HomeMy WebLinkAboutItem 4.5 Accept Improvement 84-5 CITY OF DUBLIN
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: November 13,
1984
SUBJECT
: Street Slurry Seal Program - Contract 84-5
EXHIBITS ATTACHED : None
RECOMMENDATION
1) Accept improvements under Contract 84-5
2) Authorize payment to Graham Contractors,
the amount of $29,299.43
Inc. in
FINANCIAL STATEMENT: Contract Amount: $31,037.25 .
Actual Contract Cost: $29,299.43
Sufficient funds have been budgeted
JSCRIPTION : In September, 1984 the City Council awarded Contract
64-5 to Graham Contractors, Inc., for the Annual Slurry Seal Program.
Slurry seal is a preventive maintenance technique used to prolong the life
of a street. It consists of a sand/oil mixture which seals cracks and
provides a uniform wearing surface. The major item of work under Contract
84-5 was to install a coat of slurry seal on 33 streets and courts.
During the construction phase, the City Engineer deleted Shannon Avenue
(between Peppertree and San Ramon Road) from the program due to a trenching
project to be done by the Dublin San Ramon Services District within the next
6 months. For this reason, the actual contract amount is $1,737.82 less
than the original contract amount.
The contractor has completed the improvements in accordance
approved plans, specifications and modifications. Staff
acceptance of improvements and payment to the contractor.
with the
recommends