HomeMy WebLinkAbout06-026 Dubln Gatewy Med Ctr PD Rez/CUP/SDR
AGENDA STATEMENT
PLANNING COMMISSION MEETING DATE: April 24, 2007
SUBJECT:
ATTACHMENTS:
~\\l)
'--
RECOMMENDATION: 1.
2.
3.
4.
5.
PUBLIC HEARING: P A 06-026 Dublin Gateway Medical Center
Building 3 Hospital and Garage - Planned Development Rezone and
Stage 1 and 2 Development Plan, Conditional Use Permit, Site
Development Review, and Development Agreement (Legislative and
Adjudicatory Actions)
Report Prepared by Mamie R. Nuccio, Associate Planner
1.
Resolution recommending City Council adoption of a CEQA
Addendum for an amendment to the Stage 1 and 2 Development Plan
for Planned Development Zoning District (P A 98-047) and for a
Conditional Use Permit and Site Development Review for the Dublin
Gateway Medical Center Building 3 Hospital and Garage Project,
with draft City Council Resolution and draft Addendum attached as
Exhibit A.
Resolution recommending City Council adoption of a Planned
Development Rezone and Stage I and 2 Development Plan for the
Dublin Gateway Medical Center Building 3 Hospital and Garage
Project, with draft City Council Ordinance and draft Stage 1 and 2
Development Plan attached as Exhibit A.
Resolution referring decision making authority and recommending
City Council approval of a Conditional Use Permit and Site
Development Review for the Dublin Gateway Medical Center
Building 3 Hospital and Garage Project, with draft City Council
Resolution and proposed Project Plans attached as Exhibit A.
Resolution recommending City Council adoption of a Development
Agreement for the Dublin Gateway Medical Center Building 3
Hospital and Garage Project, with draft City Council Ordinance and
draft Development Agreement attached as Exhibit A.
Proposed amended Stage 1 and 2 Development Plan in draft form
with amended text shown in strike-through and underline.
2.
3.
4.
5.
Receive Staff presentation;
Open the public hearing;
Take testimony from the Applicant and the public;
Close public hearing and deliberate;
Adopt Resolution (Attachment 1) recommending City Council
approval of a CEQA Addendum;
COPIES TO: Applicant
Property Owner
File
Mahendar Chima, Public Works Department
ITEM NO._€> .1-
G:\P A#\2006\06-026 Dublin Gateway Bldg 3 Mod\Public Hearing Documents\PC\PCSR draftJev.doc
6, Adopt Resolution (Attachment 2) recommending City Council
adoption of a Planned Development Rezone and Stage 1 and 2
Development Plan; ,
7, Adopt Resolution (Attachment 3) referring decision making authority
and recommending City Council approval of a Conditional Use
Permit and Site Development Review; and
8, Adopt Resolution (Attachment 4) recommending City Council
adoption of a Development Agreement.
PROJECT DESCRIPTION:
BACKGROUND
In November 1998, the Planning Commission adopted Resolution 98-51 approving Tentative Parcel Map
7064 and Site Development Review for the Koll Dublin Corporate Center, The Koll Dublin Corporate
Center is now known simply as the Dublin Corporate Center and is located west of Tassajara Road
between Interstate 580 to the south and Dublin Boulevard to the north within the Eastern Dublin Specific
Plan area (Figure 1), In December 1998, the City Council adopted Ordinance 22-98 establishing a
Planned Development Zoning District (P A 98-047) and adopting a Stage 1 and 2 Development Plan for
the Koll Dublin Corporate Center. The Ordinance and Development Plan, together with the Planning
Commission approvals, established the land uses and development standards for the Dublin Corporate
Center,
Figure 1. Dublin Corporate Center Vicinity Map
Dublin Blvd
Tassajara Rd
Glynnis Rose Dr
Westbound 1-580
On-ramp
2 of 15
Original Dublin Corporate Center Approvals
In 1998, the Dublin Corporate Center was originally proposed to be developed in the following multiple
phases (see Table 1):
. Phase I - Professional Office Buildings: three, 4-story office buildings for a combined total of 417,855
square feet
. Phase II - Signature Office Building: one, 6-story office building at 178,849 square feet
. Phase III - Hotel and Retail: one, 6-story hotel at 85,000 square feet and 14,000 square feet of retail
T bl 1 1998 0 .. I P
H D bl" C
t C t D I
t
a e . ngma roposa or u m orpora e en er eve opmen
PHASE No. OF USE No. OF SQUARE TOTAL
BUILDINGS STORIES FOOTAGE SQUARE
FOOTAGE
Phase I: 1 Office 4 139,285
Professional Office 1 Office 4 139,285 417,855
Buildings 1 Office 4 139,285
Phase II:
Signature Office 1 Office 6 178,849 178,849
Building
Phase III: 1 Hotel 6 85,000 99,000
Hotel and Retail 1 Retail 1 14,000
TOTAL 695,704
Subsequent Development and Approvals for Dublin Corporate Center
Subsequent to the original 1998 approvals, the three Phases of the Dublin Corporate Center development
have evolved to meet the changing market conditions. A summary of the changes to each Phase are
described in turn below.
Phase I - Professional Office Buildings Constructed as Planned
Phase I was constructed in 2000-2001 as originally proposed and includes three, 4-story professional
office buildings totaling 417,855 square feet. These buildings are currently occupied by a variety of
professional office uses including Avaya, Inc., Compass, Development Dimension International, Kronos,
Supergen, Ellie Mae, Long Beach Mortgage and Taleo, to name a few.
Phase II - Signature Office Building changed to Dublin Gateway Medical Center
Phase II of the Dublin Corporate Center was approved in 2005 for the development of the Dublin
Gateway Medical Center. The approvals for the Dublin Gateway Medical Center include the following:
two, 3-story medical office buildings; one, 3-story lifestyle/wellness center (indoor recreational facility);
and, a 4-level above ground parking garage (see Table 2). The Dublin Gateway Medical Center project
was approved to be developed in two Phases (Phase One and Phase Two). Phase Two itself was approved
to be developed in sub-phases to ensure construction of the parking garage prior to construction of the
third medical office building. Construction of Phase One was completed in January 2007.
3 of 15
Table 2. 2005 Dublin Gatewa' Medical Center Approvals (Phase II of the Dublin Corporate Center)
PHASE No. OF USE No. OF SQUARE TOTAL
BUILDINGS StORIES FOOTAGE SQUARE
FOOTAGE
Phase One 1 Medical Office 3 57,700 120,000
1 Lifestyle/Wellness 3 62,300
Phase Two (a) 1 Parking Garage 4 n/a
Phase Two (b) 1 Medical Office 3 58,000 58,000
TOTAL 178,000
The original 1998 approval for the Dublin Corporate Center anticipated the development of one, 6-story
signature office building on the Dublin Gateway Medical Center site. However, due to changes in market
conditions the developer sought approval for the development of medical offices instead of professional
offices in 2005. The 2005 approvals reflected approximately the same total square footage, but added a
parking garage where surface parking was previously proposed; however, the building's footprint
remained the same.
During the review of the construction drawings for Phase One of the Dublin Gateway Medical Center
project, the Lifestyle/Wellness Center building was modified from two full floors and a partial third floor
(to accommodate an indoor basketball court) to three full floors for medical offices. As a result of this
modification, the Lifestyle/Wellness Center building increased in square footage from 62,300 square feet
to 65,295 square feet.
The subject of this staff report is a request for an alternative approval for Phase Two of the Dublin
Gateway Medical Center project. The alternative to Phase Two includes the construction of a 6-story,
168,000 square foot, 100-bed hospital building and a 5-level parking garage with one level of parking
below ground and 4 levels of parking above ground (the "Project") on the same 3.13::!:: acres ofland which
was previously approved for development of a 3-story medical office building at 58,000 square feet and a
4-level above ground parking garage (see Table 3). Further discussion of the proposed Project is provided
below in the Analysis section of this staff report.
Table 3. Proposed Alternate Approval for Phase Two of the Dublin Gateway Medical Center
PHASE USE No. OF No. OF SQUARE TOTAL SQUARE
BUILDINGS STORIES FOOTAGE FOOTAGE
Phase One Medical Office 1 3 57,786 123,081
Medical Office 1 3 65,295
Phase Two (a) Parking Garage 1 4 above ground n/a
1 below ground
Phase Two (b) Hospital 1 6 168,000 168,000
TOTAL 291,081
Phase III - Hotel and Retail Changed to Bank and Retail
A portion of Phase III of the Dublin Corporate Center was constructed in December 2004 with the
development of a 6,100 square foot bank (Bank of America). On August 24, 2004 the Planning
Commission approved the remainder of Phase III which includes 50,530 square feet of retail (Ulferts
Center) (see Table 4). The original 1998 approval for the Dublin Corporate Center anticipated the
development of a hotel in Phase III however, due to changes in market conditions the developer sought
approval for the development of commercial shopping center instead. Consequently, the original 1998
4 of 15
approval for Phase III of 99,000 total square feet for a hotel and retail (see Table 1 above) has been
reduced to a total of 56,630 square feet for a bank and retail.
T bl 4 R . d D br C
C
D I
f 2005
a e . eVlse u III orporate enter eve opment as 0
PHASE NO. OF USE STATUS No. OF SQUARE TOTAL
BUILDINGS STORIES FOOTAGE SQUARE
FOOTAGE
Phase I 1 Office All 3 buildings constructed 4 139,285
1 Office in 2000-2001 4 139,285 417,855
1 Office 4 139,285
Phase II 1 Medical Office 2 medical office buildings 3 57,786
1 Medical Office constructed in 2007; 3 65,295
1 Medical Office remainder pending 3 58,000 181,081
1 Parking Garage approval of the alternate 4 nla
approval request
Phase III 1 Bank Bank constructed in 2004; 1 6,100
1 Retail Retail under construction 2 50,530 56,630
and nearing completion
TOTAL 655,566
ANALYSIS:
Phase Two of the Dublin Gateway Medical Center project was approved by the Planning Commission
(Resolution 05-06) for the construction of a 3-story, 58,000 square foot medical office building and a 4-
level parking garage on 3.13::!:: acres of land (the "Original Approval"). The Applicant subsequently
submitted a request for an alternative Project, which proposes the development of a 6-story, 168,000
square foot, 100-bed hospital and a 5-level parking garage with I level below ground and 4 levels above
ground on approximately 3.13 acres of the 7.14 acre Dublin Gateway Medical Center site (see Figure 2).
The current Project includes a Planned Development Rezone with amended Stage 1 and 2 Development
Plan, a Conditional Use Permit, Site Development Review and a Development Agreement. The Project
would provide the Applicant with the option of constructing the Original Approval (a 3-story medical
office building and 4-level parking garage) or the Project (a 6-story, 100-bed hospital building and 5-level
parking garage) as Phase Two of the Dublin Gateway Medical Center for the life of the Original Approval
and the Project entitlements.
Figure 2. Dublin Gateway Medical Center Project Site
'"
<l
'"
~
""
~
;:,
5 of 15
PLANNED DEVELOPMENT REZONE AND STAGE 1 AND 2 DEVELOPMENT PLAN
The 1998 Stage 1 and 2 Development Plan adopted for the Dublin Corporate Center anticipated the
development of one, 6-story, 168,000 square foot signature office building on the southwest corner of
Dublin Boulevard and Tassajara Road; the building was planned to be served by surface parking. In
200S, due to changes in market conditions, the developer sought approvals for two, 3-story medical office
buildings, a 3-story Lifestyle/Wellness Center and a 4-level above ground parking garage rather than the
6-story signature office building with surface parking. While the 200S approval included a modified site
layout from what was anticipated in the 1998 Stage I and 2 Development Plan for the Dublin Corporate
Center, the modifications to the site layout were determined to be in substantial conformance with the
Stage 1 and 2 Development Plan because the total square footage of the project remained the same.
The current Project proposes an additional 110,000 square feet above and beyond what was previously
anticipated in the 1998 Stage I and 2 Development Plan and therefore an amendment to the Development
Plan is necessary. The proposed amendments to the Development Plan include an increase in the density
on Lot 7 of Tract 7064 from approximately 178,000 square feet to approximately 292,000 square feet; Lot
7 is the entire ::!::7 acre Dublin Gateway Medical Center project site. Also included in the proposed
amendments is a provision which allows for the construction of the 3-story medical office building
approved in 200S or the 6-story, 100-bed hospital building. This provision provides flexibility to the
developer to construct either project depending upon market conditions (see Attachment S for the draft
version of the amended Development Plan; see Exhibit A to Attachment 2 for the clean version).
The amendments will also reflect the new site layout, landscaping, and development standards for the
Project. Also reflected in the amended Development Plan are changes which were previously approved
by way of a Conditional Use Permit for the Ulferts Center and the original Dublin Gateway Medical
Center. By incorporating these changes into the amended Development Plan, the Development Plan will
reflect all actions taken on projects within the Dublin Corporate Center in one document.
The findings for the Planned Development Rezone and Stage 1 and 2 Development Plan are included in
Attachment 2, pages 2-3.
CONDITIONAL USE PERMIT
The Stage 1 and 2 Development Plan adopted for the Dublin Corporate Center includes a list of permitted
and conditionally permitted uses for the Project site. A hospitaVmedical center is a conditional use and as
such requires approval of a Conditional Use Permit by the Planning Commission.
The proposed 100-bed hospital is an appropriate use for the site because it would be located adjacent to
existing medical office buildings and is located along major thoroughfares including Dublin Boulevard
and Tassajara Road. The hospital is also in close proximity to the Interstate S80/Tassajara Road
interchange which provides convenient access to the site from within the Tri- Valley region.
The hospital use would include 100 patient beds and an emergency room. The hospital and emergency
room would be operational 24 hours a day, 7 days a week. A drop-off and pick-up area is designated at
the main entrance to the hospital which is internal to the site. The entrance to the emergency room is just
east of the main hospital entrance; ambulance arrivals would occur on the east side of the building across
from the existing medical office building which is currently occupied by Palo Alto Medical Foundation.
Noise associated with ambulances arriving at the emergency room would not negatively impact the site or
adjacent properties because all sirens would be turned off upon entering the site. Additional analysis on
noise impacts are discussed below in the section titled, Environmental Review.
6 of 15
The hospital is estimated to have 75 doctors and 450 employees. Dublin Zoning Ordinance Chapter 8.76,
the Off-Street Parking and Loading Regulations, requires the following for a hospital use:
. I parking space for every 3 beds
. I parking space for every 3 (non-doctor) employees on the largest shift
. I parking space for each doctor (on the largest shift)
The Project proposes to provide 100 beds, 150 employees on the largest shift and 25 doctors on the largest
shift for a total parking requirement of 108 spaces. In calculating the required number of parking stalls,
the number of employees on the largest shift does not include doctors; in calculating the required number
of parking stalls for doctors, the number of doctors on the largest shift was used.
The parking garage would provide 512 parking spaces and an additional 172 surface parking spaces
would be provided throughout both Phase One and Phase Two of the Dublin Gateway Medical Center (36
of the surface parking spaces are located on the south side of Koll Center Drive but are within the
property boundaries of the Dublin Gateway Medical Center and therefore are counted towards the total
parking for the Project). The total amount of parking provided would be 684 stalls.
All parking stalls, both surface parking and structured parking, would be shared between Phase One and
Two of the Dublin Gateway Medical Center. Currently, the two existing medical office buildings are
surface parked; the majority of this surface parking would be incorporated into the parking structure as
part of Phase Two of the Project.
A parking ratio of I space for every 250 square feet of gross floor area was used to calculate the required
parking for Phase One (123,081 square feet) and results in a total parking requirement of 492 stalls. The
Dublin Zoning Ordinance requires 1 space for every 150 square feet of gross floor area for Health
Services/Clinics and I space for every 350 square feet of gross floor area for Professional Offices greater
than 40,000 square feet. The definition of Health Services/Clinics and Professional Offices both include
medical uses therefore a ratio of 1 space for every 250 square feet of gross floor area was used as a mid-
point calculation.
The required parking for the proposed hospital in Phase Two would be 108 stalls; combined with the 492
stalls required for Phase One, the total parking requirement for the Dublin Gateway Medical Center
project would be 600 stalls. As stated above, the total amount of parking proposed would be 684 stalls or
84 more than what is required therefore an appropriate amount of parking would be provided for the
Proj ect.
T bl 5 D br G
Md' lC
P k" S
a e . u III ateway e lca enter ar III 2 ummary
PHASE USE SQUARE REQUIRED PARKING RATIO PER No. OF
FOOTAGE/ BEDS DUBLIN ZoNING ORDINANCE PARKING
SPACES
REQUIRED
Phase One Medical Office 57,786 1/250 231
Medical Office 65,295 1/250 261
Total 492
Phase Hospital 100 beds 1/3 beds 33
Two 1/3 employees on largest shift 50
1/doctor on largest shift 25
Total 108
Total Number of Required Parking Stalls 600
Total Number of Parking Stalls Provided 684
7 of 15
SITE DEVELOPMENT REVIEW
Site Lavout (Page AI. 1. Exhibit A. Attachment 3)
The Project is generally located at the southeast corner of Dublin Boulevard and Glynnis Rose Drive;
Phase One of the Dublin Gateway Medical Center and Tassajara Road are to the east of the Project and
Koll Center Drive is to the south. The proposed hospital building would be located directly on the
southeast corner of Dublin Boulevard and Glynnis Rose Drive and the proposed parking garage would be
located south of the proposed hospital on the northeast corner of Glynnis Rose Drive and Koll Center
Drive. The Project site is currently developed with surface parking and landscaping as part of Phase One
of the Dublin Gateway Medical Center. The proposed Project would not modify the existing vehicular
access points to the site which are currently located off of Koll Center Drive and Glynnis Rose Drive.
Access. Circulation and Parking (Exhibit A. Attachment 3)
As noted above, the vehicular access points to the Project site are currently located off of Koll Center
Drive and Glynnis Rose Drive and are not proposed to be modified as part of the Project. External
vehicular and pedestrian access and internal vehicular and pedestrian circulation would remain largely the
same with some slight modifications to accommodate the parking garage on the southwestern portion of
the site and the enhanced vehicular roundabout off of Glynnis Rose Drive.
An extensive discussion on parking is included above in the section titled, Conditional Use Permit. In
short, the Project, as proposed, meets the parking requirements set forth in Chapter 8.76, Off-Street
Parking and Loading Regulations of the Dublin Zoning Ordinance and would provide adequate parking
for both Phase One and Phase Two of the Dublin Gateway Medical Center project. The majority of
parking would be provided in the parking garage with some surface parking adjacent to the hospital and
medical office buildings. The two vehicular access points to the parking garage would be located on the
north elevation and the east elevation.
Architecture (Exhibit A. Attachment 3)
The 6-story hospital building would be located on the southeast corner of Dublin Boulevard and Glynnis
Rose Drive. The building reflects four-sided architecture by utilizing a combination of both vertical and
horizontal pre-cast panels on all elevations and introducing aluminum clad canopies on every elevation.
To avoid a monotonous repetition of architectural elements and enhance the visual interest of the building,
one-story and three-story elements are introduced on each elevation and are strategically placed to relate
the building to adjacent structures. The height of the building at its tallest point is 102-feet, 6-inches. The
colors, materials, and architectural elements proposed for the hospital building are consistent with those
approved for the Phase One medical office buildings which include smooth finish and aggregate pre-cast
concrete panels, green tinted glass, and aluminum canopies and fins. What differentiates this building
from the existing medical office buildings is the height. At 102-feet, 6-inches the hospital building makes
a strong statement at the corner of Dublin and Glynnis Rose. In order to address the perceived massing of
the building, the horizontal elements draw the eye in a linear direction rather than upward. In addition,
articulating the building with the introduction of exterior elements at varying heights also adds visual
interest.
North Elevation: On the north elevation, which faces Dublin Boulevard, the building includes a curved
exterior wall with a combination of colored glass and pre-cast concrete panels. To break up the massing
of the building, a 3-story element is introduced on the east end of the elevation and is oriented towards the
existing 3-story medical office building. On the west end of the north elevation, a I-story element is
8 of 15
introduced to tie into the I-story Bank of America building located west of Glynnis Rose Drive. Both
elements are topped offwith an aluminum clad canopy.
East and West Elevations: The 3-story element from the north elevation wraps the building onto the east
elevation and provides a logical transition to the adjacent 3-story medical office building. Similarly, the
one story element from the north elevation wraps the building onto the west elevation to tie into the 1-
story Bank of America building. Also on the west elevation is the introduction of another 3-story element
to break up the massing of the 6-story building. This element has been strategically placed in order to
screen the loading dock area which is parallel to Glynnis Rose Drive.
South Elevation: The south elevation, which includes the main entrance to the hospital, faces the parking
lot. An aluminum clad canopy covers the entry to the building and provides a single story element along
this elevation. On the east and west ends of this elevation, there are 3 story elements which have wrapped
around from the east and west elevations.
Parking Garage: The 5-level parking garage is not proposed to be any different with respect to colors,
materials and architectural details from the parking garage approved in 2005; the only change to the
parking garage is the introduction of one additional level of parking which will be provided below
ground. The exterior elevations include a combination of pre-cast concrete panels to match the hospital
and medical office buildings and a decorative metal screen. The parking garage would be located on the
southern end of the site and would not be readily visible from Dublin Boulevard or Tassajara Road; short
breaks between buildings along these two street frontages would provide views of the parking garage but
to a limited degree.
Public Art
The original 1998 approvals for the Koll Dublin Corporate Center included a requirement that public art
be provided at the corner of Dublin Boulevard and Tassajara Road as part of the development of Lot 7
which is now the Dublin Gateway Medical Center. A public art piece has been installed and satisfies the
public art requirement under the 1998 approvals.
In September 2006 the City adopted a Public Art Ordinance which now requires developers to install
public art as part of new development projects. While the proposed Project falls within the definition of a
new development project it is not subject to the Public Art Ordinance since the 2005 approval of Vesting
Tentative Parcel 8524 for the Dublin Gateway Medical Center precedes the adoption of the Public Art
Ordinance; however, the Developer has agreed to provide a piece of public art in conjunction with the
proposed Project (Condition of Approval No. 13). The proposed location for the public art piece would
be within the vehicular roundabout off of the Glynnis Rose Drive entrance to the Project.
ENVIRONMENTAL REVIEW
In accordance with the California Environmental Quality Act (CEQA) the Project has been reviewed for
environmental impacts and an Initial Study has been prepared. The Project is located within the Eastern
Dublin Specific Plan area and is part of the project area covered by the Eastern Dublin General Plan
Amendment and Specific Plan Environmental Impact Report (the "Eastern Dublin EIR") certified by the
City Council in 1993 (SCH No. 91103064) and the Santa Rita Property Mitigated Negative Declaration
certified by the City Council in 1996 (SCH No. 96082092). With regards to cumulative traffic impacts at
the Dublin/Dougherty intersection, the Project is covered by the Dublin Ranch West Environmental
Impact Report (the "Dublin Ranch West EIR").
The Initial Study prepared for the Project evaluated the Project at a site specific level for potential impacts
which had not already been analyzed as part of the Eastern Dublin EIR and Dublin Ranch West EIR.
90f15
Based on the analysis contained within the Initial Study, no new environmental impacts were identified;
therefore, an Addendum has been prepared. As provided for in Section 15164 of the CEQA guidelines,
an Addendum need not be circulated for public review but shall be considered with the prior EIR(s)
before making a decision on the Project.
Four of the sixteen categories contained within the Initial Study were specifically identified for Project-
specific review. A visual analysis was prepared to address potential aesthetic impacts resulting from the
relocation of the 6-story building. Hazards and hazardous materials were analyzed at a Project-specific
level because such analysis was not undertaken as part of the Eastern Dublin EIR and noise was analyzed
for potential environmental impacts resulting from the emergency room operations. Lastly, transportation
and traffic was analyzed for the change in use from medical offices to a hospital and for impacts to the
Dublin/Dougherty intersection.
Aesthetics (Exhibit A. Attachment 1)
The 1998 Stage 1 and 2 Development Plan for the Dublin Corporate Center anticipated the development
of a 6-story signature office building at the corner of Dublin Boulevard and Tassajara Road. A project-
specific visual analysis was prepared in 1998 as part of the Koll Dublin Corporate Center Vesting
Tentative Map and Site Development Review analyzing a 6-story building at the corner of Dublin
Boulevard and Tassajara Road along with three, 4-story buildings adjacent to Interstate 580. The visual
analysis concluded that no additional significant impacts beyond those addressed in the Eastern Dublin
EIR were identified for the project.
At the time of the 2005 approvals for the Dublin Gateway Medical Center, changes in market conditions
resulted in the developer requesting approvals for two, 3-story medical office buildings and one 3-story
lifestyle/wellness building rather than the previously analyzed 6-story signature office building. The three,
4-story office buildings (Phase I) adjacent to Interstate 580 had been constructed prior to the 2005
approvals and are still in existence. Because the 3-story medical office buildings were lower than the
three, 4-story office buildings adjacent to Interstate 580, it was determined that no visual impact would
result.
The current Project proposes to reintroduce the 6-story building for a hospital use in a slightly different
location than what was previously analyzed; therefore, a new visual analysis was performed to determine
if any adverse aesthetic impacts would result. Due to the fact that the surrounding properties are largely
built out with one-, two-, three- and four-story buildings and based on the results of the visual analysis, a
determination has been made that the Project will not have any significant impacts to aesthetics. The
proposed 6-story building incorporates 3-story elements which provide a transition from the taller 6-story
structure to lower 3-story and I-story buildings in close proximity to the Project.
Hazards and Hazardous Materials (Exhibit A. Attachment 1)
As part of the development of Phase One of the Dublin Gateway Medical Center, a Phase I Environmental
Site Assessment was performed by URS Corporation dated November 1, 2004 and concluded that the
probability of environmental contamination, impairment or liability associated with the Project site was
low to moderate. Additionally, the Project site is not located on a hazardous waste and substance site
pursuant to Government Code Section 65962.5. The Project would require the transport, use and disposal
of hazardous materials such as, pharmaceuticals and bio-hazardous waste. State law requires all hospitals
to be licensed by the State and comply with strict regulations for the handling, storage and disposal of
hazardous materials. Therefore, the Project will not have any significant impacts as a result of hazards
and hazardous materials.
100f15
Noise (Exhibit A. Attachment 1)
The Project proposes to include an emergency room which would introduce a new source of noise as a
result of the Project which would otherwise not be present on the Project site if a medical office building
were to be established. Ambulance sirens associated with the emergency room operations were analyzed
to determine the level of impact to the Project site and surrounding properties.
The proposed emergency room would create a destination for ambulances and as a result would introduce
noise associated with sirens to the Project site. The use of sirens is regulated by the California Highway
Patrol and the protocols for siren use and maintenance are set forth in Ambulance Driver Handbook
published by the Department of Motor Vehicles. According to the Handbook, Code 3 operations, which
is a term used to describe the use of red warning lamps and sirens in response to an emergency call, are
only to be used when initially responding to an emergency call or when speed in obtaining emergency
medical care appears essential to save a life, prevent undue suffering, or to reduce or prevent disability.
The Handbook further states that the use of sirens shall be restricted to situations where they are most
effective.
Ambulances are not proposed to be stored at the Project site and therefore would not be dispatched from
the Project site. As a result, siren noise associated with the transport of a patient to the Project site is
more probable than siren noise associated with an ambulance being dispatched from the Project site. In
addition to siren noise being limited to the transport of a patient to the Project site, there are two other
hospitals within the Tri-Valley, San Ramon Regional Medical Center in San Ramon and ValleyCare
Hospital in Pleasanton, which could also be destinations for the transport of patients depending on the
type and severity of the injury.
In analyzing the totality of the circumstances in which ambulance sirens would be utilized in connection
with the Project's emergency room operations, a determination has been made that the noise impact
would be less than significant.
Transportation/Traffic (Exhibit A. Attachment 1)
The proposed Project would generate slightly more A.M. peak hour trips and slightly fewer P.M. peak
hour trips than the previously approved medical office building. According to the Institute of Traffic
Engineers, a project that generates fewer than 100 additional A.M. or P.M. peak hour trips does not
require additional traffic studies; therefore, the additional A.M. peak hour trips expected by the Project is
negligible and would not have a significant effect on the environment. However, the additional trips
generated by the Project would contribute to the cumulative build out impacts from development in
eastern Dublin on Interstate 580, the Santa Rita Road/Interstate 580 ramps and the Dublin
Boulevard/Dougherty road intersection. These cumulative build-out traffic impacts were fully analyzed
as part of the Eastern Dublin General Plan Amendment and Specific Plan Environmental Impact Report
(the "Eastern Dublin EIR") and the Dublin Ranch West Environmental Impact Report (the "Dublin Ranch
West EIR") and no significant impacts beyond those previously identified would result from the Project.
Therefore, the City prepared an Addendum which is attached as Exhibit A to Attachment 1.
DEVELOPMENT AGREEMENT
One of the implementing measures of the Eastern Dublin Specific Plan is the requirement that the City
enter into a Development Agreement with developers within the Plan area. The Development Agreement
provides security to the developer that the City will not change its zoning and other laws applicable to the
project for a specified period of time (the so-called "vesting period"). The City offers developers in
Eastern Dublin, where development agreements are required by the Specific Plan, a 5-year vesting period.
The benefit to the City of entering into a Development Agreement with the property owner is that the
11 of 15
document is a contract that ensures that the goals of the Eastern Dublin Specific Plan are met and the
infrastructure facilities for the area are constructed with each development phase. Additionally, it ensures
that dedications of property and easements are made, project phasing is followed, the appropriate fees are
paid for the development, and any additional terms of the Agreement are met as the development
proceeds. Due to the length of time it takes to process hospital building permits through state regulatory
bodies, the developer has requested a longer vesting period of 10 years. In exchange for this extended
vesting period, City staff requested and the Developer agreed to include a provision in the Development
Agreement that would require the Developer to provide a Community Benefit Payment (described at the
end of this page and on page 13 in the section titled, Consistency with the General Plan, Eastern Dublin
Specific Plan, Planned Development Zoning District (PA 98-047), as Amended, and the Dublin Zoning
Ordinance) upon the happening of certain events.
The Approval of Development Agreements is by adoption of an Ordinance by the City Council upon a
recommendation by the Planning Commission. The proposed Development Agreement between the City
of Dublin and Triad Dublin Gateway LP is contained in Exhibit A of Attachment 4, which is the
Resolution recommending City Council approval of the Development Agreement. The format and
structure of the Development Agreement for the Dublin Gateway Medical Center Building 3 Hospital and
Garage project is based on the standard Development Agreement developed by the City Attorney and
adopted by the City Council for projects within the Eastern Dublin Specific Plan area.
The City Attorney drafted the proposed Development Agreement for the Project with input from City
Staff, the Property Owner and Developer, and their attorneys. The Development Agreement sets forth the
agreement between the parties in relation to many items, including, but not limited to, phasing, project
and off-site infrastructure, and payment or waiver of fees. The Development Agreement runs with the
land and the rights thereunder can be assigned.
NOTICING
In accordance with State law, a Public Hearing Notice was mailed to all property owners and
occupants/residents within three hundred feet of the Project site and to all parties requesting such notice;
the Public Hearing Notice provided a description of the Project including the location, approvals sought
and environmental review undertaken and advertised the Public Hearings scheduled for April 24, 2007
(Planning Commission) and May 1,2007 (City Council). The Public Hearing Notice was also published
in the Valley Times and posted at several locations throughout the City.
REVIEW BY ApPLICABLE CITY DEPARTMENTS AND AGENCIES
The Public Works Department, Building Division, Dublin Fire Prevention, Dublin Police Services,
Dublin San Ramon Services District (DSRSD) and Alameda County Planning Division were given the
opportunity to review and comment on the Project; all comments and/or conditions of approval submitted
by these departments and agencies have been addressed with the Applicant and incorporated into the
Project.
CONSISTENCY WITH THE GENERAL PLAN, EASTERN DUBLIN SPECIFIC PLAN, PLANNED DEVELOPMENT
ZONING DISTRICT (P A 98-047), As AMENDED, AND THE DUBLIN ZONING ORDINANCE
The Project is located within the Eastern Extended Planning Area and is designated as Campus Office in
the General Plan and Eastern Dublin Specific Plan land use maps. The Project is consistent with this land
use designation in that: 1) it is an employment generating use that will provide a range of service and
professional jobs within the City and the surrounding Tri-Valley region; and 2) it provides an attractive,
campus like setting for medical office uses. Additionally, the General Plan and Eastern Dublin Specific
Plan allow for a floor area ratio (FAR) of .25-.80 for Campus Office land uses. The FAR for the Project
120f15
has been calculated in conjunction with the larger Koll Dublin Corporate Center, of which the Project is a
part, and the increase in square footage does not exceed the maximum allowable FAR for Campus Office
land uses (.80). The Koll Dublin Corporate Center was approved in 1998 with an FAR of .33; the Project
increases the FAR to .47 which is still within the allowable range.
The Project is located within the Tassajara Gateway Subarea of the Eastern Dublin Specific Plan. This
area encourages the development of uses that will benefit from the close proximity to the area's three
major corridors (1-580, Dublin Boulevard and Tassajara Road). Due to the area's visibility from these
corridors, the land uses within this area should present a high profile, quality image. The Project is
consistent with the Tassajara Gateway Subarea in that: 1) the hospital use is located in a manner which
makes it readily visible to the public; and 2) the Project incorporates design features (i.e. pre-cast concrete
panels, green tinted glass, aluminum canopies and fins, varied building heights), public art and site
landscaping.
The Eastern Dublin Specific Plan allows for the development of general commercial uses through a
Planned Development Zoning process; the Planned Development Zoning District (P A 98-047) in which
the Project is located allows for the establishment of a hospital with approval of a Conditional Use Permit
and a parking garage is a permitted use.
Section 8.100.160.G of the Dublin Municipal Code requires a finding that the Project is consistent with
applicable specific plans for approval of a Conditional Use Permit. One goal of the Eastern Dublin
Specific Plan is that new development pays for needed services [See Eastern Dublin Specific Plan, section
10.4; Policy 10-1]. The Eastern Dublin Specific Plan anticipates that revenues to pay for public services
will come from property taxes, among other revenues (section 10.2), and the Specific Plan indicates that
the monies from the Specific Plan area are anticipated to be enough by 2014. A fiscal study was done for
the Specific Plan that shows revenues and expenses, based on the assumption that property tax revenues
are received from all properties.
Property tax revenues were a significant component of the anticipated revenues needed to pay for public
services when the City adopted the Eastern Dublin Specific Plan. Chapter 3.12 of the Eastern Dublin
General Plan Amendment and Specific Plan Environmental Impact Report (the "Eastern Dublin EIR")
discussed operating costs and revenues, concluding that property tax revenue was the primary form of
new revenues. Impact 3.12/ A finds that project-generated revenues will be sufficient to cover project-
generated costs after shortfalls in the early years assuming at least 25 percent share of property taxes. No
mitigation was therefore required as part ofthe Eastern Dublin EIR.
If the proposed hospital is a non-profit hospital it is entitled to an exemption from property tax pursuant to
state law (Rev. & Tax Code section 214). In order to mitigate this loss of property tax revenues and in
order to find a hospital that is consistent with the Eastern Dublin Specific Plan if it is a non-profit
hospital, Staff recommends that the Conditional Use Permit include a condition of approval that requires a
payment, called a "community benefit payment", if the hospital will be a non-profit hospital. The
payment would be in the amount of $2,093,872, which will be paid at the time of issuance of a
grading/site-work permit for the hospital or at any time during the term of the Development Agreement if
the hospital is constructed as a for-profit hospital and converts to a non-profit during the term of the
Development Agreement. Because of the difficulty of calculating the loss of property tax revenues (i.e.
due to assumptions that must be made about the assessed value, the rate of the tax the City would receive,
adjustments to the assessed value, and the duration of the exemption) and creating an enforceable
mechanism for collecting the lost revenues, Staff recommends a flat payment. The Applicant is in
agreement with this condition. A similar provision is included in the Development Agreement.
The Project is consistent with the Zoning Ordinance in that it has been designed, and conditions of
approval have been applied, to ensure compliance with all development regulations and standards not
13 of 15
otherwise specified in the Stage 1 and 2 Development Plan, as amended, for the Planned Development
Zoning District (PA 98-047).
CONCLUSION:
This application has been reviewed by all applicable City departments and agencies, and their comments
have been incorporated into the Conditions of Approval for the Project. The proposed Project, as
conditioned, is consistent with the General Plan, the Eastern Dublin Specific Plan and the Planned
Development Zoning District, as amended, in which the Project is located and represents an appropriate
Project for the site.
RECOMMENDATION:
Staff recommends that the Planning Commission: 1) Receive Staff presentation; 2) Open the public
hearing; 3) Take testimony from the Applicant and the public; 4) Close public hearing and deliberate; 5)
Adopt Resolution (Attachment 1) recommending City Council adoption of a CEQA Addendum; 6) Adopt
Resolution (Attachment 2) recommending City Council adoption of a Planned Development Rezone and
Stage 1 and 2 Development Plan; 7) Adopt Resolution (Attachment 3) recommending City Council
approval of a Conditional Use Permit and Site Development Review; 8) Adopt Resolution (Attachment 4)
recommending City Council adoption of a Development Agreement.
140f15
GENERAL INFORMATION:
APPLICANT/
PROPERTY OWNER:
Joseph D. Carroll, Triad Dublin Gateway, L.P., 8001 Irvine
Center Drive, Suite 10000, Irvine, CA 92618
LOCATION:
4084 and 4100 Dublin Boulevard
ASSESSOR PARCEL NUMBER(S):
986-0016-021 and 986-0016-022
GENERAL PLAN
LAND USE DESIGNATION:
Campus Office
SPECIFIC PLAN/
LAND USE DESIGNATION:
Eastern Dublin Specific Plan, Campus Office
ZONING:
PD, Planned Development (PA 98-047)
SURROUNDING USES:
Location Zoning General Plan Land Use Current Use of
Property
Site PD Campus Office Medical Office
Planned Development
North PD General Commercial Retail Commercial
Planned Development
South PD Campus Office Professional Office
Planned Development
East PD General Commercial Vacant
Planned Development
West PD Campus Office Retail Commercial
Planned Development
15 of 15