RESOLUTION NO. 10-XX
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
RECOMMENDING CITY COUNCIL CERTIFICATION OF FINAL SUPPLEMENTAL
ENVIRONMENTAL IMPACT REPORT AND ADOPTION OF ENVIRONMENTAL FINDINGS
UNDER CEQA FOR THE NIELSEN PROPERTY RESIDENTIAL PROJECT
(6407 TASSAJARA ROAD - APN 985-0002-009-02)
PA 07-057
WHEREAS, Robert Nielsen submitted applications for the creation of thirty-four (34)
residential lots on the property located at 6407 Tassajara Road in the City of Dublin (Alameda
County Assessor's Parcel Number (APN) is 985-0002-009-02) ("Project Site"). The maximum
number of dwelling units that would be located on the Project Site are thirty-six (36). The project
includes applications for the following: (1) a General Plan Amendment and Eastern Dublin Specific
Plan Amendment to modify the land use designation from Rural Residential/ Agriculture to Single
Family Residential and to reduce the width of on-site streets; (2) a Planned Development Rezone
with a related Stage 1 Development Plan Amendment and Stage 2 Development Plan from PD-
RR/A to PD-SFR to allow construction of up to 36 dwellings on the Project Site; and (3) a Vesting
Tentative Subdivision Map for the Project Site. The applications are collectively known as the
"ProjecY"; and
WHEREAS, the Project is located in Eastern Dublin and the Eastern Dublin Specific Plan
area, for which the City Council certified a Program Environmental Impact Report by Resolution
51-93 ("Eastern Dublin EIR" or "EDEIR", SCH 91103064) on May 10, 1993 (incorporated herein by
reference). The Eastern Dublin EIR identified significant impacts from development of the Eastern
Dublin area, some of which could not be mitigated to less than significant. Upon approval of the
Eastern Dublin General Plan Amendment and Specific Plan, the City Council adopted
environmental findings, mitigations, a mitigation monitoring program, and a Statement of
Overriding Considerations (Resolution 53-93, incorporated herein by reference) in accordance with
the requirements of the California Environmental Quality Act ("CEQA"); and
WHEREAS, significant unavoidable impacts were identified in the Eastern Dublin EIR that
apply to the Project and Project site, therefore, any Project approval must be supported by a
Statement of Overriding Considerations; and
WHEREAS, in compliance with the requirements of CEQA, the City prepared an Initial
Study to determine if the proposed Project would require additional environmental review beyond
that analyzed in the Eastern Dublin EIR. The Initial Study found that many anticipated impacts of
the proposed Project have been adequately addressed in the Eastern Dublin EIR. This is
consistent with the comprehensive environmental analysis undertaken as part of the Eastern
Dublin EIR with a 20-30 year build-out horizon. Although the Initial Study concluded that the
Eastern Dublin EIR adequately analyzed most of the potential environmental impacts of the
proposed Project, it also identified the potential for certain new significant impacts or substantially
more severe impacts beyond those analyzed in the Eastern Dublin EIR. The City of Dublin
determined that the potential for new and/or substantially more severe impacts required
1 ATTACHMENT 5
preparation of a supplemental EIR for certain impact areas pursuant to the requirements of CEQA;
and
WHEREAS, the City circulated a Notice of Preparation, dated May 23, 2008, with the Initial
Study to public agencies and interested parties for consultation on the scope of the supplemental
EIR. The City also conducted a public scoping meeting on June 18, 2008; and
WHEREAS, based on the Initial Study and responses to the Notice of Preparation, the City
prepared a Draft Supplemental Environmental Impact Report (DSEIR) dated January 2009 for the
proposed Project which reflected the City's independent judgment and analysis of the potential
environmental impacts of the Project beyond those analyzed in the Eastern Dublin EIR (See
Exhibit A, incorporated herein by reference). The DSEIR confirmed that many aspects of the
Project were within the scope of the Eastern Dublin program and that the certified Eastern Dublin
EIR adequately described these aspects of the Project for CEQA purposes; and
WHEREAS, the DSEIR was circulated for public review from February 2, 2009 to March 25,
2009; and
WHEREAS, the City received comment letters from State and local agencies and interested
parties during the public review period. In accordance with the requirements of CEQA, the City
prepared written responses to all the comments received during the public comment period. The
City prepared a Final Supplemental EIR (FSEIR), dated April 2010, for the proposed Project which
included an annotated copy of each comment letter identifying specific comments, responses to
each specific comment, and clarifications and minor corrections to information presented in the
DSEIR. The FSEIR incorporates the DSEIR. The responses to comments provide the City's good
faith, reasoned analysis of the environmental issues raised by the comments (Exhibit B,
incorporated herein by reference); and
WHEREAS, the City carefully reviewed the comments and written responses and
determined that the FSEIR, including the clarifications and minor corrections to the DSEIR, do not
constitute significant new information requiring recirculation of the DSEIR under the standards in
CEQA Guidelines section 15088.5; and
WHEREAS, a staff report, dated April 27, 2010 and incorporated herein by reference,
described and analyzed the Project for the Planning Commission and contained information on the
Eastern Dublin EIR and FSEIR; and
WHEREAS, the Planning Commission reviewed the staff report, the Eastern Dublin EIR, the
FSEIR, including comments and responses, at a noticed public hearing on April 27, 2010 at which
time all interested parties had the opportunity to be heard; and
WHEREAS, the FSEIR, including comments and responses, reflects the City's independent
judgment and analysis on the potential for environmental impacts from the Project; and
WHEREAS, the FSEIR and related Project and environmental documents, including the
Eastern Dublin EIR, and all of the documents relating to the Project are incorporated herein by
reference, and are available for review in the City Planning Division at the Dublin City Hall, file PA
07-057, during normal business hours. The location and custodian of the FSEIR and other
documents that constitute the record of proceedings for the Project is the City of Dublin Community
Development Department, 100 Civic Plaza, Dublin, CA 94568, file PA 07-057; and
2
NOW, THEREFORE, BE IT RESOLVED THAT, the Dublin Planning Commission hereby
makes the following findings and recommendations to the City Council on the FSEIR and the
environmental review of the Project under CEQA:
A. The foregoing recitals are true and correct and made a part of this resolution.
B. The FSEIR has been completed in compliance with CEQA, the CEQA Guidelines and the
City of Dublin Environmental Guidelines.
C. The Planning Commission has independently reviewed and considered the information
contained in Eastern Dublin EIR and FSEIR, including the written comments received during
the DSEIR review period and the oral and written comments received at the public hearing,
prior to making its recommendation on the proposed Project.
D. The FSEIR reflects the City's independent judgment and analysis on the potential
environmental impacts of the proposed Project. The FSEIR provides information to the
decision-makers and the public on the environmental consequences of the proposed
Project.
E. The FSEIR adequately describes the proposed Project, its significant environmental
impacts, mitigation measures and a reasonable range of alternatives to the proposed
Project.
BE IT FURTHER RESOLVED the Dublin Planning Commission hereby recommends that,
prior to the approval of the Project, the City Council certify the Final Supplemental Environmental
Impact Report as complete, adequate and in compliance with CEQA, the CEQA Guidelines, and
the City of Dublin Environmental Guidelines, make all required findings regarding environmental
impacts of the Project, mitigation measures and alternatives (including, adoption of a Statement of
Overriding Considerations) and adopt a Mitigation Monitoring and Reporting Program, all in
compliance with the requirements of CEQA.
PASSED, APPROVED, AND ADOPTED this 27th day of April, 2010 by the following vote:
AYES:
NOES:
ABSENT: