HomeMy WebLinkAbout7.3 MurrayBellTowerCITY CLERK FiIe#E1W10_3ff ,55 AGENDA STATEMENT CITY COUNCIL MEETING DATE: November 19, 2002 SUBJECT: Murray Schoolhouse Bell Tower Project Report Prepared by (Rosemary Alex, Parks and Facilities Development Coordinator) ATTACHMENTS: 1) Budget Change Form RECOMMENDATION: 41A Approve Budget Change FINANCIAL STATEMENT: Contract Amount $ 99,500 Change Orders # 1-3 11,852 Total $111,352 Available Budget 109,450 Shortfall $ 1,902 It is also recommended that an additional 5% contingency ($5,568) be added to the project. Therefore an additional allocation from the Unappropriated Reserves for a total of $7,470 is needed. DESCRIPTION: On July 161h, 2002 the City Council awarded the design -build contract for the Murray School Bell Tower to TGK Contracting for the amount of $99,500. With the award of contract the council also approved a 10% contingency for the project for a total project budget of $109,450. Construction has been initiated and the following change orders have resulted: 1) Change Order #1, Foundation Demolition and Stair Reconstruction $5,491 The removal of the entry stair deck revealed an extensive concrete foundation for the stairs. In order for the foundation to be demolished, the entry stairs will need to be removed and reconstructed. 2) Change Order #2, Structural Calculations for Existing Wall Studs $242 The contractor removed a portion of the existing wall to determine the size of the wall studs that will support the reinforced roof truss. The size of the wall studs were 2 x 4 and will need to be reinforced. The engineer will provide a detail and structural calculations for the reinforced wall studs. -------------------------------------------------------------------------------------------------------------� COPIES TO: TGK Contracting ITEM NO. 7• Wcc-forms/agdastmt.doc Added 3) Change Order #3, Wall Studs Reinforcement $6,119 In accordance with current building codes and confirmed by the structural engineer, the existing wall studs will be reinforced with two 2 x4's nailed on either side of the wall stud. This will require the removal of a portion of the interior wall finishes to perform the work and repair the wall. Total Amount $11,852 Approved Contingency Amount $9,950 Difference ($1,902) Although the City Manager is authorized to approve Change Orders up to $25,000, there are insufficient fimds in the project budget to process Change Order #3. Consequently an additional appropriation for $1,902 from the Unallocated Reserves is needed. Also, since the project is still in its early stages of construction, it is recommended that an additional 5% contingency ($5,568) to address any unforeseen changes in construction scope of work be approved bringing the total project budget to $115,018. The proposal for Change Order #3 was received by Staff after Agenda was posted for the November 19, 2002 City Council meeting. Since the project is currently under .construction, Staff is seeking City Council approval on this item as to not further delay this project. RECOMMENDATION: It is the recommendation of Staff that the City Council approve the Budget Change authorizing an additional appropriation for $7,470 from the Unallocated Reserves for the Murray School Bell Tower Project. CITY OF DUBLIN BUDGET CHANGE FORM CHANGE FORM # New Appropriations (City Council Approval Required): Budget Transfers: X From Unappropriated Reserves From Budgeted Contingent Reserve (1080-799.000) Within Same Department Activity From New Revenues Between Departments (City Council Approval Required) Other Name: Name: Murray School Bell Tower General Fund Improvements Account #: $ Account #001.95560.750.050 $ 7,470 Name: Name: Account #: Account #: Name: Name: Account #: Account #: Name: Name: Account #: Account #: Name: Name: Account #: Account #: Fin Mgr/ASD: v~~ VN,,.~..o.~.~x~ Date: \\ ~ \ ~/~7,.~ Signature REASON FOR BUDGET CHANGE ENTRY: Additional resources are necessary for' the Murray School Bell Tower renovation project. The funds will be used to complete the additional scope of work to date and provide for an increased construction contingency. City Manager: Date: Signature Mayor: Date: Signature Posted By: Date: Signature formslbudgchng