HomeMy WebLinkAboutReso 109-99 EngrSvc/MarkThomasRESOLUTION NO. 109 - 99
A RESOLUTI6N OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING AMENDMENT TO AGREEMENT FOR CONSULTING ENGINEERING
SERVICES WITH MARK THOMAS & CO., INC.
WHEREAS, the City Council of the City of Dublin approved an agreement for traffic engineering
services with Mark Thomas, on June 16, 1998 which term was for a one year period ending June 30, 1999;
and
WHEREAS, Mark Thomas has requested an adjUstment of rates; and
WHEREAS, the term of the agreement is proposed to be extended until June 30, 2001, allowing
Mark Thomas to request an adjustment of rates for the second year of the term;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby
approve the amendment to the agreement (adjUstment of rates and extension of term) with Mark Thomas
& Co., Inc., which is attached hereto as "Exhibit A".
BE IT FURTHER RE~SOLVED that the Mayor is authorized to execute the amendment.
PASSED, APPROVED AND ADOPTED this 24th day of June, 1999.
AYES:
Councilmembers Howard, McCormick,'Zika, Vice Mayor Lockhart and Mayor
Houston
NOES: None
ABSENT: None
ABSTAIN: None
EXHIBIT"A" OF RESOLUTION ]~"7 -99
AMENDMENT TO AGREEMENT
BETWEEN CITY OF DUBLI3; AND MARK THOMAS & CO., INC.
FOR TRAFFIC ENGINEERENG SERVICES
WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and Mark Thomas &
Co., Inc. (hereinafter referred to as "CONSULTANT"), entered into a one-year agreement on June 16,
1998, to provide engineering services to CITY; and
WHEREAS, Consultant has proposed and adjustment of rates; and
WHEREAS, Consultant and the City of Dublin wish to extend the term of said agreement
for an additional two-year period (terminating June 30, 2001);
NOW, THEREFORE, the parties hereto agree as follows:
Extension of Term
The term o£the agreement shall be extended until June 30, 2001.
Adjustment of Rates
Consultant's charge rates shall be as indicated on the attached Exhibit A.
Consultant shall be entitled to submit a request for an adjustment of rates for the second year of the
contract term; i.e., 2000-2001 fiscal year.
CITY OF DUBLIN
MARK THOMAS & CO., INC.
Date:
EXHIBIT A OF AMENDMENT
MARK THOMAS & CO. INC.
CHARGE RATE SCHEDULE
EFFECTIVE FEBRUARY 1, 1999
HOURLY CHARGE RATES
PROFESSIONAL AND OFFICE
Principal/Project Manager
Engineering/Structural Manager II
Engineering Manager I
Engineer X
Engineer IX
Engineer VIII
Engineer VII
Engineer VI
Engineer V
Engineer IV
Engineer III
Engineer II
Engineer I
Land Surveyor
Senior Survey Technician
Associate Design Technician
Engineer Technician II
Engineer Technician I
Engineering Draftsperson
Technical Writer
Clerical/Typist II
Clerical/Typist I
Messenger
FIELD
2 Person Field Party and Vehicle
3 Person Field Party and Vehicle
SPECIAL SERVICES
Expert Witness
MISCELLANEOUS COSTS
Reimbursables (Printing and Materials, Mail and Delivery
Expenses, Film Expenses, Filing Fees, Parking and Field
Expenses)
Mileage
$140.00 per hour
130.00 per hour
120.00 per hour
110.00 per hour
102.00 per hour
92.00 per hour
82.00 per hour
74.00 per hour'
68.00 per hour
62.00 per hour
57.00 per hour
52.00 per hour
47.00 per hour
96.00 per hour
75.00 per hour
80.00 per hour
52.00 per hour
42.00 per hour
65.00 per hour
65.00 per hour
52.00 per hour
40.00 per hour
26.00 per hour
$152.00 per hour
214.00 per hour
$ 200.00 per hour
-Cost plus 5%
-$0.26 per mile
Outside Consultant Fees -Cost plus 5%