AGENDA STATEMENT
City Council Meeting Date: June 22, 1987
SUBJECT:
Acceptance of Contract No. 86-7
Sierra Court Southerly Extension
EXHIBITS ATTACHED: None.
~/1) Accept improvements under Contract 86-7.
RECOMMENDATION:
Vv2
Release letter of credit.
FINANCIAL STATEMENT:
Engineering/Inspection
Landscape Architect
Advertising
Construction
Material Testing
Permits
Budget. 1985-86 1986-87
$ 63,000 $ 30,133 $ 25,713
10,638 803
3O0
525,000
492,311
1,242
2,961
%588,000 ~ 41,071 $523,030
Total Project:
$364.101
Budget vs. Actual
Total 1986-87
Budget $588,000 $546,000
Actual 564,101 523,030
The project is under budget for both the total project and for Fiscal Year 1986-87.
DESCRIPTION:
In July of 1986, the City Council awarded Contract 86-7, the Sierra Court
Southerly Extension, to Robert Quatman, Inc. The project provided for the extension
of Sierra Court through the Dublin Sports Grounds for access to the Civic Center
site. This project included street improvements, street lighting, and utilities. It
also includes reconstruction of baseball fields, relocating a park storage facility,
construction of restrooms, and drainage facilities.
The City Engineer has reviewed the work on the project and determined
that it is complete and in accordance with the approved plans and specifications.
Staff recommends that the City Council accept the improvements and authorize release
of Robert Quatman's security in lieu of retention, which is in the form of a letter
of credit.