RESOLUTION NO. 14 - 07
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
*********
ACCEPTANCE OF LANDSCAPE IMPROVEMENTS FOR TRACT 7136,
DUBLIN RANCH AREA A (NEIGHBORHOOD A-1)
(TOLL BROTHERS, INC.)
WHEREAS, the subdivider of Tract 7136, filed on May 3, 2002, in Book 263 of Maps at Pages 87 -
93, previously entered into two (2) Tract Developer Agreements with the City of Dublin, one for Street
Improvements and one for Landscaping, to improve said Tract in accordance with plans and specifications on
file with the Public Works Director, said Tract identified as follows:
a) Subdivider:
b) Tract Location:
c) Tract Size:
d) Resolution Approving Agreement:
e) City Streets Affected:
Toll Brothers. Inc.
West of Fallon Road
110 Single-Family Lots
No. 32-02, City of Dublin City Council
None
WHEREAS, the Tract Developer Agreements were previously amended on March 18, 2003, via City
Council Resolution Nos. 44-03 and 45-03, and on March 16, 2004, via City Council Resolution Nos. 41-04
and 42-04 to extend the completion date to March 19,2005; and
WHEREAS, the Tract Developer Agreement for Landscape was further amended via City Council
Resolution No. 214-04 on November 2, 2004, to accept partial landscaping, with the exception of the
landscaping within Parcels A, B, C and D, associated with Tract 7136; and
WHEREAS, the Street Improvement work was accepted via City Council Resolution No. 212-04 on
November 2, 2004; and
WHEREAS, the third amendment to the Tract Developer Agreement for Landscape Improvements
for Tract 7136 was approved via City Council Resolution No. 214-04 on November 2, 2004, to accept
partial Landscape Improvements, with the exception of the landscaping within Parcels A, B, C, and D; and
WHEREAS, Section 2 of the governing Tract Developer Agreement was amended via City Council
Resolution No. 214-04 on November 2,2004, to reflect a reduced total security amount of $40,000 which
was sufficient to guarantee the remaining Parcels A, B, C, and D work; and
WHEREAS, the Landscape Improvements as guaranteed by a Performance Bond and a Labor and
Materials Bond each in the amount of $40,000, and as governed by the landscape Tract Developer Agreement,
are complete in accordance with said plans and specifications, and any approved modifications thereto, to the
satisfaction of the Public Works Director; and
WHEREAS, the original Performance Bond and Labor and Materials Bonds that guaranteed the
Landscape Improvements can be released, in accordance with the authority contained in S66499.7 of the
Government Code of the State of California, and replaced with a Maintenance Bond to guarantee the
completed work for a one-year period following acceptance;
Reso No. 14-07, Adopted 2/20/07, Item 4.3
Page 1 of2
NOW, THEREFORE, BE IT RESOLVED that
1. The Landscape Improvements completed within Parcels A, B, C and D within said Tract
7136, are hereby approved and accepted subject to a one-year guarantee period; and
2. The original Performance Bond issued by Travelers Casualty and Surety Company of America
(Bond No. 104091615) in the amount of $40,000 be released; and
3. The original Labor and Materials Bond issued by Travelers Casualty and Surety Company of
America (Bond No. 104091615) in the amount of $40,000 be released; and
4. The submitted Maintenance Bond issued by Travelers Casualty and Surety Company of
America (Bond No. 104564074) in the amount of $10,000 be accepted as security for the
aforesaid one-year maintenance period, said period to commence on this date and terminate on
the 20th day of February, 2008.
PASSED, APPROVED AND ADOPTED this 20th day of February, 2007, by the following vote:
AYES: Councilmembers Hildenbrand, Oravetz, Sbranti and Scholz, and Mayor Lockhart
NOES: None
ABSENT: None
ABSTAIN: None