HomeMy WebLinkAbout4.09 Advertise ForBids 89-3 CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: February 13, 1989
SUBJECT:
Contract 89-3 Annual Street Overlay and Repair
Program
EXHIBITS ATTACHED: Plans and Specifications will be available at the
City Council meeting.
RECOMMENDATION: ~/~~A~uthorize Staff to advertise for bids.
FINANCIAL STATEMENT:
Budgeted costs are as follows:
Design and Inspection (from CIP Budget)
Overlay (from CIP Budget)
Repair of overlay and slurry streets
(from Street Maintenance Budget, which includes
$5,000 for striping and $295,000 for street repair)
$ 30,000
174,000
300,000
$ 504,000
Engineer's Estimate for Construction:
474,000
DESCRIPTION:
The annual overlay program consists of placing at least a 1 1/2"
asphalt overlay on streets that are in a deteriorated condition. A special
pavement fabric will also be placed over the travelway prior to the asphalt
overlay. This fabric helps bridge the existing minor pavement cracks and
prevent the reflection of cracks through the new asphalt.
Before installing the overlay, the pavement failures are dug out
to the base rock and replaced with a section of asphalt. The contract also
includes repair on the streets which will be slurry sealed in late spring.
The repair will also include replacing 63 signal loop detectors which are in
failed areas. This year's overlay project will complete the rehabilitation
of the Brighton/Tamarack loop, begun in last year's project, and the downtown
loop (Village Parkway/Dublin Blvd./Amador Valley Blvd.) begun in 1984. This
last section of Amador Valley Boulevard was held off until the traffic signal
and median work could be completed between Amador Plaza' and Village Parkway.
The streets to be overlaid this year are Amador Valley Boulevard
between Starward and Village Parkway, Regional Street between Dublin
Boulevard and Amador Valley Blvd., Sierra Court from Dublin Boulevard 2000'
north, Tamarack Drive between Village Parkway and Elgin Lane, and Emerald
Ave.
The following list identifies the streets which are to be
repaired under this contract.
Burnham Way
Newcastle Lane
Langmuir Lane
Dover Lane
Elba Way
Thames Ct.
Emerald Ave.
Sierra Ct.
Regional Street
Mansfield Ave.
Darian Ct.
Brookdale Ct.
Newport Ct.
Elba Ct.
Amanda Lane
Stagecoach Rd.
Village Parkway
Ione Way
Ca]lan Street
Dover Ct.
Frederiksen Ct.
Burton Street
Tamarack Drive
Sierra Lane
Amador Valley Blvd.
ITEM NO. ~__ COPIES TO: