HomeMy WebLinkAboutReso 108-07 Shannon Center Change Order RESOLUTION NO. 108 - 07 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DUBLIN ********** AUTHORIZING THE CITY MANAGER TO APPROVE A CHANGE ORDER OF UP TO $75,000 FOR ADDITIONAL GRADING WORK DUE TO UNFORESEEN CONDITIONS WHEREAS, the City of Dublin did, on March 20th, 2007, award the contract for Shannon Community Center Contract No. 07-02, for the amount of $8,572,332; and WHEREAS, Construction Demolition has uncovered unforeseen conditions; and WHEREAS, these unforeseen conditions have resulted in unanticipated costs to the contractor; and WHEREAS, the work is necessary to complete the construction of the project and remain on schedule; and WHEREAS, the Contract authorizes the City Manager to approve change orders for additional work up to $25,000, and Council approval is required for change orders in excess of the City Manager's authority. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby authorize the City Manager to approve a change order of up to $75,000 for additional grading work made necessary due to unforeseen conditions. PASSED, APPROVED AND ADOPTED this 28th day of June, 2007, by the following vote: AYES: Councilmembers Hildenbrand, Oravetz, Sbranti and Scholz, and Mayor Lockhart NOES: None ABSENT: None ABSTAIN: None ATTEST: (l~ ( (J~ '--, City Clerk I Oepvt:J Reso No. 108-07, Adopted 6/28/07, Item 4.3 Page 1 of 1