HomeMy WebLinkAboutItem 8.1 DataProcssngImprov&InfoSysPln "".- , CITY OF DUBLIN . AGENDA STATEMENT CITY COUNCIL MEETING DATE: October 3, 1994 SUBJECT: Authorization to Solicit Proposals - Data Processing Improvement Project and the Information Systems Master Plan tt:J (Prepared by: Bo Barker, Management Assistant) EXHIBITS ATTACHED: 1.~fOrmatiOn Systems Master Plan 2. /Bid Specifications for the Purchase of Computer Equipment RECOMMENDATION: 1. ~ 3. Adopt the Information Systems Master Plan Authorize Staff to be relieved of the competitive bidding process based on Dublin Municipal Code Section 2.36.050(b)(6) Authorize Staff to distribute the Bid to qualified vendors FINANCIAL STATEMENT: The proposed purchase represents approximately $130,000 or 85% of the total budget for this Capital Improvement Program (CIP). DESCRIPTION: The 1994-95 Capital Improvement Program (CIP) includes the installation of a local area computer network (LAN) in the Civic Center. In determining what needs to be " done, Staff completed an extensive review of the City's Information Systems. This Staff report presents the results of this review in the "Information Systems Master Plan" (Exhibit 1). Additionally, Bid Specifications for the Equipment to be purchased in Fiscal Year 1994-95 are included as Exhibit 2. The Master Plan The mission in creating the master plan was to first analyze the problems and qualities of the City's rorrent computer system. Next, the functions of the staff were examined to determine how the introduction of new technology could improve efficiency. Finally, the plan attempts to provide a guide for implementing technology over the next five years. By providing a guide, the City will no longer need to evaluate technology on a year-to-year basis, but can base information systems decisions in an organizational wide context over the long term. Reviewing the Master plan was included in the Scope of Work for the City's computer consultant. This review was completed and a number of modifications have been made in the content of the plan. The main focus of the consultant was to verify that the proposed equipment and software are able to work together, technologically speaking. Furthermore, the consultant concurs that the proposed applications for the next five years are appropriate system solutions. One word of caution made by the consultant is that five years is a long period in terms of technology. Specifically, the City should expect the estimated costs in the plan to be different (higher or lower depending on the application or hardware) from the final costs. This comment should not be alarming however, as Staff would certainly evaluate the cost/benefit of these applications prior to their purchase. The initial phase (FY 1994-95) of the master plan solution is the installation of a personal computer local area network (LAN). The LAN. will provide the City with the ability to share information and resources such as printers, software and databases. Through sharing resources (printers, etc...) all employees are provided with access to the same high quality tools while the costs of the tools are shared by every department. This configuration is commonly referred to as a "client/server" network. Once the LAN is installed, other appropriate applications can be implemented. The applications included in the rorrent five year CIP are as follows: 1) Police Evidence and Fixed Assets Inventory (FY 94-95) 2) Records management/document imaging system (FY 95-96) 3) Permit Tracking System (FY 95-96) 4) AutoCAD (Computer Aided Design (FY 95-96) 5) Geographic Information Systems. (FY 96-97) 6) Transition from the IBM System/36 (FY 97-98) Although these applications may require additional equipment, the goal is to assure that the information they produce will have the ability to be shared by every employee on the LAN. ... COPIES TO: CITY CLERK FILE ~ ITEMNO.&.1.- . . Historically, information technology has been purchased on a year-to-year basis. The Master Plan provides a management tool through which decisions relative to the long term direction of technology can be applied to City operations. Bid for Computer Equipment Included as Exhibit 2, are the Bid Specifications detailing the following main components for the Fiscal Year 1994-95 LAN installation: 1. Replacement of 24 personal computer workstations and printers which have been fully depreciated in the Internal Service Fund. 2. Purchase of one network file server. 7 new personal computers; (4 for the police department, 2 for the Public Works Department and 1 for the Building Department). 3. Purchase of Software including: the network operating system, Word Processing, Spreadsheet, Database, and Desktop Publishing programs. These applications will be available to everyone on the network. The computer industry offers many different types of machines assembled in many different ways. In order to determine the appropriate equipment for the City, Staff has undertaken a thorough review of options using industry literature, technical specifications, and personal interviews. Using minimum specifications designed by Staff and the City's computer consultant, vendors will have the opportunity to bid on four specific manufactured machines. The proposed manufacturers are Hewlett Packard, Compaq, mM and Dell. These four are recommended based on quality and performance reviews, price estimates, warranty, and overall value of the equipment. Structuring the bid this way not only allows the City to look at a four different manufacturers and the associated prices but also eliminates the possibility of receiving quotes on sub-par equipment. The bid methodology is designed to assure the City receives quality equipment for the best price. Staff has compiled a list of vendors that appear to be able to meet the requirements of the bid. This list was composed from interested parties calling the City as well as vendors used by the City in the past. The notice to bidders will also be advertised with the Chamber of Commerce and posted in two other locations in the City. Qualified vendors must not only be able to supply the hardware, but must also be able to support the installation process. The final award will be made at a future City Council meeting. The City Council must give authorization to release the bid since the cost of the total award will be over $5,000 and because the bid limits vendor proposals. The City Council is able to do so under Dublin Municipal Code Section 2.36.050 (B) (6) which states: "The provisions of this chapter requiring competitive bidding shall not apply when a purchase involves goods of a technical nature where it would be difficult for a vendor to bid on a standard set of specifications, the purchasing agent shall undertake a thorough review of known products which would meet the City's needs at the lowest costs." In addition, to the items listed above, Staff will be soliciting separate proposals for three other main hardware items. The three items listed below are proposed to be bid separately because they are distinct in their features as compared to the equipment listed above. 1) Portable Computer: This computer will used for City Council, Planning Conunission and Parks and Community Services Meetings for minutes. It is recommended that it bid separate from the main hardware purchase as there are portable computer manufacturers that can provide a high quality deal on the portable, but not necessarily on file servers and workstations. The projected cost for the portable is $2,700. 2) 5ystem/36 Gateway: A Gateway is composed of adapter cards and software that provide access to the System/36. This is a highly specialized component of the network which is better handled through direct negotiations with the companies that make the equipment. The projected cost of the Gateway is $4,000. 3) External Modem: This unit will provide access to the network from remote locations. The projected cost of the modem is $400. Since the cost of these individual items will be lower than $5,000, no action is required by the City Council. However, it is appropriate to list these items as they are part-of the equipment acquisition for Fiscal Year 1994-95. ,;.' . . City of Dublin Information Systems Master Plan EXHIBIT - J- : . Table of Contents . Objective............................................................................................................. ................ ........ ....... 2 Introduction..................... .................................... ........................ ..................................................... 2 Informa tion abou t Informa tion ................................................ .................................. ......... ............ 3 The Information Future........................................... ........... ......... ............................ ..... ...... 4 Information abou t the Ci ty of Du bUn ............................................................................................. 4 The Curren t Information System.................................... ....................... ...... ....................... ............ 5 Compatibility ................... ............................................ ........... .............. .......... .......... .......... 8 Integra tion and Access ............................................ ................. ................ ........ .................. 10 Performance ................................ ................................... ........ .............................. ............... 10 IBM System/36 ....................... .................................... ......................................... ............... 11 Summary of Current Environment ................................................................................... 11 System Migra tion ........................................................................................................ ............... ...... 12 The Network .................................................... ................ ............. ........ ................ .............. 13 Justification for a PC Network........................................................................................... 14 Word and Excel for Windows.............................................................................. 15 Electronic Mail..................................................................................... .................. 16 Data Security, Integrity and Backup.................................................................... 16 Land Based Information/Permit Tracking System ............................................ 16 Au toCA D ............................................................................................................... 18 Geographic Information System (GIS) ................................................................ 19 Network Personnel.. ................................ ......... .......................... ................ ...................... ................ 20 Network Costs and System Implementation Schedule ................................................................. 21 Fiscal Year 1994-95 - Year 1................................................................................................ 21 Fiscal Year 1995-96 - Year 2................................................................................................ 22 Fiscal Year 1996-97 - Year 3................................................................................................ 22 Fiscal Year 1997-98 - Year 4................................................................................................ 22 Fiscal Year 1998-99 - Year 5............................... ................................................................. 22 Appendix.............. ......... ............. ....... .............. ....... ................. .... ......... ... ........... ............. .... .............. 23 : . . Objective The need for an information systems master plan has become prevalent in light of a number of issues the City is facing. Most notably, the City is involved in a Geographic Information System (GIS) planning process with the Cities of Pleasanton Livermore and San Ramon, the Dublin San Ramon Services District (DSRSD), and the Dougherty Regional Fire Authority (DRFA). These agencies are exploring the feasibility as well as the desirability of a joint GIS. Additionally, the City's current information system is relatively old and is beginning to experience various mechanical difficulties such as monitor and processor failure. The current hardware will continue to fail and therefore a plan for the transition of the system is necessary to allow the organization to efficiently utilize data processing technologies that make sense for the City at an affordable cost. Introduction The world of information technology (IT) is moving at a rapid pace. It is difficult for policy makers and administrators to know exactly how to make decisions relating information processing systems. What is current technology today may be outdated tomorrow. Therefore, this master plan is predicated upon the theory that the successful organizations are not necessarily the ones which have the latest and most extensive deployment of new data processing technologies. In fact, success comes from institutions that manage the introduction of new information system products and services as part of a master planning process which addresses the needs of the organization. The goal of this master plan is to provide the City of Dublin with a customized planning document that serves as the framework for data processing technology decisions over the next five years or through the year 1999. In general, information systems should act as tools that enable employees to carry out the policies, goals and objectives established by the City Council. Therefore, the master plan will focus on information resources which promote the accomplishment of the City's goals. Using an organization wide context, as opposed to a department by department approach, will accomplish the following positive attributes by: 1) Maximizing the uses of information resources 2) Maintaining a good return on the information technology investment 3) Standardizing information processing functions 4) Providing the city an overall view of its information system management functions In the end, the analysis presented will provide the City with a master plan that, among other benefits, will eliminate future guess work associated with information system decisions. The content of the Master Plan will be presented in the following manner. -2- - 1. Information about Inform 5. System migration tha ts City needs 2. Information on the City of Dublin 6. Implementation schedule and costs 3. Looking at the Current Information System 7. Strategies for the next five years 4. Problems and needs identification 8. Glossary of Terms Information about Information Information is a key aspect of any local government operation. Information is to local government what manufactured goods are to private industry. Information about parcels, streets, sidewalks, financial status, leisure opportunities as well as the production of information. Staff reports, letters and correspondence, budget preparation and other various analytical functions are the information products of local government. Information systems are quite different from what they were as recently as 10 to 15 years ago. Public organizations have gone through three phases in their response to the rapidly emerging information technology.1 The first phase in the late 1950's and early 1960's was characterized by experimentation with the newly developed digital computing technology. This technology was beneficial to large batch processing operations that were routine and repetitive. This phase included functions such as payroll, motor vehicle registration and tax processing. Later in the 1960's and early 1970's, the second phase consisted of the advent of the large mainframe computer. Mainframes were generally only afforded to large organizations who could justify the cost benefit of the expensive systems. Smaller agencies purchased services from the larger central systems or simply used manual systems. The third phase that emerged in the late 1970's and the 1980's with the introduction of micro electronic circuitry. In essence, personal computers were born. The introduction of this technology was significant as the price of mini and micro tomputers plummeted. Consequently, the acquisition of equipment has become more affordable and accessible. In the early years of the first personal computers (PC's), software and hardware manufacturing companies where scrambling to get their products to market. This created compatibility problems as the computer industry was defining what would become the standard. Although there are some exceptions such as the Macintosh, most PC's are built around the IBM compatibility standard with the MS- OOS operating system. (See glossary for more specific definitions about compatibility and operating systems.) The first PC was the IBM XT which was introduced in 1983. Today, Intel, AMD and IBM have all produced faster micro-processors that have been generally classified by the catch phrases of "286", "386" and "486." More lAndersen, D and Dawes, 5.1991. Government Info~ation Managemenl Prentice Halt New Jersey. -3- : recently Intet has released the t.tium" chip which claims to be 70% faster t. the "486." In contrast IBM and Motorola have produced the "PowerPC" chip. The ''Power PC is a new product and currently is not completely compatible with all business software. Overall, the personal computer is overcoming mainframe and mini computing platforms as the most utilized piece of information technology. The Information Future As the revenues for California Cities continued to decline, and with the general theme that government must "do more with less," PC's will play an increasingly important role in information processing. However, technology will continue to change and that is why it is recommended that the City of Dublin disregard the "latest and greatest" approach to information systems. In other words, the City should not simply purchase the latest releases of technology without first analyzing how the product will help staff to do their jobs better. , The small size of the City combined with the absence of a dedicated Management Information Systems (MIS) deparbnent mandate that only proven technological resources should be introduced. This master plan utilizes the basic assumption that PC technology will continue to be the tool of choice within the operational framework of the City. Historically, Intel has held the majority of the micro processing market. As noted previously, IBM, AMD and others have begun to make headway into this market. The significance is that processors types (Intel vs. power pc), to an extent, begin to redefine the hardware architecture standard. For this reason, it is recommended that the City focus on being consistent with the processor /hardware architecture, not just with purchasing from one hardware manufacturer, i.e. IBM PS/2. This issue will be more clearly defined later in the Master Plan. Information about the City of Dublin In the early years after incorporation, City staff utilized a word processing system called Syntrex. This was a micro chip based word processor which, by today's computing standards, could be viewed as an elaborate typewriter. Beginning in 1988, IBM personal computers (PCs) were introduced into city operations along with the IBM System/36 Minicomputer (System/36). Today, a common city employee workstation includes a PC running various word processing and spreadsheet programs with about 15% of the employees being able to access information from the System/36. The City also staffs three remote facilities including the Shannon Community Center, the Dublin Swim Center and the Dublin Senior Center. The Shannon Center operates two personal computers, and utilizes a "dummy" workstation to communicate via a modem with the IBM System 36 located at the Civic Center. The Senior Center utilizes one stand alone Pc. The Swim Center does not house any data processing equipment. Overall, the City has positioned itself well regarding the current information system. Capital expenditures have been incurred only to acquire new equipment to replace failed equipment or to satisfy immediate short f -4- : . . term needs, such as buying equipment for new staff. This ultimately maximizes the return on inveshnent of the current computer equipment since the equipment is utilized through its entire depreciation schedule. Additionally, there has not been an introduction of different hardware/software operating system platforms, i.e. Macintosh, etc. This allows flexibility in planning a new system. Multiple operating systems limit the flexibility of any system changes or additions. However, this is not to say the system is perfect. As will be noted later in the Master Plan, there are numerous problems associated with the aging data processing system. In addition to the problems with the current system, greater efficiencies could be realized by updating certain aspects of the information system. The justification for this assertion will be covered in greater detail as this plan develops. The Current Information System In the simplest terms, computers are tools that allow employees to perform tasks quickly and more efficiently than they could without computers. The table below displays the primary system functions currently utilized by City staff and is differentiated by the hardware platforms. Primary Functions of System Hardware Personal Com uters (PC's) 1. Word Processin S stem/36 aration 1. General Led er 2. Accounts Receivable 3. Accounts Pa able 4. Pa roll 5. Ci Clerk Records Index 6. Recreation Schedulin 2. S readsheet 4. Databases 6. S stem/36 Workstations 7. Business License Records The current system hardware consists of IBM-compatible pes and an IBM System/36 mini computer. The specific hardware brands are: IBM 8088 Model 30 IBM 286 Model 50 IBM 386 Value Point IBM 286 Model 30 IBM 386 Model 70 IBM 5262 System 36 IBM 486 Value Point -5- : The primary software used bY' Staff is sorted by the hardware PlatfOrm'resented below. S stem/36 Software BRC* - General Led er BRC - Business Licenses Muni-Metrix LeisureSoft BRC Pa ate It BRC - Business Records System When combining the different features listed above, the overall system distribution is shown in the following table. PC Software Microsoft Word for DOS Framework III Microsoft Word for Windows Microsoft Excel Lotus 1-2-3 Aldus Pa emaker Microsoft Access Word erfect Hard ware Word Spreadsheet Database Desktop System 36 Processing Publishing Administrative Services Assistant CM/ ASD IBM/30 - 286 DOS Word Lotus 1-2-3 Yes Finance Technician II IBM/30 - 286 Framework Framework Yes Finance Technician II IBM/30 - 286 Framework Framework Yes .5 Office Assistant IBM/30 - 286 DOS Word Yes Assistant to the CM IBM/30 - 286 Framework Framework Yes Management Assistant IBM/VP - 486 Win Word Win Excel Access Pagemaker Community Safety Assistant Citll Mana~er's Office City Manager IBM/30 - 286 Framework Yes City Clerk IBM/30 - 286 DOS Word Yes Economic Dev. Manager Administrative Secretary IBM/30 - 286 DOS Word Yes Recreation Recreation Director IBM/30 - 286 Framework Framework Yes Recreation Coordinator IBM/70 - 386 Win Word Pagemaker Administrative Secretary IBM/30 - 286 DOS Word Recreation Supervisor IBM/VP - 386 Win Word Pagemaker Yes Senior Coordinator IBM/VP - 486sx Win Word Pagemaker Office Assistant IBM/30 - 286 DOS Word Recreation Coordinator IBM/30 -286 Yes -6- : Planning Planning Director IBM/30 - 286 DOS Word Yes Senior Planner IBM/VP - 386 Win Word Senior Planner IBM/30 - 286 DOS Word Associate Planner IBM/VP - 386 Win Word Associate Planner Administrative Secretary IBM/VP - 386 Win Word Assistant Planner IBM/30 - 286 DOS Word Office Assistant IBM/VP - 386 Win Word Additional Computer IBM /8088 DOS Word Public Works Public Works Director Senior Civil Engineer Public Works Inspector Public Works Inspector AT& T Bernuli Engineering Technician IBM/40-sx DOS - Word R-Base Administrative Aide IBM/50 286 DOS Word Lotus 1-2-3 Yes Office Assistant IBM/30-286 DOS Word Maintenance Superintendent Building Building Official Building Inspector Administrative Secretary IBM/30-286 DOS Word Yes Police Administration Chief IBM/30-286 WordPerfect Yes Lieutenant IBM/VP - 386 WordPerfect Detective Sergeant IBM/VP - 386 WordPerfect Detective Sergeant IBM/VP - 386 WordPerfect Detective Sergeant IBM/VP - 386 WordPerfect Secretary IBM/30-286 WordPerfect Police Clerk IBM/30-286 WordPerfect Police Clerk IBM/30-286 WordPerfect f -7- . . The table above demonstrates: 1) A majority of the hardware consists of IBM\30 - 286 which are all between 4 to 6 years old; 2) City staff currently utilizes three different word processing programs, three different spreadsheet programs, and two different database programs; 3) There are individuals who have no access to computers or access to information. The problems these issues create are in the areas of: 1) Compatibility 2) Integration and Access 3) Performance Specifically, each department has unique problems associated with the current systems. The City's Data Processing Users Group, made up of employees from different city departments, has analyzed the current system and identified problems with the current system. The following descriptions identify some of the more significant areas of concern within the context of compatibility, integration and performance. Compati bility Compatibility means, "fitting together." A piece of software and hardware are incompatible if they can not be used together. Incompatibility is the most significant problem with the City's information system. Incompatibility is prevalent in every department. Two examples below demonstrate some problems created by the compatibility issue within the City. -8- : Administrative Services Depa ent The Administrative Services Director/Assistant City Manager and the Office Assistant use Word for DOS for word processing and Lotus 1-2~3 for spreadsheets. The Assistant to the City Manager, and the two Finance Technicians use Framework III for word processing and spreadsheets. The Management Assistant uses Windows based software. Files can be transferred between the Word for DOS program and Windows, but no files are transferred between Framework III and the other software. Windows based software can read Word for DOS files, but Word for DOS can not read Windows files. By not having the ability to share files or programs, employees end up duplicating work. For example, during budget preparation duplication occurs when spreadsheets programs/files are not available or are different between departments. This means that although a number of different employees may be working on budget documents, most of the employees can not edit, update or create man of the com onents. Recreation Department The Director uses Framework III, the Administrative Secretary uses Word for DOS, and the Recreation Coordinator uses Windows products. The department does not share files between each other. This situation can cause duplication, and prohibits an integrated teamwork approach to data processing activities. In other words, if the Director has a document that needs to be revised by someone else in the department, the entire document must be retyped on the other software. Additionally, the software functionality becomes proprietary. That is, only the individual using the software knows how to use it. If that person is gone, than the others have no way of getting information that may be stored on that persons computer. The problems above relate to software incompatibility. Framework III is an extremely old software program which, while it was a popular product when it was delivered, is an antiquated, difficult to learn and provides little flexibility within scope of the entire organization. Software standardization will eliminate the problems stated above and will provide staff with opportunities to create new ways of sharing information. So during budget preparation, for example, all employees could share all the information thereby maximizing the ability of the staff to generate the necessary documents in a team oriented approach. The incompatibility problem also extends to hardware. The simple process of sharing "floppy disks" is a problem in the current environment. Most computers have low density disk drives, while others have high density disk drives. All floppy disks must be formatted on low density disk drives for any sharing to occur. If they are formatted on high density drives, the low density drives will not read the disk. The hardware issue coupled with the software problems segregates systems from any interaction resulting in only rare occasions when files are shared. These relatively small issues tend to cause normal inefficiencies during the daily operations of the staff. For example, an on-going task in the Administrative Services department is the , -9- : tracking of statistics related to "at control, budgets, waste management,' Because files can not easily be shared, staff is unable to use resources from fellow employees to support routine functions. The person who created the tracking device has no alternative to updating and maintaining the system. Incompatibility issues extend to all city departments. The issue does not cause system failure, but if remedied could provide staff with greater flexibility to share resources resulting in time efficiencies due to an increased teamwork approach to operating processes. For example, if a department employee wants the Director to review a report, the Director has the ability to modify the document on-line as opposed to the employee getting the document back with hand written notes and inputting the changes. Since the work of the employees tends to be similar in nature, it makes common sense to provide the same operating software to accomplish their tasks. Inte~ration and Access Integration is the process of sharing compatible resources. In essence, once hardware is compatible, it can be integrated to share system resources like software and printers. Integration then produces greater access to various information databases. The issue of integration or lack thereof, exists between personal computers and in the area of limited access to the City's financial information stored on the System/36. Currently, the System/36 allows access to only 15 employees. The lack of access to the financial reporting systems results in increased demands on the small finance department to produce information to different departments. Conversely, it is not productive to require individuals to rely on the Finance Department to produce records which could be accessed on-line. Technology has advanced to allow communication between computers. The integration of information system components are providing the ability to share resources while improving access to information and improved software applications. Perfonnance The relative slowness of the IBM - 286 (Model 30 and Model 50) processors are prevalent throughout the City and cause many inefficiencies. Employees are, of course, still able to complete most assignments. However, lost time waiting for the computer to "catch up" causes a lost opportunity situation. Additionally, in some cases work may not be able to be completed. The table below presents specific example of problems caused by the lack of speed in the processors. -10- The City Clerk must sometime ait up to 12 minutes for the system to query muni-metrix files related to the City's records. Also, the Word for DOS "document retrieval" mechanism which provides a full listing of files can take up to 3 minutes just to provide a list of files. This can cause severe inefficiencies when searching for files. Every employee with a 286 processor (75% of the stafO will incur delays while printing. That is, when a print job is sent to the printer, the computer can not continue processing until the a majority of the print job has been completed. (Current technology allows almost immediate access to the computer after a print job is sent to the rinter.) The City Manager's Sec ry must wait from 10 to 15 seconds for the computer to "catch up" when simply scrolling through some of the larger documents such as budget documents. Additionally, some documents consume so many system resources that the system fails completely, losing or damaging data. When an employee loads a document file into the 286, the document is slow in moving into the resident memory. The delay can sometimes take up to 20 seconds, depending on the size of the document. Furthermore, some documents are too large for the 286 resident memory and simply don't load at all. Overall, every employee in the City utilizing the IBM - 286 processor encounters a processing delay and performance problems depending on the function they are conducting. When factored over the entire organization, these issues equate to inefficiencies which could be mitigated. Additionally, software enhancements drive the need for faster machines. In other words, new software can not run on old machines. IBM System136 In 1986, the City purchased an IBM System/36 mini computer. Utilizing software supported by Business Records Systems, the System handles all financial functions, payroll and business licenses. The main areas of concern with the System 36 are age and functionality due to the lack of software manipulation ability. Additionally, there is a limited access to the System/36 from all necessary personnel. This issue will be addressed in the System Migration discussion later in the Master Plan. The System/36 has adequate disk space (memory) and is not showing any serious signs of failure. Of course, since the information on the system/36 is so vital, it is important to plan for the replacement of the unit. Summarv of Current Environment The issues of software/hardware incompatibility, integration, and performance are causing small problems that, when viewed organizationally wide, constitute inefficiencies in production and service delivery. The positive aspect of the current configuration is that the city hasn't taken a piece meal approach to change. The equipment is generally consistent and the/software incompatibility problem could be far worse. In the end, the -11- city has received an excellent ra on investment on the current equiPmen.d software and has not wasted funds in developing systems which never produce productive results. However, the City's current data processing system was purchased between 1988 and 1991. The equipment is aging and is beginning to fail. To date, two monitors and a central processing unit have required replacement. Inefficiencies occur when equipment fails and staff must wait for equipment to be replaced. Moreover, many of the 286 PC's have been showing signs of failure such as failure of internal clocks and lost data. Each occurrence requires support staff to provide progressively more service to the failing units. The state of information technology is such that a transition or migration of systems would address the problems noted above and would make city staff considerably more productive and efficient. The master plan will now address the problems noted above, will recommend a system migration plan that will expand the processing abilities of City staff, while providing for standards and integration of system resources and databases. In short, the following will detail a plan that gives employees a greater access to a variety of the same, improved, software programs, databases and printers. System Mi~ration The existing information system structure needs to be addressed. The age of the current system equipment, the efficiencies of more up-to~date technology, in addition to the changing environment, i.e. fewer resources, expansion plans for Eastern Dublin, make it evident that the organization must establish a plan for the future of its information technology resources. System migration means changing or moving the information system to a new mode of operation. The system migration plan will first present the end result of the new recommended system. Then working backwards, the migration plan will describe why the various aspects are recommended, what the benefit of the recommendations will yield in time and enhanced customer service. The main components of the master plan include: . Installation of a local PC network to connect all PC's in the Civic Center and allow access from the Shannon Center and Senior Center. . Selection and installation of a permit tracking/land information system, AutoCad and Geographic Information System (GIS) software and providing access to the network. . Migration of the City's System/36 and software to an IBM AS400, RISC\6000 or additional file server. -12- : . Recommend a s.ule for system changes covering the nextlars. The Network The proposed network would operate under a Windows NT operating system running from a file server with an Intel Pentium processor file server. All PC's on the network will have access to the System/36 through adapter cards installed in a PC acting as a System/36 gateway. With the necessary number of adapter cards, the gateway can allow up to 28 Concurrent sessions on the System/36. The 1994-95 implementation schedule proposes to replace the 24 existing "286" PC's. The typical network PC should be 486/DX2 - 66 megahertz or ~reater with 8 to 16mb of RAM depending on the user. For example, the individual using AutoCad will require faster and larger system resources than the individual using the network for mainly word processing, e-mail and spreadsheets. The network will store the primary software induding the Microsoft Windows graphical user interface with Word (word processing), Excel (spreadsheet), Access (database) and Pagemaker (desktop publishing), electronic mail, as well as other specific department applications. Specific recommendations for resource allocations as well as specific system configurations are presented in the appendix. A portable computer is also recommend for use at City Council meetings and commission meetings. The City Clerk has estimated that time savings of at least 75 hours per year will be achieved by not having to retype meeting minutes from shorthand notes. Additional savings of approximately 50 hours per year will be recognized by the Planning and Recreation Staff related to their individual commission meetings. The network will require new wiring in order to support operations. The general wiring scheme, although more elaborate, is shown in the graphical illustration below. Network Hub System 36 -13- : . . The Master plan proposes the remaining hardware, the System/36, be replaced in Fiscal Year 1997-98. There are options available, although limited, in terms of how to make a successful transition. The main issue is related to the financial system software stored on the System/36 and how to change hardware that supports the software. The easiest transition would be to an IBM AS/400 mini computer installing the more up to date General Ledger software. This is also the most expensive solution. Thus, staff will need to evaluate the cost/benefits of an AS 400 solution vs. other hardware solutions, like a micro computer solution that may integrate better with the PC network. For the purposes of this Master Plan, however, it is known that an AS 400 solution would provide a high quality solution and therefore the cost for this are identified in the Implementation Schedule section of the Master Plan. Justification for a PC Network The new network proposed in Fiscal Year 1994-95 will provide staff with the software and hardware which will: 1) share system resources (printers, software, e-mail) 2) provide greater access to standardized software applications and to the System/36 3) enhance processing capabilities (speed) One of the main benefits of a PC network is sharing of system resources, standardizing software, reducing system resource costs, and ensuring data integrity and security. Savings will be recognized because if one compares the cost of setting up each employee with the resource capabilities proposed with the network, the cost is lower because not as many resources are required to be purchased. A PC network allows individuals to access any software on the system without requiring every user on the network to be licensed to use the software. For example, if the City purchased two licenses for a desktop publishing system, any two users on the network could use the software. The network operating system will monitor access to software allowing for proper management of the resources. (The recommended software allocation plan is presented later in this section). In addition, printer resources can be shared by anyone on the network. This reduces the need to purchase a printer for every user, as is the current situation, and alleviates down time as a result of one particular printer failing since users can select any other printer on the network. In addition to sharing hardware, all employees will have access to the following software and their advanced features. -14- Word and Excel for Windows. . All users on the network would have access to Word for Windows 6.0 and Excel for Windows 5.0 as their main processing applications. Windows and associated applications have the well known advantage of a user friendly graphical user interface (GUI). The GUI provides an on-screen environment which allows the use of a mouse, standardized pull down menus and user defined macros and tool bars. Overall, the Windows GUI provides an environment which is extremely user friendly thus allowing users to maximize the enhanced features of the software. Improved tables, merging, document formatting and tabs, access to Microsoft Draw and improved graphing capability are just a few of the improved aspects that will allow staff the opportunity for increased productivity. For example, if a secretary has a list of names, addresses, etc. of people who need to be contacted, that secretary can simply "click" on the file and, over the network, merge those names into the necessary document. Eventually, databases containing information such as this will be organized on the network for anyone who needs them. These Microsoft products also come with the much publicized Object Linking and Embedding 2.0 (OLE 2.0). This feature allows users to take information from one application like a spreadsheet and easily place the information in another application like a word processor. For example, if a user has an Excel spreadsheet and graph that needs depiction in a Word document, OLE requires the user select the objects in Excel and using the mouse, drag the object to the Word Document. Anytime the Excel information is changed, the object in the word document updates as well. This feature will be especially beneficial to staff in budget preparation, and other reports which require calculations and text in the same document. Technically, Windows products are superior to current MS-DOS software as they have broken the resident memory (RAM) limitations faced by the MS-DOS products. Matched with the more advanced hardware, this gives the software makers the ability to incorporate the numerous advanced features of the windows applications and allows users to produce larger documents more efficiently. Electronic Mail A major resource accessed through a network is the use of electronic mail (E-Mail). E-Mail removes the need for paper based interoffice communication. It will allow short or long messages, allows users to attach application files (spreadsheets, etc.) and automatically routes the mail to correct individuals. E-mail messages can be stored, deleted or copied to other users. The network will also allow for access of e-mail, and other resources, from locations such as home computers, or the Shannon Center and Senior Center. E-Mail will free clerical staff or managers from spending time making copies for routine interoffice memos and other routine routing functions. Data storage functions such as "read files" could be centralized, so managers could simply copy memos, letters, etc. to the appropriate "directory" for storage or printing. Additionally, a time savings -15- will be recognized by the recre.n staff which could receive all interoffice .munications through the E- Mail system. Data Security. Integrity and Backup Data security, integrity and backup of the system will be improved and centralized. Centralization of system resources eliminates the City's exposure to costly software infringement violations because the network will only allow access to a specified number of licenses. The number of licenses will need a close evaluation initially so the City is providing the optimal amount access to users. Additionally, every user will have data backed up at the file server. This will reduce/eliminate costly mistakes related to lost data. Data integrity will be improved, as the file server will include an independent power supply that initiates a shut down procedure allowing user files to be saved. Thus, data is not necessarily lost in a power failure. Land Based Information/Permit Tracking System A permit tracking system consists of three main features: 1) Land based information 2) Planning, Building and Public Works automated and customized permitting 3) Interfacing with a Geographic Information System (GIS) over the network Land based information consists of information from all parcels and addresses within the city which is electronically available for use by staff or, if appropriate, the public. The land based information is considered to be one of the greatest attributes of the permit system and will provide benefits in terms of time and efficiency. Currently, staff must utilize numerous resources to get answers for the public. A typical question, for example may be a flood zone question. Staff must look in the Assessors Parcel Map, identify the correct area, go to the flood zone map, define the scale which may be on multiple pages and calculate the flood zone. Planning staff has indicated a flood zone question can take from 10- 20 minutes to answer. With the land information database, these questions would take no longer than 5 minutes. The permitting system will also streamline the pennitting process. The computer network will assist staff to electronically process the numerous permits issued by the planning, building and public works departments. When an permit application is accepted, the system automatically verifies the address the permit is assigned to (if any). All existing permits and status's for that address can also be displayed. The Contractors, Architects, Engineers and Developers can be verified for valid license, etc. The fees for elements within a permit type can then be calculated. Payments can then be accepted for each fee item defined to the system (either partial or full payments can be accepted). Automatic notification to the departments involved in the approval process can then take place. The departments needed ~or approval can inspect the information collected for the permit -16- immediately on-line and poss' approve the simple permits without any .y to the applicants. Of course, other permit types may require various plans, etc., to be approved or hearings to be held before approval can take place. However, notification to the departments involved can take place immediately. Permit systems are designed to monitor the complete development process from the initial site plan review through the final inspection and all the processes in between. Inquiries into the land database and the GIS assist in the gathering of information required to complete the permit. Other benefits of the permits system are as follows: 1. Growth Management functions providing: * Up to date zoning and use information * Up to date map district information * Historic site, projected districts, seismic hazard areas * Ability to place holds on a development, projects or permits 2. Complete permit and inspection tracking 3. Complete plan check tracking 4. More precise assessment of environmental health impacts is obtained by using * Up to date hazardous waste material information * Ability to create health inspection /violation activities and monitor results * Ability to interface with GIS * Ability of the user to define and maintain demographic information, code enforcement tracking * Evaluate disaster inspection results 5. Centralized Database of developments providing for consistency and accuracy 6. Automated preparation of required reports including: * Reports generated from a list of user-input parameters * Complete development, single project, single permit, multiple permits and census reports. * Reports by time, status, class type, and minimum valuation * Print screens on-line 7. Up to date information replies to agency management and the public * Current, proposed or completed work * Current status of routed work * Ability to create a violation or complaint activity type and track progress * Allow agency management to check on progress of activity without utilizing staff time * Automated routing of work through the departments required for each activity. 8. Increased Staff Effectiveness * Decreased time spent in searching for a particular permit, application, inspection results, or event. * Decreased time spent in searching for site specific data * Up to date status information for all developments, projects, permits, or activities * Automated approvals and clearances Getting the system to a point were all of these benefits are recognized will not be as easy as simply plugging a machine into the wall. The land information is available through Alameda County but needs work in order to get the information in a more usable form. This may include a part-time data entry individual to complete the necessary changes. The details of these impacts should be analyzed in greater detail prior to purchasing a permitting system. Specifically, however, once the system was complete, a time savings would be recognized. In January 1994, the Planning Staff tracked time spent answering questions for the public at the counter and over the phone. In total, the planning staff spent about 36 hours on 121 customer contacts in January, either on the phone or at the counter. This represents an average of 18 minutes per contact which includes research and follow up on the -17- contacts. Conservatively, it is.mated that once the permit system is ins. it would cut the research time in half. This represents a savings of at least 18 hours per month in research and analysis provided by the Planning Department. Furthermore, this doesn't take into account the potential for increased customer satisfaction from receiving consistently accurate and timely information. These benefits will enhance the City's economic development abilities, and improve the perception that the City is a customer service based organization. The Building Department estimated that in a given two week period about 10.5 hours are spent on computer related items such as; assigning new addresses, scaling grid map; issuance of commercial and residential and permit and plans; pull and log current and new building permits; compile statistics for monthly reports; various phone and counter questions relating to permits; soil report information; filing and purging workers compensation statistics; and pulling copies of permits issued. Using the permitting system, it is estimated these tasks would take about 25% of the time saving about 200 hours per year on these activities. Additionally, staff has been working with the Dublin San Ramon Services District and the Dougherty Regional Fire Authority to set up procedures to cooperatively issue development permits. The goal is for the City and accompanying agencies to reduce costs of system installation and to establish "one stop shopping" for the development community. Additionally, it is intended that the land information system and the permitting system work interactively with the proposed GIS as will be discussed later in the Master Plan. AutoCAD CAD stands for "computer aided design." AutoCAD is a popular CAD system software that is made by a company called AutoDesk. The main benefits of AutoCAD will be seen in the Public Works Department. AutoCAD will allow the engineering division automated and more efficient design capabilities. Additionally, since AutoCAD will be a resource connected to the City's network, drawings, maps and other AutoCAD information will be available to all Public Works employees on the network. AutoCAD is also available in the ''Windows format." This is beneficial because the other network functions are running under windows, thus standardizing the operational aspects of the system wide architecture. The use of AutoCAD will create benefits in terms of time savings and customer satisfaction. Ease of editing drawings, copying, manipulation and scaleability of plans are some of the benefits received through AutoCad. The time savings will be recognized by the engineer required to produce drawings. For example, in 1993, the Engineering Technician produced 17 sets of plans (size of 24 x 36) which resulted in 41 sheets of plans. The Engineering Technician estimated these drawings required an average of about 6 hours per sheet for a total of 246 hours. Also the Engineering Technician has estimated an average of 2 hours per sheet was spent on 50 mylars produced for the Standard Plans Book totaling 100 hours. A total of 346 hours was spent on these two -18- functions alone in 1993. With .0CAD, it is estimated time spent on these_tions could be cut in half, saving 173 hours in one year for these two functions alone. AutoCAD will also result in greater customer service. Since most developers in the private sector utilize AutoCAD, their designs could be submitted to the City "on disk." If the City has changes, these can be quickly and easily completed. Additionally, the Dublin San Ramon Services District (DSRSD) has agreed in principle to develop a standard by which the development community could submit the same design to both agencies. As proposed, AutoCAD will be used with, and significantly enhanced by, the GIS package which is discussed in the next section. Geographic Information System (GIS) A GIS is a software package which is a geographic mapping system. In general terms, a GIS gives the City the ability to make, manipulate and analyze information using geographically oriented maps. Benefits of a GIS system come from the ability to not only produce customized maps for the City, but by also displaying map "attributes" while allowing a variety of analyses to be performed. As stated previously, the land information system developed as part of the permit system would be used to generate the "attribute" information. GIS mapping software can give the City benefits in the following general areas: Address Matchin Crime Anal sis Disaster Mana ement!Plannin Vehicle Routin sis Land Records Mana ement Interface Street Ma Maintenance Trans ortation Anal sis Subdivision Desi /Review A GIS system will give City Staff many tools to work with related to mapping activities. These activities are most frequently carried out in the Development Services area of the City's operations. An example of a GIS application would be if a real estate agent came to the public counter requesting information on a piece of property. The property could be viewed on the computer and the information relative to the property owner, zoning information, assessed value and other information would be displayed. Other examples include the 300 foot notification process completed by City Staff. Currently, Staff must use the micro fiche to manually look up every owner within a project area. With the GIS this can be done in a matter of minutes by drawing a circle around the area on the computerized map. General Plan and Zoning Maps can be easily updated and printed using different colors and markings. Proposed development scenario's can be input in order to identify potential impacts. Street maintenance records can be tracked and can provide maintenance schedules. -19- Although there are benefits taill be recognized by using a GIS, it ShOUI. considered a "higher service level," because there will be a costs to implement and maintain the system. In short, it will be necessary to have an individual working with the system to build and maintain the information which makes up the GIS. Also, the equipment necessary to achieve accuracy on the maps, although currently unknown, will still not be inexpensive. Further analysis will need to be completed before the system is fully recommended. Some of these cost may be reduced by participating in the regional GIS project. The Cities of Pleasanton, Uvennore, San Ramon, Danville, the Dublin San Ramon Services District, the Dougherty Regional Fire Authority, Zone 7, Alameda County, East Bay Regional Parks, and a number of other private utility companies have been discussing a joint GIS project. The current concept is that the group will establish a standard for establishing monuments used to achieve accuracy on the map. Accuracy levels refer to how close the lines on the map are to what they are in reality. A map with a 2' to 5' accuracy are considered to be good levels of accuracy. However, the GIS group is discussing the potential use of GPS (global positioning system) monitoring units that achieve accuracy levels within 2 centimeters. At this time the group is in a preliminary assessment stage of the project. The cost/benefits of the a GIS will require further analysis once the information is available. Network Personnel There will be a need for greater system support with the centralization of the computer processes and the migration of software applications into a computer network. The network installation and maintenance will require increased staff support or consultant support. It is anticipated that the network administration support would take approximately .25 more of the current Management Assistant's time (.25 of the Management Assistant is already dedicated to computer support) Overall, the centralization of information processing that is achieved with a network results in increased administrative requirements to support the network. In order to adequately service the network a total of .5 of the current Management Assistants time will be utilized. Contracting for these services has been examined to determine its cost and ability to meet City needs. It was determined that cost of such services are about 3 times the amount of the current data processing personnel. Additionally, these services tend to be provided on an on-call basis and most support problems are relatively small problems that can be solved very quickly. Network Costs and System Implementation Schedule The network costs and implementation schedule are presented based on the fiscal year for which the particular aspect of the system is proposed. The computer market does change of course, so the costs presented below will not be 100% accurate. It should also b,e noted that the system activities and proposed applications are the -20- primary system components. .e will likely be other incidental costs rela.to the City's information technology that are not listed. Fiscal Y ear 1994-95 - Year I Fiscal Year 1994-95 represents a majority of the City's liability over the five years of the Master Plan. This is, of course, due to the costs associated with the start up of the network. In the first year it is proposed the City purchase the following hardware, software and services: Hardware Software ,.. 1 File Server ,.. Windows NT Advance Server (Network System) ,.. 24 Replacement Personal Computers ,.. Microsoft Professional 4.0 (Includes Word, Excel, ,.. 7 New Personal Computers and Access) ,.. 4 Laser Jet Network Printers ,.. Pagemaker (Desktop Publishing) II- 4 Deskjet Printers II- Sitelock (Network Security) ,.. 1 Portable Computer ,.. PC Tools for Windows (Anti-virus, System Maint.) II- Assorted Networking Devices (Gateway Adapter Cards, Network Cards for existing PC's) II- Independent Power Supply II- Cabling and Hubs (Network Infrastructure) II- RAM upgrades (current PC's) II- Police Department 16 Channel MUX Services II- Procurement Consultant ,.. PC Training II- Network Administration Training II- Cabling Upgrade II- Telephone Line installation Estimated Year 1 Costs: $149,055 Year 1 Master Plan Activities: Begin assessment of Document Imaging System Begin AutoCad Software Evaluation Review cost/benefit of adding automated faxing Determine incidental needs of network components (i.e. RAM upgrades, etc.) -21- Fiscal Year 1995-96 - Year 2 Hardware: AutoCad Personal Computer Software: AutoCad Application Document Imaging System/Indexing Software Automated Permit System Install Windows 4.0 (New Workstation Operation System) Training and Consulting PC Training Permit System Support AutoCad Training Year 2 Estimated Costs: $65,000 Year 2 Master Plan Activities: Study process automation feasibility Re-evaluate PC training program Review network printer allocation scheme Review PC system component adequacy (386 performance, RAM adequacy, etc.) Fiscal Year 1997-98 - Year 4 Hardware: Migration from System/ 36 Software: Address GIS/Permit System Needs Install update to Network Operating system, if necessary Training and Consulting: Permit System Support PC Training Estimate Year 4 Costs: $30,000 Year 4 Master Plan Activities: Review needs of PC processor upgrade Review File Server adequacy Review PC s stem software u ade needs Fi Hardware: GIS Computer Add Printers, if necessary Replace existing "386" Machines Software: GIS Software Purchase Forms Software, automation apps. Training and Consulting: PC Training GIS Training Hire automation firm, if necessary Year 3 Estimated Costs: $35,000 Year 3 Master Plan Activities: Compile information on System 36 migration Review Network Operating System Software Review AutoCAD software updates Fiscal Year 1998-99 - Year 5 Hardware: Upgrade Network PC system processors (as necessary) Address File Server Needs Software: Install necessary PC system software upgrades Training and Consulting: PC Training Installation of PC system processors Year 5 Estimated Costs: $33,000 Year 5 Master Plan Activities: Review if the system configuration meeting needs Update Master plan for future -22- R",,,,,, Ne - Non Pollce Costs Pentium/90, 32mb, 2g HD, 14" Mon., tape bak. Network pes ~ Non-Police g~"~'~<::,,~~:.ri~;:~llll~;'~fiHP~!t';,MRi;,"'/"""'."':"'i..',.'...2;~Q:}\ ................2, i.',AAI~(j: '.:..:....'.'....'....'.'../....."... ."",.,..,n.,..x,."".,.."., ',." :".,.",.4;94,9 ~~;~~~~~~:;2iiiHJ;i~~~q~d;,14~So0.);:,~~:1;1:1::t:~~r.)..~9~20r'2M9 3) REPLACEMENT PC, 50 mz, 16mb, 200+ HD,14" mono 2,649 4 ~ SubTotal 67,400 Tax 8.25% 5,561 Shipping 400 Total 73,361 --\~.. ''ii : :,-:....~~'(f1;;l'f..z'J1~~'"": ;:~.. .:~.~; '.';' ' '.'-,;:..~":.',"'.'. Unit Price 9,695 ~j'RmYp~#~~~ri~g.~;J1s~~;i;Wflr,'.,.....i.....'/}...??.....'H:'>'.:2,4i~\: 2) REPLACEMENT PC, 66 mz, 8mb, 200+ HD, 14" man. 2,470 16 Channel MUX - Police RMS Connection 3,600 RAM Upgrades (Blocks of 4 MB) 350 HP4 si with 6mb memory 3,033 HP Oeskjet 350 Ethernet Network Adaptor Card 100 Police RMS Adaptor Cards 300 SubTotal Tax 8.25% Shipping Total BASlCNElWo&95 COST DETAIL Proposed !SF Proposed Other Fmanced Iml 9,695 Fmanced 9,695 10.596 50,116 17,284 4,135 1,426 400 0 54,651 18,710 .'..............:::::...'1. 4 1 4 1 4 4 3 ,:..,.::i9;~iW:....,..).:>.:'.',."'" ,',' 9,880 3,600 1,400 ................ ." ........ . ............. ... . . . . .. . . . ................. . , ....... . ':,,):?,880 . ..... ................... 9,880 3,600 1,400 3,033 3,033 1,400 1,400 400 400 2QQ 900 30,493 12,913 17,580 2,516 1,065 1,450 400 400 0 33,409 14,378 19,030 Other Hardware Unit Price Ouantilv Total HP4 si with 6mb memory 3,033 3 9,099 9,099 HP Oeskjet Printers 350 3 1,050 1,050 Ethernet Network Adaptor Card 100 8 800 800 Active Hub (50 port hub) 2,500 2 5,000 5,000 Pac Bell Telephone Une Installation 400 1 400 400 SubTotal 16,349 9,099 7,250 Tax 8.25% 1,349 751 598 Shipping 400 400 0 Total 18,098 10,2S0 7,848 Unit Software Price MS Word for Windows 6.0 Upgrade (MS-UP) 110 MS Word for Windows 6.0 Ucense (MS) 275 Windows NT Advanced Server 2,664 MS Office Ucense; Word, Excel and Powerpoint (MS-OFF) 415 E-Mail User Ucences (25 - Pack) 565 Gte Lock - Network Security 366 SubTotal Tax 8.25% Shipping Total Training and Consultin~ Procurement Consultant Wiring lnstalla tion 3,000 2,500 Total Access to Network Gateway (7 port access card) 2,200 Total Citv CounciIlPlolnn;n<> Commission Portable Portable Computer, 33mz, 8mb, 250+ HD, Ether 2,700 Total 1fOT AlL B AS\C NETWORK COSTS 1-- C-_ L. Total Number of Replacement units Total Number of New Units (includes Portable) Total ~ 6 660 660 11 3,025 3,025 1 2,664 2,664 6 2,490 2,490 2 1,130 1,130 1 366 W 10,335 10,335 853 853 400 400 11,588 11,588 1 3,000 3,000 1 2,500 2,500 S,500 S,soO 2 4,400 4,400 4,400 4,400 1 2,700 2,700 2,700 149,OSS 2,700 69,776 79,279 24 8 '!1 :j~::i':::::'{:i:::':~l~:i::::l:,HHj:::::::":,'. ~~j!l&j;~ Fisca Year 1994-95 Evidencp Trackln<7 - J::lxed Asset" ~v"tem Evidence Tracking System. Fixed Assests (inc. bar reader) 4,159 1 4,159 2) NEW PC, 66 mz, 8mb, 200+ HD, 14" mono 2,470 1 2,470 Dot Matrix Printer - Inventory System 300 1 300 SubTotal 6,929 Tax 8.25% 572 Total 7,501 Fiscal Year 1994-95 Total 7,501 Fiscal Year 1995-96 AutoCAD AutoCad/ ArcCad Plotter 9,000 1.00 9,000 AutoCAD - Software 2,100 1 2,100 4) Network PC, 66mz, 16mb,250+ HD, 17", Mon 3,103 1 3,103 AutoCAD Training 1,500 1 UQQ SubTotal 15,703 Tax 8.25% 1,295 Total 16,998 Permit SYstem Permit System - Software 12,500 1 12,500 Permit System and Land Database Install and Training 10,000 1 10,000 SubTotal 22,500 Tax 8.25% 1,856 Total 24,356 Document lmalrin",f Archivin", SVstem Imaging Software and CD Recorder 6,000 1 6,000 Indexing Software 5,500 1 5,500 Scanner 5,000 1 5,000 CD Media 500 1 500 Total 17,000 Fiscal Year 1995-96 Total 58,355 Fiscal Year 1996-97 GIS ArcCad - GIS 4,000 1 4,000 4) Network PC, 66mz, 16mb,250+ HD, 14", Mon 3,103 1 3,103 ArcCad Training 1,500 1 1,500 SubTotal 8,603 Tax 8.25% 710 Total 9,313 Fiscal Year 1996-97 Total 9,313 Fiscal Year 1997-98 Reolacement of '"vstem /'>,6 Uplrrade of System/36 25,000 1 25,000 Fiscal Year 1997-98 Total 25,000 Fiscal Year 1995.99 Network - Hardware and Software Upgrades 33,000 1 33,000 Total for Fiscal Year 1995.99 33,000 Total for All Application Options 133,169 . . CITY OF DUBLIN, CALIFORNIA ADMINISTRATIVE SERVICES DEPARTMENT REQUEST FOR BIDS FOR THE "LOCAL AREA NETWORK HARDWARE/SOFTWARE PROJECT" DATED SEPTEMBER, 1994 EXHIBIT c2 =- . . CITY OF DUBLIN LOCAL AREA NETWORK HARDW ARE/SOFTW ARE ACQUISITION NOTICE TO BIDDERS Notice is hereby given that sealed bids, subject to the conditions named herein and in the Specifications therefor for the City of Dublin Local Area Network Hardware/Software Contract addressed to the City of Dublin will be received at the City Clerk's Office, 100 Civic Plaza, 2nd Floor, Dublin CA 94568, up to October 21, 1994 at 10:00 p.m., at which time they will be publicly opened and read. A complete set of bid documents is available at City Offices, 100 Civic Plaza, City Manager's Office, Dublin, CA 94568. For further information on this bid contact Bo Barker, Management Assistant, at 510-833-6650. Paul S. Rankin, Assistant City Manager/Administrative Services Director 2 :- . . INSTRUCTIONS TO BIDDERS 1.0. General Information 1.1. City Objective The City of Dublin has recently completed a master planning project that details changes to the current information systems. As part of the master plan, in fiscal year 1994-95, the City will embark on an installation of a personal computer local area network (ethernet -10BaseT). The City of Dublin is seeking proposals for computer hardware and software which will meet City needs for a new local area network as outlined in these bid specifications. 1.2. Proposals Instructions In order to receive consideration, all bid proposals shall be made in accordance with the following instructions: 1.2.1. Proposals shall be made upon the forms provided therefor, properly executed and with all items filled out; the signature of all persons signing shall be in long hand. 1.2.3. No FAXED proposals will be considered. No proposal received after the time fixed for receiving them will be considered. Late proposals will be returned to the vendor unopened. 1.3 Proposal Format 1.3.1. Signature: Proposal shall be signed by an authorized corporate officer. 1.3.2. Bid Forms. Each vendor shall fill out completely and accurately the proposal forms supplied with this invitation to respond to the Bid. Do not use your own forms. Failure to use the forms provided will invalidate the proposal. The inability to meet a specific feature or item of equipment requested or any specific general condition will not invalidate your proposal, but will be weighed in the final selection of the successful vendor(s). 1.3.3. Valid Period: Include a statement that the terms of the proposal will remain valid for 60 days. 1.3.4. Qualifications: Firm's relevant experience; responsiveness; ability to perform; Provide 3 references of agencies where similar work has been performed in the past. In each case briefly describe the project scope and indicate a contact person and phone number. 1.3.5. Identify the personnel to be involved in the project and their background. Include information relative to any subcontractor. 3 ~ . . 1.4 Deadlines 1.4.2 Due Date for Response: October 21, 1994, 10:00 p.m. 1.4.3. One Copy of the bid proposals should be submitted to: City of Dublin City Clerk's Office 100 Civic Plaza, 2nd Floor P.O. Box 2340 Dublin, CA 94568 1.5 Bid Clarification: Upon receipt of your proposal, you may be called for additional information and/ or detailed discussion of the proposal. 1.6 Addenda or bulletins: Any addenda or bulletins issued by the City during the time of bidding or forming a part of the documents provided to the bidder for the preparation of his bid shall be covered in the bid and shall be made a part of the contract. 1.7 Withdrawal of bids: Any bidder may withdraw a bid, either personally or by a written request, at any time prior to the scheduled deadline for receipt of written bids. 1.8 Economy of preparation: The proposal should be prepared simply, economically and provide a straight forward, concise description of the bidder's capabilities to satisfy the requirements of these specifications. The bidder shall be responsible for costs incurred in the proposal preparation and delivery. 1.9 City Right to Accept or Reject Proposals: The City of Dublin reserves the right to accept or reject any proposals, and all subsequent material, either verbal or written, exclusive of an executed written contract. This invitation to respond to the bid in no way obligates the City of Dublin to any company, supplier, manufacturer, or respondent to the bid. All companies are to respond on the identical configurations. 1.10 Award and Execution of Contract 1.10.1 These bid specifications are separated into two different bid alternatives. (Bid Alternative #1 and Bid Alternative #2). Bidders may bid on one or both bid alternatives. The City will select a vendor(s) whose bid proposal meets the City's needs most appropriately including price, experience and service. One vendor will be selected for one or both of the bid alternatives. 1.10.2 BONDS. Contractor shall provide, at the time of the execution of the agreement or contract for the work, and at his own expense, a bid bond in an amount equal to at least ten percent (10%) of the contract price. 4 :- . . 1.11 Errors and Omissions The City of Dublin shall not be held responsible for errors, omissions, oversights, etc., in the vendors response to the bid proposal. Said errors, omissions, or oversights brought to the attention of the City of Dublin subsequent to the due date of this proposal which alter or modify the information which form the basis for evaluation of the submitted bid response, shall remain the responsibility of the vendor. Additionally, any errors, omissions, or oversights of a material nature may constitute grounds for rejection of the submitted proposal. 5 ~ . . BID SPECIFICATIONS AND FORMS Bid Parameters: The bid specifications represent the minimum requirements for the equipment required for the network. For example, the specification for a personal computer may be a minimum 200MB Hard Drive (HD). Any hard disk should therefore have a minimum HD capacity of 200MB. If, for example, the hard drive is 250MB, that information should be included in the table as appropriate. Any additional information from the manufacturer that describes the proposed equipment is welcome, but cannot be used as a substitute for completing the bid form tables. The following sample is provided to give vendors information on how the forms should be completed. Manufacturer #1 Hewlett Packard #2 Dell #3 Compaq Model Name Model 486x Modelxyz Model 445z Pentium 90 MHz - 256kb L2 same same same Cache 32MB RAM wi the capability 32MB expandable to 32MB expandable to same to expand to 192 MB 291 MB 350 MB (1) 2GB Fast SCSI 2 HD wi 2.2GB same 2.1GB access time of 10-15ms Unit Price Est. Quantitv Total Price Manufacturer #1 $5,000 2 $10,000 Manufacturer #2 $5,500 2 $11,000 Manufacturer #3 $6,000 2 $12,000 In order to provide the mechanism for vendors to bid on equal components, the City will only accept bids for equipment made by the three following manufacturers: Hewlett Packard, Compaq, IBM and Dell. The proposed printers are limited to Hewlett Packard printers as described below. The City intends to purchase 1 file server, 31 personal computers, 4 laser printers. Bidders shall not re-engineer hardware or substitute any 3rd party parts other than what is included by the original manufacturer. Third party monitors can be proposed in the space provided, however, the manufacturers model should be included on the summary form quotation. All equipment proposed should be described sufficiently to allow the City to contact manufacturers and verify the proposed information. 6 :- . . Bid Alternative #1 The bid forms provided show tables to fill in as appropriate. Three columns are provided to allow vendors to provide bids on up to three different hardware solutions. Vendors may choose to provide bids on only one or two solutions as well. A space should only be left blank when the specification is met exactly. For example, if the File Server that is being proposed is a Pentium 90mHz with 265kb L2 cache, as specified, than the space provided need not be filled in or can be labeled "same." Otherwise all spaces should be completed. Included at the end of Bid Alternative #1 is a "Summary and Total Bid for Alternative #1." This form is designed to take the cost detail listed in each section and put it into a format that allows the City to evaluate the total proposal. Vendors proposing solutions based on more than one manufacturer should complete one Summary Form for each. (Bid bonds should be based on hi~hest Grand Total that is listed on the Summary Form). Section A . 1: File Server - Minimum Specifications Please complete the following table as directed in the preceding sections. Manufacturer #1 #2 #3 Model Name Pentium 90 MHz - 256kb L2 Cache 32MB RAM w / the capability to expand to 192 MB (1) 2GB Fast SCSI 2 HD w / access time of 10-15ms Fast IDE Controller EISA/PCI Bus at least 4 EISA slots 512kb Video RAM CD-ROM w / controller (double speed) Internal 2GB DA T Tape Backup Drive Section A . 1: File Server Cost Totals Unit Price Estimated Total Price Manufacturer #1 $ 1 $ Manufacturer #2 $ 1 $ Manufacturer #3 $ 1 $ 7 ~ . . Bid Alternative #1 Page 2 Section B-1: Network Personal Computers - Minimum Specifications Please complete the following table as directed. Manufacturer #1 #2 #3 Model Name Intel 80486DX2 66 MHz - 128Kb L2 Cache (256k expandable) ZIP Socket - Intel Overdrive Expandable 8MB RAM (1) 3.5" FDD (1) 200MB IDE HD Enhanced IDE Controller Local Bus (32 bit expandable) 512KB VRAM NE 3200 Ethernet network adapter- 10base T with RJ45 connectors (include a cable at least 4' in length RJ45 connectors) Mouse DOS 6.2 and Windows for Workgroups 3.11 101-Enhanced Keyboard Manufacturers 14" 1024 x 768 - 256 colors - non interlace SVGA Monitor Section B-1: Total Costs Unit Price Estimated Total Price Manufacturer #1 $ 26 $ Manufacturer #2 $ 26 $ Manufacturer #3 $ 26 $ 8 :- . . Bid Alternative #1 Page 3 Section B w 2: Network Personal Computers - Minimum Specifications Please complete the following table as directed. Section B -2 only differs from B-1 in the amount of RAM. Manufacturer #1 #2 #3 Model Name Inte180486DX2 66 MHz - 128Kb L2 Cache (256k expandable) ZIF Socket - Intel Overdrive Expandable 16MB RAM (1) 3.5" FDD (1) 200MB IDE HD Enhanced IDE Controller Local Bus (32 bit expandable) 512KB VRAM NE 3200 Ethernet network adapter - lObase T with RJ45 connectors (include a cable at least 4' in length RJ45 connectors) Mouse DOS 6.2 and Windows for Workgroups 3.11 lOI-Enhanced Keyboard Manufacturers 14" 1024 x 768 - 256 colors - non interlace SVGA Monitor Section B w 2: Total Costs Unit Price Estimated Total Price Manufacturer #1 $ 5 $ Manufacturer #2 $ 5 $ Manufacturer #3 $ 5 $ 9 : . . Bid Alternative #1 Page 4 Section C - 1 - Printers Please complete the following table as appropriate. P' U 'tP' Q n G dTtl TInter m nce uan lty ran oa HP 4si Laser Printer (include $ HP JetDirect card 2 Ethernet/RJ45 supporting Windows NT) Additional 4mb memory for $ the HP4si Printers 2 HP4siMX $ 2 $ Total Cost of Printers: Section C - 1 Section D -1: Network Devices NE3200 or equivalent, lOBase T Ethernet Adapter Card w /RJ45 connector (for existing PCs) - EISA bus. Include, at minimum, a 4' cable with RJ4S connectors APC 600 or equivalent Uninterruptable Power Supply (UPS) Unit Price Est. Quantity Total Price $ 10 $ 1 Total for Section D -1 $ Section D - 2: Memory Upgrades 4MB Blocks of Additional RAM compatible with existing IBM PS - Value Point Model 32ST's. Unit Price Quantity Total Price Section D - 2 $ 4 10 ~ . . Bid Alternative #1 Page 5 Section E - 1: Installation In addition to supplying the equipment, the vendor who is awarded Bid Alternative #1 will be required to complete the following items: 1) Work with City Staff and City Consultant to install and configure Windows NT Advanced Server on the File Server and configure the UPS. (The Operating System may be provided by the City depending on the results of Bid Alternative #2) 2) Work with City Staff to schedule, install and configure workstations at the appropriate locations in the Civic Center. 3) Configure and install the four network printers. 4) Provide up to 10 hours of additonal telephone support for hardware related problems. Hourly Rate Estimated Hours Total Installation Costs - Section E-1 $ Labor Costs Section F - 1: Miscellaneous Options These items will not be included in the Summary and Total Bid Form. The items should be provided as additional information for the City's consideration. Item Description Cost Equipment should come with a minimum 3 Year Warranty - at least 1 year on site. Other Software that is included (Please list or attach additional pages) Track mouse (please indicate $ manufacturer and unit cost. Base price on a Cluantitll of 15) 1 (5.25) High Density FD (please list $ manufacturer and additional cost) 3rd party monitor - 14" 1024 x 768 - $ 256 colors - non interlace SVGA f Monitor- Please provide brand 11 :- . . Summary and Total Bid for Alternative #1 Using the detail forms above summarize the proposal using the parameters listed below. Equipment Unite Price Est. Quantitv Total Price Section A-I: $ 1 $ File Server Section B-1: $ $ Workstations (with 26 manufacturer's monitor) Section B-2: $ $ Workstations (with 5 manufacturer's monitor and 16mb Total RAM) Section C. 1: $ 4 $ Printers Section D - 1: $ 10 $ Network Adapter Cards for existing PCs Section D - 2: $ 1 $ Uninterruptable Power Supply Section E - 1: N/A N/A $ Installation Sub Total $ Tax $ Shipping $ Bid Alternative #1 $ Grand Total The above summary represents possible elements of the local area network. It does not necessarily constitute the actual quantities to be purchased. 12 : ~---= .- ......-w ~..-- '" . 'I. , Bid Alternative #2 SOFTWARE Listed below are software descriptions as well as the estimated quantities the City currently projects. The unit price specified by the vendor should apply to any quantity deviations the City deems necessary to properly license users. Software Description Unit Price Quantity Total Price Microsoft Windows for Workgroups v. 3.11 with $ 1 $ Docs. Microsoft Windows for Workgroups v. 3.11 $ 8 $ License Only Microsoft Word for Windows 6.0 Upgrade $ 6 $ License Microsoft Word for Windows 6.0 License w /Docs $ 4 $ Microsoft Word for Windows 6.0 License Only $ 4 $ Microsoft Office for Windows 4.2 License $ 4 $ W /Docs Microsoft Office for Windows 4.2 License Only $ 4 $ Microsoft Office Professional for Windows - $ 2 $ w / Access 4.2 on CD ROM Microsoft Office Professional for Windows - $ 1 $ Professional 4.0 License Only Microsoft Project 4.0 - License w /Docs $ 1 $ Windows NT Advance server ver 3.5 w /Does on $ 1 $ CD ROM Sitelock 3.3 $ 1 $ WordPerfect for Windows 6.0 Upgrade $ 4 $ WordPerfect for Windows 6.0 License w /Docs $ 8 $ WordPerfect 5.1 for DOS License Only $ 1 $ PC Tools for Windows 2.0 $ 1 $ Grand Total Bid Alternative #2 $ 13 :--