RESOLUTION NO. 228 - 06
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
*********
APPROVING AN AMENDMENT TO THE AGREEMENT WITH ENGEO, INC
FOR THE SHANNON COMMUNITY CENTER GEOTECHNICAL TESTNG
WHEREAS, the 2006-2011 Capital Improvement Program includes a project to construct The
Shannon Community Center; and
WHEREAS, the City has entered into an agreement with ENGEO, Inc to perform Geotechnical
testing and recommendations for the design and construction of the proposed facility; and
WHEREAS, ENGEO, Inc has performed the required tasks; and
WHEREAS, the City is prepared to bid the Shannon Community Center project which will
require Geotechnical testing; and
WHEREAS, ENGEO, Inc is qualified and available to perform work as specified.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
approve the amendment to the agreement with ENGEO, Inc, attached hereto and authorize the Mayor to
execute the Agreement.
PASSED, APPROVED AND ADOPTED this 19th day of December 2006, by the following
vote:
AYES: Councilmembers Hildenbrand, Oravtez, Sbranti and Scholz, and Mayor Lockhart
NOES: None
ABSENT: None
ABSTAIN: None
ATTESA ~...
()..h\
City Clerk
Reso No. 228-06, Adopted 12/19/06, Item 4.5
Page 1 of 1
GEO
INCORPORATED
GEOTECHNICAL
ENVIRONMENTAL
WATER RESOURCES
CONSTRUCTION SERVICES
Project No.
7096.1.002.01
November 7, 2006
Revised November 27,2006
Ms. Herma Lichtenstein
Parks and Facilities Development Manager
City of Dublin
100 Civic Plaza
Dublin, CA 94568
Subject:
Shannon Community Center
Dublin, Califomia
PROPOSAL FOR TESTING AND OBSERVATION SERVICES DURING
CONSTRUCTION
Reference:
ENGEO Inc.; Shannon Community Center, Geotechnical Exploration and Fault
Hazard Evaluation; June 8, 2006; Project No. 7096.1.001.01.
Dear Ms. Lichtenstein:
At your request, this letter presents our scope of services and fee estimate to provide continuing
geotechnical consultation and testing and observation (T &0) services during grading and site
development of the proposed replacement of the Shannon Community Center building located at
11600 Shannon Avenue in Dublin, California. The referenced report provides the results of our
geotechnical exploration and fault hazard study for the subject project.
We understand that it is proposed to demolish the existing building, and construct a new building
to create the new Community Center. Based on discussions with you, the new approximately
19,OOO-square-foot building will roughly occupy the same location and be slightly expanded to
the west towards the kiosk and to the north towards the existing slope. According to the plans
transmitted by Dahlin Group, the lower floor on the southeast comer of the proposed building
will be a partially below grade.
We expect that the foundation system for the proposed building will consist of conventional
spread footings and a perimeter strip footing with a concrete slab-an-grade floor. The building
loads are expected to be relatively light to moderate for this wood-framed structure.
It is anticipated to expand the main parking lot to the north and west by adding a new row of
parking spaces. It is also likely that the upper parking lot will be reconfigured. Grading is
EXHIBIT A - AMENDMENT TO THE AGREEMENT
201 0 Crow Canyon Place. Suite 250 . San Ramon, CA 9'.l5R3-4634 . (925) 866-9000 . Fax (888) 279-2698
wwvv.engeo.c0111
City of Dublin
Shalmon Community Center
PROPOSAL FOR TESTING AND OBSERVATION SERVICES
DURING CONSTRUCTION
7096.1.002.01
November 7, 2006
Revised November 27, 2006
Page 2
anticipated to consist of preparing the sub grade for the parking improvements and building
slab-on-grade. This will require cuts in some areas and moisture conditioning and constructing
new engineered fills. The area which now serves as a patio for the existing lower floor, and will
be backfilled with engineered fill (approximately 10 feet thick). According to our discussions,
the deck of the central pedestrian bridge will be replaced. However, the foundation of the bridge
is anticipated to be re-used.
SCOPE OF SERVICES
Geotechnical Testing and Observation
In addition to demolition of the existing building, general site grading to create the building pad,
other site improvements will include utility trench backfill (sanitary sewer, storm drain, water line
and joint trench); access drive and parking lot preparation (subgrade and aggregate base
preparation); and retaining wall construction (footing excavation observation, backdrain facility
installation and wall backfill). The following work described herein will be perfonned under the
terms and conditions contained in your standard contract for professional services to be issued. The
elements of our services will include the following:
· Observation and testing during mass grading including backfilling of the fault trenches.
· Observation and testing during utility trench backfill (Sanitary Sewer, Storm Water, Water and
Joint Trench).
· Observation and testing during retammg wall construction including backdrain facility
installation and backfill of retaining walls.
· Observation and testing of on-site access drives mid parking area subgrade and aggregate base.
· AttendallCe at project meetings and geotechnical consultation during construction, as requested.
· Review of the grading plallS alld .foundation plans.
· Preparation oflelters documenting our reviews, observations and testing.
· Observation and testing of pavement subgrade and base.
1. TESTING AND OBSERVATION SERVICES
The following estimates are based upon an assumed on-site schedule indicated below, Additionally,
it is based upon an 8-hour workday, and 5-day workweek. Overtime and weekends are not
included. If any schedules are available, we can update this estimate accordingly. We will bill our
fees on a time and materials basis utilizing our standard billing rates (attached).
City of Dublin
SIlmman Community Center
PROPOSAL FOR TESTING AND OBSERVATION SERVICES
DURING CONSTRUCTION
7096.1.002.01
November 7,2006
Revised November 27,2006
Page 3
Demolition and Site Grading: Field Technician - Observe geotechnical aspects of demolition
and site grading and perform relative compaction tests during grading; full-to part-time over
5-weeks (18 days): $16,800.00
Utility Trench Backfill: Field Technician - Observe trench backfilling and perform relative
compaction tests; full to part-time over 5 weeks (80 hours): $9,000.00
On-site Access Roads /Parking: Observe subgrade and AB and perform relative compaction tests
during site grading (16 hours): $2,000.00
Retaining Walls: Field Technician -Document foundation construction, subdrainage and test soil
backfill compaction; full to part-time over 2 weeks (20 hours): $2,500.00
Field Manager/Engineer: Site visits to verify compliance with recommendations and observe
. footing excavations: $6,000.00
Laboratory Testing: We estimate that 6 laboratory compaction tests will be needed to detennine the
maximum dry unit weight and optimum moisture content of the site and import material: $2.500.00
SUBTOTAL FOR TESTING AND OBSERVATION SERVICES
$38,800.00
2. REPORTS AND CONSULTATION
· Meetings, consultation and site visits as needed during construction
· Review of grading plans
· Review of Foundation Plans and preparation of a letter:
· One Testing and Observation Report summarizing our Grading and Improvement
services, including test data, to be prepared at completion of site activities:
$3,000.00
$1,500.00
$1,500.00
SUBTOTAL FOR REPORTS/CONSULTATION
$2,000.00
$8,000.00
SUMMARY OF FEES
Testing and Observation Services
Reports/Consultation
] 0% Contingency
ESTIMATED TOTAL
$38,800.00
$8,000.00
$4.600.00
$51,400.00
City of Dublin
Shannon Community Center
PROPOSAL FOR TESTING AND OBSERVATION SERVICES
DURING CONSTRUCTION
7096.1.002.01
November 7, 2006
Revised November 27, 2006
Page 4
LIMITATIONS
We will strive to perform our work in general confonnance with the geotechnical engineering
practice that exists within Dublin area at the time our services are provided. No warranties are
expressed or implied. ENGEO's liability for damage due to professional negligence, acts, errors,
omissions, breach of contract and consequential damages will be limited by Client to an amount of
available coverage defined in the Consulting Services Agreement or ENGEO's fee, whichever is
greater, regardless of the legal theory under which such liability is imposed
If you are in agreement with the scope of services and fees outlined above, please issue an
addendum to our existing Consulting Services Agreement dated December 5, 2005 for a total
not-to-exceed fee of$51,400 without your written approval as authorization for us to proceed.
We look forward to our continuing our work with you on this project. If you have any questions
regarding the scope of services or fee estimates, please do not hesitate to contact us.
Very truly yours,
ENGEO INCORPORATED
.rI
c::iJ _I ~~__
Donald E. Bruggers
deb/cc:revprop