the Pleasanton Unified School District. (Behind
schedule)
2 93150 Network System Upgrade
UNDERWAY; Goal is to release RFP in Sep and
award by Nov; Report complete by Feb and to
Council in Mar.
3 93191 Accounting System
UNDERWAY; Phase 1-Consultant Assessment; Goal
release RFP in Sep and award by Dec; Phase 1
report by Mar.
4 93192 Geographic Information System NO PROGRESS; Scope of work for consultant will be
(Phase III) developed. Work will occur after Jan 1, 2007.
5 93200 Building Permit System UNDERWAY; Proposals under review.
6 93402 Maintenance Facility Study UNDERWAY
7 93451 Library Repairs NO PROGRESS; Goes out to bid beginning of Sep
2006; Bid opening at the end of Sep 2006.
8 93462 Inspector Trailers NO PROGRESS; Utility hook-ups Apr 2007 with
trailer move Jun 2007.
9 93900 Building Management Study UNDERWAY; RFP out.
10 93910 Civic Center Mod. Design Svcs UNDERWAY; Report to City Council Nov 2006.
& Construction
~ 11 93917 ADA Transition Plan UNDERWAY
~
~
~ 12 93923 Civic Center Window Sealing UNDERWAY; Authorized to go to bid Sep 2006.
~
= 13 93970 Automated Document Storage & NO PROGRESS
=: Retrieval System
~ 14 94500 Public Facility Fee Study Update UNDERWAY; Appraisal complete.
~
~ \')
Page 1
10 Number Project Name
1 94250 Sidewalk Safety Repair
2 94601 San Ramon Road Concrete
Sound Wall Maintenance
3 94942 Seasonal Street Banners
NO PROGRESS
NO PROGRESS
CITY OF DUBLIN
FY 2006-2007 CIP STATUS AS OF 8/31/2006
COMMUNITY IMPROVEMENTS
Status
Jul
UNDERWAY; Designs to City Council Oct 2006.
Page 2
\;
'\:)
"'-.
~
CITY OF DUBLIN
FY 2006-2007 CIP STATUS AS OF 8/31/2006
PARKS
ID
1
Number
95010
Project Name
Community Needs Assessment
Status
UNDERWAY
2
95210
Stagecoach Park Assessment
District Water Meter
UNDERWAY; Meter purchased.
3 95465 Shannon Community Center UNDERWAY; Design development approved,
Reconstruction construction documents in progress.
4 95555 Dublin Historic Park COMPLETE; Master Plan Complete.
5 95566 Murray Schoolhouse Exhibit COMPLETE
Restoration
6 95602 Emerald Glen Park Recreation & NO PROGRESS; Pending evaluation of publiclprivate
Aquatic Complex partnership.
7 95625 Dougherty Hill Park - Dog Park UNDERWAY; Bid awarded with construction to begin
Sep 2006.
8 95631 Park Furniture Replacement UNDERWAY; Bid awarded with installation to be
complete by Oct 2006.
9 95635 Park Play Area Renovations NO PROGRESS; Project to begin Nov 2006.
10 95640 Dublin Ranch Neighborhood UNDERWAY; Area F Neighborhood Square.
Parks
11 95640 Dublin Ranch Neighborhood UNDERWAY; Area G Neighborhood Square.
Parks
12 95640 Dublin Ranch Neighborhood NO PROGRESS; Area F Neighborhood Park.
Parks
13 95830 Dublin Sports Ground Renovation NO PROGRESS; To begin after the fields close in
December.
14 95851 Fallon Sports Park (Water Meter) COMPLETE; Water meter purchased. '""'
\N
I;:)
\:-"
Page 3 .........
~
CITY OF DUBLIN
FY 2006-2007 CIP STATUS AS OF 8/31/2006
STREETS
12007
ID Number Project Name Status Jul I Aug I Sep I Oct I Nov I Dec 1 Jan I Feb 1 Mar I Apr I May 1 Jun
1 94520 Tri-Valley Triangle Study UNDERWAY ..:;.:,' ~
2 96001 Tri-Valley Transportation UNDERWAY I': ' ~" ~
Development Fee Regional
Transportation Projects :
3 96011 West Dublin BART Station NO PROGRESS I.:. .,,:'" .:'..' "'" .: "'" '~," ~
Corridor Enhancement - Dublin
Boulevard - Hansen Drive to
Clark Avenue
4 96012 East Dublin BART Station NO PROGRESS I .
Corridor Enhancement - Dublin
Boulevard - Tassajara Road to
Clark Avenue
5 96022 Dublin Boulevard Bridge NO PROGRESS .".
Resurfacing at Alamo Canal
6 96082 Underground Utilities - Dublin UNDERWAY .... "",.,,';::. .-
Blvd./Dougherty Rd. intersection
and Vicinity
7 96400 Eastern Dublin Arterial Street UNDERWAY ;..:,:.;:: .::'" . : . .
.
Improvements
8 96430 1-580/Fallon Interchange UNDERWAY; Awaiting Caltrans approval. .' ''':'i'':'''''~'' .: .
Improvements
9 96452 Downtown Traffic Signal UNDERWAY . ;':"';' .
Equipment Replacement
10 96580 Annual Street Overlay Program NO PROGRESS I ~
' '"
11 96585 Annual Slurry Seal Program NO PROGRESS !' . ,..":;:;~; "':''''''':>k::'':''~
12 96773 Alamo Canal Trail Under 1-580 UNDERWAY; Public meeting held Aug 2006. I :,;:,,";;1<;;:Jl;~'1'J:~~l"';J~,'I~ .. .....:~
". .. . ,..'''~, '"''
. ,
13 96775 Citywide Bicycle I Pedestrian UNDERWAY; Plan is nearing completion. .;
.,-
Plan
14 96840 Scarlett Dr I Iron I-jorse trail UNDERWAY; Preliminary engineering to be : .,..",,:..::;,):' .:,'c',".: ".: ..
Extension completed Dec 2006.
15 96852 Dougherty Rd Improvements- UNDERWAY '::;:.." '. <E,:,;i:fi .... ...... ,.,:.,:,. ,i\,: .
Houston to 1-580
16 96870 St. Patrick Way - Regional UNDERWAY I. "':: . .';:::;::',/:;,'.:..:' .::' . .
Street to Golden Gate Drive :
17 96920 Dublin Boulevard Improvements UNDERWAY u '."""i:,i,',. ..,. ".:: .
- Village Parkway to Sierra Court
:
Page 4
..........
-t:
~
.,
"-
~~
ID
1
Number
96400
2
96400
3
96400
4
96400
5
96400
6
96400
7
96400
CITY OF DUBLIN
FY 2006-2007 CIP STATUS AS OF 8/31/2006
EASTERN DUBLIN ARTERIAL STREET IMPROVEMENTS - 96400
Project Name
Tassajara Road from Dublin
Ranch Phase I north to Fallon
Road. Four lanes total. Two to
be constructed by Pinn, two by
Un.
Status
UNDERWAY; Pinn section under construction; Un
portion pending approval and development of Wallis
Ranch.
Median on Dublin Blvd. between NO PROGRESS; Construction extended to 2006.
Scarlett Dr. and DeMarcus Blvd.
Fallon Rd. from Tassajara Rd
southeasterly to the end of
Dublin Ranch improvements.
Installation of a westbound
right-turn from Dublin Boulevard
to northbound Hacienda Drive
Pavement overlay on Central
Parkway just east of Tassajara
Road
Dedications and improvements
along Tassajara Road south of
the proposed intersection with
Fallon Road
Improvements to Fallon Road
between Dublin Boulevard and
1-580.
NO PROGRESS; Design complete; Construction on
hold until 2007 pending resource agency permit being
issued.
NO PROGRESS; Project is not currrently schedlued
for construction.
NO PROGRESS; Project is not currrently schedlued
for construction; Pending development of DiManto
property.
NO PROGRESS; Project is not currently scheduled;
Dependant on timing of DiManto, Wallis Ranch, and
Quarry Lane School.
UNDERWAY; Under Construction.
Page 5
Jun
~
..............
:~\>>f' ._'.
{'ddM
~
I;:)
.'
z'"
CJ'\