HomeMy WebLinkAboutItem 4.02 Accpt Work Sidewlk Safeti~~ \
-~-~
''r\\V
CITY CLERK
File # ^~ b^^- 3^^5
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: September 1, 2009
SUBJECT: Acceptance of Work -Contract No. 09-06, 2008-2009 Annual
Sidewalk Safety Repair Program and Curb Ramp Installation
(Maxicrete, Inc.)
Report Prepared by: Melissa A. Morton, Public Works Director
ATTACHMENTS: 1) Fiscal Year 2008 / 2009 Budget Change Form
RECOMMENDATION: 1) Approve the budget change for Fiscal Year 2008-2009; and
2) Accept the improvements under Contract No. 09-06, 2008-
2009 Annual Sidewalk Safety Repair Program and Curb Ramp
Installation, and authorize the release of retention after 35
days if there are no subcontractor claims.
FINANCIAL STATEMENT:
~
~~~~'~ ~- ~~~ee ' ua1,
,
~
C~ ~ ~ ~ ~ Y - t:~' _ ~yMp~~
l~ i .~Yets 1
Sidewalk Safety Repair (949100) General Fund $ 65,000 $ 44,25 Transfer $1,500
to 939100
ADA Transition Plan /Curb General Fund $ 30,000 $31,500 Increase
Ramps (939100) appropriation
Sub-Tots $1,500 from
Sidewalk Pro'ect
Bike Lane Amador Valley Blvd. Traffic Impact Fees Additional
(96015) Electrical work of the #300(after signal & $ 4,214 $ 7,250 appropriation
project under separate contract.
Inspection) from Impact Fees
$3,036
Measure B Bike/Pe 42,243 25 12
Sub-Tota $ 46,457 $ 32,37
GRAND TOTAL 3 PROJECTS $141,457 $108,12
* Although the total cost of the three projects was less than the total budgeted amounts for improvements,
the City Council is requested to approve a Budget Change which will: 1) Transfer $1,500 of unexpended
General Funds from the Sidewalk project to the ADA Transition Plan Project; and 2) Authorize $3,036 in
COPY TO: Maxicrete, Inc.
G:\CIP\SIDEWALK\2008-2009\Agenda Statement acceptance.DOC
Page 1 of 2
ITEM NO. ~'
ri
additional expenditures from available Traffic Impact Fees for the Bike Lane Project. This will fully
exhaust the Amador Valley Blvd Bike Lane mitigation funds.
DESCRIPTION: On May 19, 2009, the City Council awarded Contract No. 09-06,
2008-2009 Annual Sidewalk Safety Repair Program and Curb Ramp Installation, to Maxicrete, Inc.
The Annual Sidewalk Safety Repair Program (Remove and Replace) repairs sidewalk offsets of 3/4-inch
or more that may pose a tripping hazard. The Remove and Replace process is used in locations where the
offset is more significant or where tree roots are causing the offset. This procedure requires removal of
the existing sidewalk, and in the case of root problems, removal of the tree roots, and then replacement of
the concrete sidewalk.
While the maintenance of sidewalks and other frontage improvements is legally the responsibility of the
private property owner, the City Council has adopted aCity-paid sidewalk repair program on a year-by-
year basis since 1983. At the budget hearing for Fiscal Year 2008-2009, the City Council extended the
funding of the repair program for an additional year.
This year's Sidewalk Safety Repair Program included the construction of twenty nine (29) pedestrian curb
ramps. Fourteen (14) of these ramps were funded as part of the Amador Valley Boulevard Bike Lane
Capital Improvement Project (CIP No. 960015). The remaining fifteen (15) ramps were funded through
the General Fund as identified in the ADA Transition Plan (CIP No. 939100). In addition, 3,518 square
feet of sidewalk was repaired. Staff has reviewed the work performed under this contract and has
determined that the work is satisfactory and complete.
As noted in the financial section of this report, the improvements were completed under budget for the
three projects combined. A Budget Change is required to recognize minor adjustments to the funding on
two of the projects. The first change represents an increase in funding for the ADA Transition project of
$1,500. The source of funds will be a reduction in the Sidewalk Repair Project, which has funds
available. The second change is intended to address the complete expenditure of Mitigation Funds held
for the Amador Valley Boulevard Bike Lane project. After the budget for the project was adopted,
additional interest earnings were available in the mitigation fund. This change will allow the City to
expend an additional $3,036 which will fully expend these special funds. The expenditure of the
Mitigation Funds will also reduce the amount of Measure B funds required for the project.
RECOMMENDATION: Staff recommends that the City Council 1) approve the Budget
Change for Fiscal Year 2008-2009; and 2) accept the improvements under Contract No. 09-06, 2008-
2009 Annual Sidewalk Safety Repair Program and Curb Ramp Installation, and authorize the release of
retention after 35 days if there are no subcontractor claims.
Page 2 of 2
.CITY OF DUBLIN
BUDGET CHANGE FORM FY 2008 / 2009
CHANGE FORM #
~~ 1
New Appropriations (City Council Approval Required): Budget Transfers:
X From Unappropriated Reserves (Traffic MitigationFund)= From Budgeted Contingent Reserve (1080-799.000)
Within Same Department Activity
From New Revenues X_ Between Projects (City Council Approval Required)
Other
DECREASE BUDGET~ACCOUNT AMOUNT (DT(~REASE BIIDGFTA(>Ct}UNT ' AMOiJNT
Name: EXPENSE: General Fund - 08/09- Name: EXPENSE: General Fund - OS/09-
Sidewalk Repair Project -Improvements $ 1,500 Americans With Disabilities Transition Plan $ 1,500
Project -Improvements
Project Account #: 94100-9400-9401-1001 Project Account #: 939100-9400-9401-1001
GL Account #: GL Account #: 3300.9301.73103
Name: EXPENSE: Traffic Mitigation Funds
(Project Specific) -Amador Valley Bike $ 3,036
Lane Project -Improvements
Project Account #: 960015-9400-9401-4309
GL Account #: 3600.9601.73103
Fin Mgr/ASD: ~~It~X~ • `~~~
Signature
REASON FOR BUDGET CHANGE ENTRY: This budget change will: 1) Transfer $1,500 in unexpended
Sidewalk Repair Project funding to the Americans With Disabilities Act Transition Plan Project. This project
constructed curb ramps and adjacent sidewalks at several locations in the City. 2) Authorize an additional
expenditure of Traffic Mitigation funds in lieu of Measure B Funds, on the Amador Valley Boulevard Bike
Lane Project.
The Budget Change was presented to the City Council 9/1/2009 as part of the acceptance of project)
improvements.
City Manager:
Mayor:
Posted By:
Signature
Date:
Date:
G:IBudgetChm+ges!/_2008_09!9_9_/_09_TripleSidewalkProj.DOC ATTACHMENT # 1
Signature
Date: O 2.! ~ Q'
Date:
As Approved at the City Council Meeting on: Date: 9/1/2009
Signature