HomeMy WebLinkAboutPCReso00-51 PA99-064 Rec CC Quarry School NegDec/MMP RESOLUTION NO. 00-51
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
RECOMMENDING CITY COUNCIL ADOPT A MITIGATED NEGATIVE DECLARATION
AND MITIGATION MONITORING PROGRAM FOR PA 99-064
V~-IEREAS, the applicant, Dr. Sabri Arac of Quarry Lane School has requested approval ora
Planned Development (PD) Prezoning and Annexation of an area of approximately 15 acres generally
located north of the City Limits at 6363 and 6237 Tassajara Road within the Eastem Dublin Specific Plan
area (APN: 985-0002-006-01,985-0002-005-01 and 005-02.); and
WHEREAS, the General Plan Amendment ("GPA") and Eastern Dublin Specific Plan ("EDSP")
were adopted by the City in 1994; and
WHEREAS, the EDSP provides more specific and detailed goals, policies and action programs
for approximately 3313 acres within the GPA area nearest to the City on its Eastern side; and
WHEREAS, a Program Environmental Impact Report ("Program EIW') was prepared for the
EDSP and GPA (SCH No. 91103604) and certified by the City Council on May 10, 1993, by Resolution
No. 51-93, and two Addenda dated May 4, 1993, and August 22, 1994 ("Addenda") have been prepared
and adopted by the City Council and are hereby incorporated by reference; and
WHEREAS, on May 10, 1993, the City Council also adopted Resolution No. 53-93, adopting the
GPA and EDSP, making findings and adopting overriding considerations as to the environmental impacts
and mitigation measures relating to the EDSP and GPA, and adopting a Mitigation Monitoring Program
("Program MMP") for the GPA and EDSP which resolution is hereby incorporated by reference; and
WHEREAS, an Initial Study has been prepared for the project to evaluate site-specific impacts of
the project, to a greater level of detail than in the Program EIR, pursuant to CEQA guidelines Section
15168. Based on the Initial Study, a Mitigated Negative Declaration and Mitigation Monitoring Program
has been prepared for the project with the finding that with the implementation of Mitigation Measures
previously adopted for the Program EIR and with site specific Mitigation Measures contained in the Initial
Study, the potential site-specific impacts of the project would be reduced to a level of insignificance. The
Program EIR and Initial Study adequately describe the impacts of the project, and there have been no
substantial changes or new information which would necessitate supplementing the Program EIR pursuant
to Public Resources Code section 21166 and CEQA guidelines Section 15162; and
WHEREAS, a complete application for the project is available and on file in the Planning
Department; and
WHEREAS, a 20 day public review period was held for the Mitigated Negative Declaration, from
July 19, 2000 through August 7, 2000; and
WHEREAS, a total of four comment letters have been received during the public review period
from the Attorney representing the adjacent property owner and local and State agencies;
WHEREAS, all pertinent comments have been responded to and have become part of the Response
to Comments attached as Attachment 4 to the staffreport, dated August 22, 2000 for PA 99-064
WHEREAS, the Planning Commission did hold a public hearing on said application on August 8,
2000 and August 22, 2000; and
WHEREAS, proper notice of said heating was given in all respects as required by law; and
WHEREAS, a Staff Report was submitted to the Planning Commission recommending City
Council adopt a Mitigated Negative Declaration and Mitigation Monitoring Program for PA 99-064; and
WHEREAS, the Planning Commission did hear and use their independent judgment and considered
all said reports, recommendations and testimony hereinabove set forth.
NOW, THEREFORE, BE IT RESOLVED THAT the Dublin Planning Commission does hereby
find that:
1. The project is within the scope of the Program Environmental Impact Report for the Eastern Dublin
General Plan Amendment and Specific Plan (SCH 91103064). Site-specific environmental affects
have been analyzed in the Initial Study prepared for the project and circulated for public review.
The project will not have a significant effect on the environment with the application of Mitigation
Measures identified in the Program EIR and in the Initial Study.
2. All pertinent comments received during the public comment period have been responded to and
have become part of the Response to Comments document.
The Mitigated Negative Declaration, Mitigation Monitoring Program, and the Response to
Comments have been prepared in accordance with State and local environmental laws and
guidelines.
4. The Mitigated Negative Declaration, Mitigation Monitoring Program, and the Response to
Comments are complete and adequate.
BE IT FURTHER RESOLVED THAT THE Dublin Planing Commission does hereby
recommend City Council adopt a Mitigated Negative Declaration and Mitigation Monitoring Program
for PA 99-064, the Mitigation Monitoring Program is attached as Attachment 8 to the Staff Report
dated August 8, 2000, the Initial Study/Mitigated Negative Declaration is attached as Attachment 7 to
Staff Report dated August 8, 2000, and the Responses to Comments is attached as Attachment 4 to
Staff Report dated August 22, 2000 are incorporated herein by reference.
2
PASSED, APPROVED AND ADOPTED this 22nd day of August, 2000.
AYES:
Cm. Hughes, Oravetz, Jennings, Johnson, and Musser
NOES:
ABSENT:
Community Development Director
Planning Commission Chairperson