Loading...
HomeMy WebLinkAbout4.09 AlamoCanalBike02-04CITY CLERK File # 1:1600-3� AGENDA STATEMENT CITY COUNCIL MEETING DATE: May 21, 2002 SUBJECT: Award of Bid — Contract No. 02-04, Alamo Canal Bike Path from the Iron Horse Trail Junction to I-580 Report Prepared by: Lee S. Thompson, Public Works Director ATTACHMENTS: 1) Resolution 2) Bid Results RECOMMENDATION: �, dopt resolution awarding bid to Top Grade Construction, Inc. FINANCIAL STATEMENT: 2000-2001 2001-2002 Salaries/Design/Misc: $ 39,685 $ 30,400 Improvements: 154,080 TOTAL: $ 39,685 $ 184,480 BUDGET: 2002-2003* TOTAL LOW BID $ 4,700 $ 74,785 295,920 450,000 $ 243,982.50 $ 300,620 $ 524,785 $ 243,982.50 * Costs estimated at the time Council authorized go to bid BUDGET BY FUND: Revised TFCA (221) $ 154,080 TDA (211) 102,770 Measure B (217) 95,000 General Fund (001) 172,935 ** TOTAL: $ 524,785 ** Because the low bid is substantially below the budget, not all of these funds will be required. The CIP budget for FY 2002-03 will reflect the reduced need for funding. There are sufficient monies budgeted in FY 2001-02 to perform the work to be completed this Fiscal Year. DESCRIPTION: On April 16, 2002, the City Council authorized Staff to solicit bids for Contract No. 02-04, Alamo Canal Bike Path from the Iron Horse Trail Junction to I-580. At the same time, a budget change was approved so that the project could be started in Fiscal Year 2001-2002 in order to meet the current funding guidelines for the TFCA grant. Completion of the project is scheduled for the end of July 2002. --------------------------------------------------------------- COPIES TO• B'dd 00 . i ers gAmiscproj\alamo bike IH-I580\agstawrd ITEM NO. f� This project will pave the existing Zone 7 maintenance road along the east side of the Alamo Canal, resulting in a path approximately 12 feet wide with a concrete curb and gutter to control drainage. When complete, the path will complete the Iron Horse Trail system and provide pedestrian and bicycle access to the Civic Center and Library. A total of six (6) bids were received. The low bidder is Top Grade Construction, Inc., with a bid of $243,982.50. Staff has reviewed the bids, called references and determined that Top Grade Construction, Inc., has satisfactorily performed similar projects for other cities. Staff recommends that the City Council adopt the resolution awarding Contract No. 02-04 to Top Grade Construction, Inc. Page 2 c~ ~ RESOLUTION NO. - 02 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN AWARDING CONTRACT NO. 02-04 ALAMO CANAL BIKE PATH FROM THE IRON HORSE TRAIL JUNCTION TO 1-580 WHEREAS, the City of Dublin did, on May 14, 2002, publicly open, examine, and declare all sealed bids for doing the work described in the approved Plans, Specifications, and Modifications for Contract No. 02-04, Alamo Canal Bike Path Project from the Iron Horse Trail Junction to 1-580, authorized by the City Council on April 16, 2002, which Plans, Specifications, and Modifications are hereby expressly referred to for a description of said work and for all particulars relative to the proceedings under the request for bids; and WHEREAS, said bids were submitted to the City Engineer, who has recommended that the bid hereinafter mentioned is the lowest and best bid for doing said work; NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby award City of Dublin Contract No. 02-04 to the lowest responsible bidder therefor, to wit, Top Grade Construction, Inc., at a bid of Two Hundred Forty-Three Thousand, Nine Hundred Eighty-Two Dollars and Fifty Cents ($243,982.50), the particulars of which bid are on file in the Office of the City Engineer. PASSED, APPROVED AND ADOPTED this 21 st day of May, 2002~ AYES: NOES: ABSENT: ABSTAINING: Mayor ATTEST: City Clerk BID RESULTS: ALAMO CANAL BIKE PATH - IRON HORSE TRAIL JUNCTION to 1-580, CONTRAC~T 02-04 _ BID OPENING DATE - MAY 14, 2002 I I ENGINEER'S ESTIMATE TOP GRADE CONSTR. FANFA, INC. GRADE TECH, INC. BID UNIT ITEMi ITEM DESCRIPTION MEAS. QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE 1. Construction Staking LS 1 12,500.00 12,500.00 11,000.00 11,000.00 6,385.00 6,385.00 10,000.00 10,000.00 2. Clearing and Grubbing LS 1 5,000.00 5,000.00 2,000.00 2,000.00 14,185.00 14,185.00 25,000.00 25,000.00 3. Remove Drainage Inlet -- EA 6 500.00 3,000.00 500.00 3,000.00 1,295.00 7,770.00 500.00 3,000.00 4.- Roadway Excavation (cut 1,100/fill 15~0) CY 1,100 54.55 60,005.00 30.00 33,000.00 26.96 29,656.00 __ 73.00 80,300.00 5. Shoulder Backing LF 3,500 2.50 8,750.00 1.00 3,500.00 3.60 12,600.00 0.50 1,750.00 6. Class 2 Aggregate Base CY 630 60.00 37,800.00 60.00 37,800.00 45.90 28,917.00 34.00 21,420.00 7. Asphalt Concrete - Type B TON 1,400 100.00 140,000~00 55.00 77,000.00 63.65 89,110.00 48.00 67,200.00 _ 8. 12"CMP LF 12 125.00 1,500.00 100.00 1,200.00 83.20 998.40 200.00 2,400.00 9. 24" RCP - Class 3 LF 6 175.00 1,050.00 100.00 600.00 172.55 1,035.30 200.00 1,200.00 10. Drainage Inlet - Type A Modified EA 11 3,000.00 33,000.00 1,450.00 15,950.00 2,089.50 22,984.50 1,500.00 16,500.00 11. Drainage Inlet- Field Inlet EA 1 2,500.00 2,500.00 1,250.00 1,250.00 1,807.00 1,807.00 1,300.00 1,300.00 12. Minor Concrete (6" Curb/l' Gutter) - LF 3,450 20.00 69,000.00 13.00 44,850.00 13.76 47,472.00 13.00 44,850.00 13. Minor Concrete (2' Wide Valley Gutter) LF 35 25.00 875.00 9.50 332.50 25.90 906.50 15.00 525.00 14. Reconstruct 6' Chain Link Fence LF ----500 25.00 12,500.00 15.00 7,500.00 28.70 14,350.00 15.00 7,500.00 15. Chain Link Gate (Two 8' Panels) EA 1 1,000.00 1,000.00 1,500.00 ___ 1,500.00 1,502.42 1,502.42 ...... 1,200.00 1,200.00 16. Roadside sign"END OFTRAIL" EA 1 250.00 250.00 500.00 500.00 498.75 498.75 300.00 _ 300.00 17. Hydroseeding SY 2,000 3.00 6,000.00 1.50 3,000.00 1.50 3,000.00 1.00 2,000°00 TOTAL BiD: -- $ 394,730.00 $ 243,982.50 $ 283,177.87 $ 286,445.--00 * · Amounts adjusted after verification. REDGWlCK CONSTR. C.F. ARCHIBALD O'GRADY PAVING BID UNIT ITEM ITEM DESCRIPTION MEAS. QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE 1. Construction Staking -- LS 1 5,000.00 5,000.00 10,000.000 10,000.00 5,000.00 5,000.00 __ _ 2. Clearing and Grubbing LS I 5,000.00 5,000.00 15,000.000 15,000.00- 15,000.00 15,000.00 3. Remove Drainage Inlet EA 6 700.00 4,200.00 1,000.000 6,000.00 500.00 3,000.00 4. Roadway Excavation (cut 1,100/fill 150) CY 1,100 66.00 72,600.00 45.000 49,500.00 72.00 79,200.00 5. Shoulder Backing LF 3,500 1o75 6,125.00 3.000 10,500.00 3.00 10,500.00 6. Class 2 Aggregate Base CY 630 --- 70.00 44,100.00 37.000 23,310.00 70.00 44,100.00 B TON 1 55.00 77,000.00 72.000 100,800.00 70.00 98,000.00 7. Asphalt Concrete Type 8. 12"CMP LF 12 70.00 840.00 150.000 1,800.00 270.00 ___ 3,240.00 __ 9. 24" RCP - Class 3 __ LF 6 150.00 900.00 300.000 1,800.00 330.00 1,980.00 10- Drainage Inlet - Type A Modified EA 11 1,800.00 19,800.00 1,600.000 17,600.00 1,600.00 _17,600.00 11. Drainage Inlet - Field Inlet EA 1 1,700.00 1,700.00 1,400.000 1,400.00 1,300.00 1,300.00 12. Minor Concrete (6" Curb/l' Gutter) LF 3,450 14.00 48,300.00 14.000 48,300.00 14.00 48,300.00 -- 13. Minor Concrete (2' Wide Valley Gutter) LF 35 10.00 350.00 10.000 350.00 9.00 315.00 14. Reconstruct 6' Chain Link Fence LF 500 15.50 7,750.00 - 22.000 11,000.00 16.00 8,000.00 15. Chain Link Gate (Two 8' Panels) EA 1 1,700.00 1,700.00 2,000.000 2,000.00 1,600.00 1,600.00 16. Roadside sign "END OF TRAIL" EA 1 500.00 500.00 500.000 __500.00 600.00 600.00 -17. Hydroseeding SY 2,000 1.00 _ 2,000.00 1.000 2,000.00 1.00 2,000.00 TOTAL BID: $ 297,865.00 $ 301,860.00 $ 339,735.00