HomeMy WebLinkAboutItem 4.5 AdvertiseForBids 90-3 CITY OF DUELIN
AGENDA STATEMENT
City Council Meeting Date: February 26, 1990
SUBJECT:
Contract 90-03 Annual Sidewalk Safety Repair;
Handicap Ramp Construction; Modification of Civic
Center Service Driveway; and Dublin Boulevard
Sidewalk - South Side at Clark Avenue
(Report by: Public Works Director Lee Thompson)
EXHIBITS ATTACHED:
1) Resolution Adopting Sidewalk Repair Policy for
1989-90 Program
2) Policy for Fiscal Year 1989-90, Sidewalk Repair
Program
3) Plans and specifications to be available at
meeting
RECOMMENDATION:
Adopt policy resolution for Sidewalk Repair
Program
Authorize Staff to advertise for bids
FINANCIAL STATEMENT:
Funds budgeted are as follows:
Annual Sidewalk Safety Repair
Handicap Ramp Construction
Dublin Blvd. Sidewalk at Clark
Civic Center Service Entrance
Design/
Inspection
Construction Total
8,500 41,500 50,000
7,000 53,000 61,000
1,100 9,500 10,600
0 0 0
Total Project: $ 16,600 104,000 121,600
DESCRIPTION:
Funds are scheduled for the annual sidewalk program for each year of the Five
Year Capital Improvement Program. For Fiscal Year 1989-90, $50,000 has been
budgeted from the General Fund.
In 1985, the City Council adopted a policy for the repair of pedestrian
sidewalk hazards for 1984-85 Fiscal Year. It is Staff's recommendation that
this policy again be adopted for Fiscal Year 1989-90.
In order to obtain a lower per-project bid price, the 1989-90 sidewalk repair
program is being combined with three other projects involving sidewalk work.
(1) The City has been awarded $61,000 in TDA funds for Phase IV of a project
to construct handicap ramps throughout the City. (2) The Capital Improvement
Project to install sidewalk on the south side of Dublin Boulevard between
Clark Avenue and the Alamo Canal bridge will be constructed under this same
contract. This CIP will provide a continuous sidewalk along Dublin Boulevard
from Clark Avenue to the Civic Center and the Dublin Sports Grounds. The
City's Maintenance Department has already removed ice plant at this sidewalk
location. (3) The City's Traffic Engineer recommended modifications to the
Civic Center service entrance driveway which are proposed to be constructed in
conjunction with this contract. At the present time, no monies are budgeted
for this modification, and Staff recommends waiting until the bid prices are
available before transferring funds. The engineer's construction estimate for
the driveway modification is $10,775.
Staff recommends that the City Council adopt the policy resolution and
authorize Staff to advertise for bids.
ITEM NO.~__ COPIES TO:
RESOLUTION NO. -90
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
ESTABLISHING A POLICY FOR THE REPAIR OF PUBLIC IMPROVEMENTS DEEMED TO BE
PEDESTRIAN HAZARDS
WHEREAS, public improvements such as curbs, gutters, driveways,
and sidewalks sometimes become damaged due to natural and man-made causes;
and
WHEREAS, these damaged improvements sometimes become tripping
hazards to pedestrian traffic; and
WHEREAS, it is in the best interest of safety to have these
hazards eliminated;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
Dublin to establish a policy of the City of Dublin for Fiscal Year 1989-90
entitled "Annual Sidewalk Repair Program."
PASSED, APPROVED, AND ADOPTED this 26th day of February, 1990.
AYES:
NOES:
ABSENT:
Mayor
ATTEST:
City Clerk
POLICY FOR THE CITY OF DUBLIN
for Fiscal Year 1989-90
ANNUAL SIDEWALK REPAIR PROGRAM
It is the policy of the City of Dublin to cause repairs to be made to certain
public improvements for the safety of the general public under the following
guidelines.
Improvements Included:
Public improvements included under this program shall be limited to those
improvements which may constitute a potential tripping hazard to pedestrian
traffic such as curbs, gutters, driveways, and sidewalks.
Need:
Where these improvements have settled, heaved and/or cracked and offset such
as to represent a tripping hazard as identified by the City Engineer, or his
representative, these improvements shall be replaced.
Responsibility:
Where it is apparent that the damage to improvements has been caused by
natural causes such as tree roots or utility trench settlement, the City of
Dublin will pay for the cost of repair.
Where it is apparent that the property owner fronting the damaged improvement
has caused the damage, such as driving vehicles into a side yard, the
property owner shall be responsible for the repair. The City Engineer shall
establish a procedure whereby the property owner will be notified of the
needed repair, and if not done in a specified reasonable time, he shall cause
the repair to be made and the cost of repair, together with reasonable
administrative costs, shall become a lien against the property.
Time Limit of Policy:
This policy shall be in effect for the Fiscal Year 1989-90 and thereafter be
reviewed for extension, modification, or replacement.
Legal Responsibility:
The City of Dublin, in adopting this policy, does so as an accommodation to
property owners who find it difficult to hire their own contractors to make
these necessary sidewalk repairs. The City will let one contract for the
1988-89 Fiscal Year and repair those defective sidewalks which have been
brought to the attention of the City by the property owners (or others) and
that have an offset of over one half inch (1/2") measured vertically. The
existence of this program does not abrogate the responsibility of the
property owners to maintain their frontage improvements in a safe manner
under Section 5610 of the California Streets and Highways Code.