HomeMy WebLinkAbout4.20 Overlay #01-09 AICITY CLERK File # 1:11GIOld-&ZI AGENDA STATEMENT CITY COUNCIL MEETING DATE: June 18, 2002 SUBJECT: Acceptance of Work — Contract No. 01-09, 2000-2001 Annual Overlay Project (Fall 2001-2002) Report Prepared by: Lee S. Thompson, Public Works Director ATTACHMENTS: RECOMMENDATION/: FINANCIAL STATEMENT: I►�t.Tii11 Accept improvements under Contract No. 01-09 and authorize the release of retention after 35 days if there are no subcontractor claims. Estimated Actual Budget Remaining Budget for FY 2001-2002 for FY 2001-2002 FY 2001-2002 Fall Overlay Spring Overlay Design/Inspections/Misc: $ 63,200 $ 42,170* $ 21,030 Improvements: $ 1,678,089 $ 1,075,663 $ 602,426 Total: $ 1,741,289 $ 1,117,833 $ 623,456 * Expenditures as of May 31, 2002. This project is funded by TEA-21 Federal funds ($439,000), State Transportation Congestion Relief Fund ($294,470), Gas Tax ($577,559), Measure B ($391,260) and General Funds ($39,000). The FY 2001-2002 budget includes funds to perform this contract and Contract No. 02-03, 2001-2002 Annual Street Overlay Project. The remaining budget of $623,456 will be used to fund the Spring 2001-2002 Annual Street Overlay Project (Contract 02-03) that is currently under construction. DESCRIPTION: On August 21, 2001, the City Council awarded the 2000-2001 Annual Overlay Project, Contract No. 01-09, to McGuire & Hester. The project was delayed from the Spring of FY 2000-2001 until the Fall of FY 2001-2002 due to the securing of additional Federal/State funds and coordinating the overlay work with the Dublin San Ramon Services District (DSRSD) recycled water pipeline project on Dougherty Road. 4 / -------------------------------------------------------------- COPIES TO: McGuire & Hester 0 /�' ) 4 ITEM NO. 20 g:\over1ay\2001\project\AS acceptance This overlay project removed and replaced failed asphalt concrete pavement to a minimum depth of 4 inches, resurfaced various street with a 1-1/2-inch overlay of asphalt concrete and re-striped pavement striping and markings. Reinforcing fabric was used prior to the overlay in order to prevent cracks from reflecting through the new overlay. The project also included median landscaping improvements on Dougherty Road between Sierra Lane and Dublin Boulevard. This portion of work was funded by Federal TEA-21 funds. The following streets were overlaid as part of Contract No. 02-03: Alto Way Dublin Green Court Prow waY Amanda Street Dublin Green Drive Sheffield Court Bonfield Court Elgin Lane Sheffield Lane Canterbury Court Jasmine Court Solana Drive Cardiff Court Knollwood Place Spencer Court Cardigan Court Larkdale Avenue Thames Court Catalan Court Mayan Court York Court Dougherty Road (800' North of Houston Place to Dublin Blvd.) San Ramon Road (Dublin Blvd. to Amador Valley Blvd., northbound lanes only) ' Village Parkway (Amador Valley Blvd. to Davona Drive) Staff has reviewed the work and recommends that the City Council accept the improvements under Contract No. 01-09, 2000-2001 Annual Overlay Project, and authorize the release of retention after 35 days if there are no subcontractor claims. Page 2