HomeMy WebLinkAbout4.07 Award Of Bid 87-4 CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: April 13, 1987
SUBJECT:
Award of Bid - Contract No. 87-4
1987 Sidewalk Repair Program
EXHIBITS ATTACHED: .s~mmary of Bids
RECOMMENDATION: ~ 1) Award Bid to Ambo Engineering, Inc.
2) Authorize Mayor to execute agreement.
FINANCIAL STATEMENT:
Low Bid Received:
Funds Budgeted:
Construction
Design/Inspection
$38,507.98
$41,000
9,000
50,000
DESCRIPTION:
At its meeting of February 23, 1987, the City Council authorized Staff to
advertise for bids for Contract 87-4, 1987 Sidewalk Repair Program.
The City received a total of 4 bids (see attached bid summary) for this
project. The low bidder was Ambo Engineering with a bid of $38,507.98.
Staff has reviewed the low bidder's proposal and checked with references
and recommends that the City Council award the bid to the iow bidder.
ITEM NO.__~ COPIES TO: Ambo Engineering
CONTRACT 87-4 ANNUAL STDE~ALK REPAIR PROGRAM
ITI~TZATTON OF WORK ENGINEER' S ESTIMATE AMBO E~GII~F. RING P & F CONST~UCTION SWIsHEI( CF~F.I~
BID ITEM UNIT UNIT TOTAL UNIT TOTAL UNIT TOTAL UNIT TOTAL
DESCRIPTION MEAS. PRICE PRICE PRICE PRICE PRICE PRICE - PRICE PRICE
41,231.80
ITEM qTY.
1 S/W RMV & REPL SF 6,154 5.00 30,770.00 4.87 29,969.98
2 C&G RMV & REPL LF 220 18.50 4,070.00 17.35 3,817.00
3 SAW CUT LF 660 2.50 1,650.00 2.65 1,749.00
4 ROOT SHIELD LF 160 14.00 2,240.00 12.00 1,920.00
5 AC PAVING SF 400 3.20 1,280.00 2.63 1,052.00
4.90 30,154.60 6.70
17.00 3,740.00 19.00 4,180.00
3.00 1,980.00 2.90 1,914.00
12.25 1,960.00 7.50 1,200.00
3.75 1,500.00 2.70 1,080.00
TOTAL: 40,010.00 38,507.98 39,334.60 49,605.80
TT~4IZATION OF WORK CONNINGHAM & SONS
BID ITEM UNIT UNIT TOTAL ~ UNIT TOTAL UNIT TOTAL UNIT TOTAL
ITEM DESCRIPTION MEAS. QTY. PRICE PRICE PRICE PRICE PRICE PRICE PRICE PRICE
1 S/W RMV & REPL SF 6,154 6.25 38,462.50
2 C&G RMV & REPL LF 220 21.00 4,620.00
3 SAW CUT LF 660 3.00 1,980.00
4 ROOT SHIELD LF 160 20.00 3,200.00
5 AC PAVING SF 400 6.50 2,600.00
TOTAL: 50,862.50