HomeMy WebLinkAboutReso 61-09 Shannon Accept WorkRESOLUTION N0.61-09
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
ACCEPTANCE OF WORK -CONTRACT N0.07-02,
SHANNON COMMUNITY CENTER PROJECT
WHEREAS, Sierra Bay Contractors entered into a contract with the City of Dublin to complete
the construction of the Shannon Community Center in accordance with plans and specifications on file
with the City Engineer; and
WHEREAS, said improvements have been completed in accordance with said plans and
specifications, and any approved modifications thereof, with the exception of remediation of minor items,
to the satisfaction of said City Engineer of the City of Dublin; and
WEAREAS, as a condition of said contract, Sierra Bay Contractors is required to guarantee the
improvements for a period of one year following acceptance of the work by the said City of Dublin; and
WHEREAS, as improvements are now completed, and the original performance bond security
requirement can be reduced, in accordance with the authority contained in Section. 66499.7 of the
Government Code of the State of California, to an amount found necessary to guarantee maintenance of
the completed work for the aforesaid one-year period..
NOW, THEREFORE BE IT RESOLVED that:
1. The improvements are completed per plans and specifications except for minor punch list items,.
and the City Manager has the authority to approve and accept the improvements upon completion
of the remaining punch list items subject to the aforesaid one-year guarantee; and
2. Upon approval and acceptance by the City Manager, the aforesaid performance bond security
requirement may be reduced from the amount of $8,572,322 to the amount of $899,477 upon
acceptance by Staff of the replacement maintenance bond as security for the aforesaid one-year
maintenance period; and
3. Upon approval and acceptance'by the City Manager, the said original performance bond in the
amount of $8,572,322 posted in connection with the work involved in the construction of said
Facility is hereby released upon acceptance of said maintenance bond.
PASSED, APPROVED AND ADOPTED this 19th day of May 2009, by the following vote:
AYES: Councilmembers Biddle, Hart, Hildenbrand, Scholz, and Mayor Sbranti
NOES: None
ABSENT: None
ABSTAIN: None
~.J M~
Mayor
ATTES
c.~ (~ /
~~ L}1~ City Clerk
Reso No. 61-09, Adopted 5-19-09, Item 4.7 Page 1 of 1