HomeMy WebLinkAbout4.04 AdvertiseContract 88-4 CITY OF DUBLIN
AGENDA STAT~EHENT
City Council Meeting Date: March 28, 1988
SUBJECT:
Contract 88-4 Annual Street Overlay and Repair
Program and Dougherty Road Bike Path
EXHIBITS ATTACHED: Plans and Specifications will be available at the
y Council meeting.
RECOMMENDATION: / \~'~Authorize Staff to advertise for bids.
FINANCIAL STATEMENT:
STREET OVERLAY AND REPAIR:
Budgeted costs are as follows:
Design and Inspection $ 34,000
Overlay 190,000
Repair (overlay and slurry streets) 227,500
$ 451,500
DOUGHERTY ROAD BIKE PATH:
Budgeted costs are as follows:
Design, Topographic Survey,
and Inspection
Construction
Total:
Funding Through TDA Grant
$ 15,000
60,000
75,000
75,000
DESCRIPTION:
The annual street overlay and repair program and the Dougherty
Road Bike Path are being combined into one contract as the two projects will
both be bid by grading and paving contractors. Combining these similar
projects will reduce Staff administration time and should help to reduce unit
costs because of economies of scale.
overlay and Repair
The annual overlay program consists of placing at least a 1 1/2"
asphalt overlay on streets that are in a deteriorated condition. A special
pavement fabric will also be placed over the travelway prior to the asphalt
overlay. This fabric helps bridge the existing pavement cracks and prevent
the reflection of cracks through the new asphalt.
Before installing the overlay, the pavement failures are dug out
to the base and replaced with a section of asphalt. The contract also
includes repair on the streets which will be slurry sealed in late spring.
Additionally, this year's program will include replacement of 33 traffic
signal loop detectors at the intersections of Amador Plaza Road and Regional
Street at Dublin Boulevard. These loop systems have ceased to function
properly due to the deteriorated street section.
The streets to be overlaid this year are Regional Street (which
was repaired last year); Brighton Drive between Wexford Court and Amador
Valley Boulevard; and Tamarack Drive between Brighton Drive and Village
Parkway.
ITEM NO. ~ COPIES TO:
The following list identifies the streets
repaired under this contract.
Bonniewood Court
Bonniewood Lane
Ardmore Court
Sharon Court
Sharon Street
Kilrush Avenue
Lucanta Street
Limerick Avenue
Chatham Street
Cardiff Drive
Cardiff Court
Sheffield Court
Sheffield Lane
Alene Street
Canterbury Lane
Wexford Court
Firethorn Way
Elgin Lane
Knollwood Place
Aldea Street
Bonfield Court
Larkdale Avenue
Bristol Road
Cranford Lane
Diana Lane
Bedford Court
Bedford Way
Lisa Court
Mayan Court
Canterbury Court
Cardigan Street
which are to be
Sierra Lane
Sierra Court
Golden Gate Avenue
Amador Plaza Road
Newcastle Lane
Burnham Way
Dover Lane
Emerald Avenue
King Way
Clark Avenue
Sutton Lane
Peppertree Road
Jasmine Court
Hastings Way
Cardigan Court
Dougherty Road Bike Path
This project will construct an asphalt bike path along the east
side of Dougherty Road, beginning just north of the Southern Pacific Railroad
right-of-way and extending to Amador Valley Boulevard. The project also
relocates the chain-link fence belonging to Camp Parks eastward to a location
behind the bike path. ~
A bikeway along Dougherty Road was established by the County as
part of the County bikeway master plan. Dublin has adhered to this master
plan in completing such projects as the striped bike lanes on Amador Valley
Boulevard.
During FY 1986-87, Dublin applied for and obtained a TDA
bike/pedestrian grant in the amount of $75,000 for construction of the
Dougherty Road bike path.
- 2 -