HomeMy WebLinkAbout4.05 Final Acceptance 87-7 CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: July 25, 1988
SUBJECT:
Acceptance of Work - Contract No. 87-7
Dolan Park Improvements Phase I
EXHIBITS ATTACHED: None.
RECOMMENDATION:
1)
2)
Accept improvements under Contract 88-7
Authorize final progress payment and retention
payment in the amount of $18,046.18 to Valley
Crest Landscape
FINANCIAL STATEMENT:
Actual Budget Total Budget
(as updated for 88-89) Both Phases
Construction $ 327,992.66 $ 328,000.00 $ 574,475.00
Design/Inspection 35,119.38 35,590.00 62,620.00
Water Fees 28~005.00 28,000.00 28,000.00
$ 391,117.04 $ 391,590.00 $ 665,095.00
DESCRIPTION:
In August, 1987, the City Council awarded Contract 88-7 Dolan
Park Improvements Phase I to Valley Crest Landscape. The project consisted
of construction of a park in the 5-acre area south of Padre Way which was
formerly owned by the Murray School District. Phase I improvements included
major grading, irrigation, landscaping, lighting, walkways, and a children's
play area.
During the course of construction, changes were authorized for
the following: substitution of planted ground cover for hydroseed, a grade
change using onsite soil, the addition of a water meter, and substitution of
aluminum light poles for wood.
The City Engineer has reviewed the work on the project and
determined that it is complete and in accordance with the approved plans and
specifications. Staff recommends that the City Council accept the
improvements and authorize final payment and retention to Valley Crest
Landscape in the amount of $18,046.18.
ITEM NO. ~. ~ COPIES TO: Valley Crest Landscape