AGENDA STATEMENT
CITY COUNCIL MEETING DATE: May 6, 2003
SUBJECT: Award of Bid — Contract No. 03-06,
2002-2003 Annual Street Overlay Project
Report Prepared by: Lee S. Tlzoinpson, Public Works Director
ATTACHMENTS: 1) Resolution.of Award
2) Bid Results
3) Location map of Overlay Streets
RECOMMENDATION: *10
FINANCIAL STATEMENT:
Adopt resolution awarding Contract No. 03-06, 2002-2003 Annual
Street Overlay Project, to Top Grade Construction
2002-2003 Annual Street Overlay:
Salaries/Inspections/Miscellaneous
Improvements — Overlay
Subtotal
Improvements — Slurry seal pavement repairs
TOTAL:
FY 2002-2003
Budget
$ 28,760
$630,740
$659,500
$ 25,000*
$684,500
Low Bid
$379,731.70
$ 7,129.00
$386,860.70
* Pavement repairs for slurry seal streets have been included in this contract as a cost -savings
measure and are funded through the Gas Tax in the Annual Slurry Seal Program. The budget
amount is approximate and the remainder of funds will be used for the Annual Slurry Seal project.
The FY 2002-2003 Annual Overlay budget includes funding from the General Fund ($28,760),
Measure B Local Streets & Roads Fund ($219,000), Gas Tax ($312,740) and Traffic Congestion
Relief Program (TCRP) funds ($99,000). However, it is anticipated that the TCRP funds available
for this project will be less than budgeted due to State budget cuts.
The low bid of $386,860.70 for the 2002-2003 Annual Street Overlay is $243,879.70 less than the
original amount budgeted for improvements, which is $630,740. Due to the current construction
climate for asphalt concrete (AC) work, bids were lower than anticipated, even though oil and gas
prices have increased substantially this year. As a result, Staff will work with the low bidder to
include additional streets in the project area for pavement repair and overlay, as allowed, with a
revised budget accounting for the reduced TCRP funds.
COPIES TO: Top Grade Construction
ITEM NO.
9
g:\overlay\2003\AS award
CC
DESCRIPTION: On April 1, 2003, the City Council authorized Staff to solicit bids
for Contract No. 03-06, 2002-2003 Annual Street Overlay Project.
The Am~ual Street Overlay project consists of removing and replacing failed asphalt concrete pavement to
a minimum depth of 4 inches, resurfacing the street with a 1-1/2-inch overlay of asphalt concrete, and re-
striping pavement markings. Major cracks will be sealed prior to resurfacing in order to prevent the
cracks from reflecting through the new overlay. Pavement fabric will be placed on major arterial and
collector streets such as Village Parkway to control cracks and further pavement base failure.
Pavement repair for slurry seal streets is also included in this Overlay contract as this type of work is not
normally performed by contractors specializing in slurry seal. A reduced cost to the City is achieved by
incorporating the repairs with the Overlay project. The annual slurry seal project will follow shortly after
completion of the overlay project.
Notices have been sent out to advise residents and schools of the work to be performed.
The 2002-2003 overlay project will repair and overlay the following streets:
Countess Court Longford Way
Countess Street Chatam Street
Valencia Street Limerick Court
Deervale Court Limerick Street
Cavalier Lane Diana Lane
Cavalier Court Ardmore Street
Ferncliff Court Bonniewood Court
Shamrock Place Bonniewood Lane
Beverly Court Sharon Court
Wexford Court Kilrush Avenue
Firethom Way Elgin Lane (southernmost leg only)
Portion of San Ramon Road Bike Path 200' north of Vomac Road
This contract will also repair the pavement for the following streets in preparation for the Annual Slurry
Seal Program:
Amarillo Road Tory Way
Rolling Hills Drive Ann Arbor Way
Mansfield Avenue Eden Street
Emerald Avenue Hemlock Street
Burton Street Ebensburg Lane
Betlen Drive (Hansen Drive to Las Palmas Court)
San Ramon Road (North City Limit to Silvergate Drive)
A total of eleven bids were received (Attachment 2). The low bidder is Top Grade Construction with a
bid of $368,860.70. Staff has reviewed the bids and determined that the low bid contractor has
satisfactorily performed similar jobs.
Staff recommends that the City Council adopt the resolution awarding Contract No. 03-06, 2002-2003
Annual Street Overlay Project, to Top Grade Construction.
Page 2
RESOLUTION NO. - 03
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AWARDING CONTRACT NO. 03-06
2002-2003 ANNUAL STREET OVERLAY PROJECT
TO TOP GRADE CONSTRUCTION
WHEREAS, the City of Dublin did, on April 22, 2003, publicly open, examine, and
declare all sealed bids for doing the work described in the approved Plans, Specifications, and
Modifications for Contract No. 03-06, 2002-2003 Annual Street Overlay Project, authorized by the City
Council on April 1, 2003, which Plans, Specifications, and Modifications are hereby expressly referred
to for a description of said work and for all particulars relative to the proceedings under the request for
bids; and
WHEREAS, said bids were submitted to the City Engineer, who has recommended that
the bid hereinafter mentioned is the lowest and best bid for doing said work;
NOW, THEREFORE, BE .IT RESOLVED that the City Council of the City of Dublin does
hereby award City of Dublin Contract No. 03-06 to the lowest responsible bidder therefor, to wit, Top
Grade Construction, at a bid of Three Hundred Eighty-Six Thousand, Eight Hundred Sixty Dollars and
Seventy Cents ($386,860.70), the particulars of ~vhich bid are on file in the Office of the City Engineer.
BE IT FURTHER RESOLVED that the Mayor is authorized to execute the Agreement.
PASSED, APPROVED AND ADOPTED this 6th day of May, 2003.
AYES:
NOES:
ABSENT:
ABSTAINING:
Mayor
ATTEST:
City Clerk
G: 10 VERLA Iq2003 t reso award, doc
SUMMARY OF BID RESULTS - Apr 22, 2003 .. ~
CONTRACT 03-06, ANNUAL STREET OVERLAY PROJECT .......
..... ENGINEER'S ESTIMATE TOP GRADE SILICON VALLEY PAVING REDGWICK CONSTR. C.F. ARCHIBALD MCK SERVICES
BID .......... UNIT ........ T
ITEM ITEM DESCRIPTION MEASURE QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE
1 _ .Stripi_ng & Marking Rem ~-al L§' ~._ _ 1 ~$ 5,0"00~0 ~ 5 0_0_"0.p0 i $ 24~)0.0(~ ~$ 2,4~0-0.00 .............. $ 2.000.00 $ 2.000.00 $ 2.500.O0 ' $ - -2,500.00 ~ ' 2.500.00 ' $ 2,500.00 $ 2.000.00 $ 2.000.00
2 Plane AC Pavement12' Wide LF 1,560 $ 3.._0."0_ 4,680:0_0.$. 2.50-$ 3,900.00_$ 1.00._$ _1.._5.6_(~._00 _$ .1_.70.$ 2,652.00 $ 2.40 $ 3,744.005__ _1.40 $ 2.184.00
~-'Pl~n~ACPavemer~'~'Wide LF 24,499 $ 1.50 36,748.50 $ 1.00 $ 24.499.00 $ 0.50 $ 12,249.50 $ 0.80 $ 19,599.20 $ 0.80 $ 19.599.20 $ 0.79 $ 19,354.21
4a 'Failure Repairs 3" (~)_ver~a-~;) - ~ 104,419 ......................... '$ 1.85 $ 193 175.15 :$- - '1.~3~"' $ 135.74~.~0--$ 1.35 $ 140,965.65 $ 1.45 $~-5'~2,~$ '1.;~5 ' $ 140.96-~-' $ 1.80 ~ $ 187,954.20
4b-FaiiL~mRepairs3"(SlurryS_~_al) SF 875 $ 1.85 $ 1,618.75_$ __.2..0(~0_ $ 1,750.00 $ 2.00 $ 1,750.00 $ 3.00 $ 2.625.00 $ 1.50 $ 1,312.50 $ 1.98 $ 1,732.50
4_c...~ai!_u_reRepairs4"(SanRamonRd) "-S-F .... : 3,586'$ _!~_85.$ 6,63410. $ 1.500 $ 5,379.00 $ 2.00 _$ _7,172.q0._ $ 2.6015-- ~i~2-3760_~$ 2.80 $ 10,040.805 . 2_.20 _$ 7,889:20
5 Crack Sealing .... L~_ __ 1 $ 10,000.00 $ 10,000.00 $ !0,~0(~.0"0. $ 10,500.00 $ 9.000.00 ~ $ 9.000.00 $ 6.200.00 $__ _.6=200.00 $ 5.000.00 $ 5.000.00 $ 8.000.00 $ 8,000.00
6a Install1 1/2" AC overlay _ SF 383,324_$ 0.60. 229,994.40 $ 0.45 $ 172,495.80 $ 0.50 ........ $ 191.662.00 $ 0.48 $ 183,995.52 $ 0.50 $ 191,662.00 $ 0.39 $ 149.496.36
~b 'Install 1 1/2"AC overlay(Woodrose_) SF 650 $ 0.60 390.00 $ 3.00 $ 1.950.00 $ 10.00 $ 6,500.00 $ 1.40 $ 910.00 $ 5.00 $ 3,250.00 $ 0.41 $ 266.50
7 Adjust Monuments to Grade EA 30 $ 300.00 $ 9 000.00 ' ~ '~ 200.00 ~ 6~000 00 $ 75 00 $ 5,250.00 $ 200~-0"~ ' -~,000.00 $ '-"240.00~ 7,200.00 $ 250.00 $ 7,500.00
8 12"StopBar V~i~i~e, Therm~)--___~ LF . _ 218 _ $ 3~0- 65400 $ - ~:~'~$ 436.0_0. $ 2.0_0 '$_ 436.00 .... ~ 2.00- $ 4-36.~)~) $ 2.50 $ 545.00 $ 2.00 '$ -'436.00
9 12" Stop Bar, Yellow, Thermo. LF .... 388 $ 2.50_ 970.00 $ 2.00 $ 776.00 ..... $ 2.00 $ 776.00 $ 2.00 $ 776.00 $ 2.50 ' ......... $- - 970.00 $ 2.00 $ 776.00
"1'0'" D~i~ 21, Yel ow, Thermo. LF 1,054 $ 1.50 1,581.00 . $ 1.30 $ 1,370.20 $ 1.40 $ 1,475.60 $ 1.50 $ 1.581.00 $ 1.50 $ 1,581.00 $ 1.40 $ 1.475.60
l~"~'EL~DL~gend, The~pl-astic _ _~,~._ , ~i~.$ 125.0-d"-~; 125.00- $ 100.00 $ 100.00_$ 125.00 $ 1~.'(~_0' $ 100.0--(~'"'$- 100.0~.-$- i!_0.00_-$ _11.0:0_0_$ 100.00 $ 100.00
12 STOP Legend, Thermoplastic ! EA 12 $ 100.00 1,200.00 $ 100.00 $ 1,200.00 $ 100.00 ............ $ 1,200.00 $ 100.00 $ 1.200.00 $ 110.00 $ 1,320.00 .__$. 100.00 ........ $ 1.200.00
13 Reflective Markers (Blue) i EA 30-~ 18.00 i $-" 540.00 $ 1~:0(~ j $ 360.00 $ 10.00 _ $ 300.00 $ 10.00 $ 30.0.00 . $ 11.00 $ 330.00 $ 11.00 $ 330.00
- TOTAL: : i $ 502,310.90' i'~; 368,86~.~70 $ 3.82_,42'1.75 $ 389,60,~.8~ $ 390,130.15 $ 390,694:5.7
-:.' ~ .... ' : :_ - . ~' Amou,t c~rrected after ver_ifi_ca~i_o.n of calculation
.... DESILVA GATES O'GRADY PAVING EL CAMINO PAVING BAY CITIES PAVING GALEDRIGE CONSTR. GRANITE CONSTR.
BID .... UNIT .... ~
ITEM ITEM DESCRIPTION MEASURE QTY UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE TOTAL PRICE UNIT PRICE ............ TOTAL PRICE UNIT PRICE TOTAL PRICE
I rSti'iping& ~a~ki~g Remova! LS '~ · ~" 3,700.00 ~ $ 3,700.00 .~$ 2 600.0_0 . $ 2 600.00 '~ ~,300.00 r ~ 2,300.00 ~ :~.__ 6 688.00 : $ .6 688_.00 -- $ 2.700.00 $ 2.700.00 $ 2.500.00__.$___ 2,500.00
2 PlaneAC Pavement 12'W!de . [~F ~ 1,560 $ 3.00 $ 4,680.00 $ 2.00 $ 3,120.00. $ .2.335. $ 3,642.60 ~ $ 1.92 $ 2.995.20 $ _ 1_.450 $ 2.262.00 $ 2.00 $ 3,120.00
3 Plane AC Pavement 6' Wide LF 24,499 $ 1.00 $ 24,499.00 $ 0.95 $ 23,274.05 $ 0.80 $ 19.599.20 $ 1.16 $ 28.418.84 $ 0.7725 $ 18.925.48 $ 1.00 $ 24.499.00
4_a iFailu?¢_ReP~ir~s3"(Oveday) SF '. 104¢419'~'$ 1_.45_'~;-' 1~1,407.55_.__$ 1.43 $ 149.319.17 $ 1.69 $ 176.468.11 ' $ $ 1.73 $ 180,644.87 $ 1.80 $ 187.954.20
4b Failure Repairs 3" (Slu_r.~y Seal) . SF 875 $ 1.45 $ 1,268._7_5.. _$~ 3.00. $ 2,625.00_ $ 4.62 ' $ 4,-042.~d ' ~ 4.~ ~ $ 3.543.75" $. 2.00 $ 1.750.00 $ 1.~(~ ' $ 1.575.00
4c Failure Repairs 4" (San Ramon Rd) . . SF _ 3,586 . $ 2.70 $ 9,682.20 $ 3.00 $ 10,758.00 $ 2.03 $ 7.279.58 $ 4.22 $ 15,132.92 $ 2.75 $ 9,861.50 $ 2.00 $ 7.172.00
5 Crack Sealing LS 1 $ 100000 $ 1,00000 $13,000.000'$ 'i3(~00.00 $ 11:742.00 $ 11,742_00 $ 20000.00 $ 20,000.00-- i $12 540.000*$ 12;540~00 $ 11.00~0~ ~ 11,000.00:
6a Install 1 1/2" AC overlaY ...... SF . 383 324 $ O.~.8 ' $ 183,995.52 is. 0.47 $ 180.162.28_ $ 0.475 $182,078.9~ ' ' $ 0_~50. :-$191,662.~ i $. 0.532 $ 203.928.37 $ 0:5~7- $ 209,678.2--3
6b ,l_ns_tall ! l/2"ACoverl~y__(Woodrose) SF 650 $ 1.00 $ 650.00 . $ 5.00_ $ ~,250.00 $ 3.40 $ 2,210.00 $ 4.09 $ 2.658.50 $ 2.00 $ 1.300.00 $ 0.55 $ 357.50
7 Adjust Monum_e~t_s to Grade . . EA 30 $ 190.00 . $ 5,'(~0.00 ~$ _180.00 . $. 5,400.00 $ 190.00 $ 5.700.00 ........ $ 270.30 $ 8.109.00 ' $-' 305.00' $ 9.150.00 $ 210.00 . $ 6:3_0~)._00
8 12" Stop Bar, White, Thermo. . LF . 218 $ 2.00 $ 436.00 $ 2.20 $ 479.60 $ 2.07 $ 451.26 $ 2.04 ......... $ 444.72 $ 3.00 $ 654.00 $ 2.20 $ 479.60
9 .12" Stop Bar, _Ye!!~.w_, Thermo. LF 388 $ 2.00 $ 776.00 $ 2.20 ' $ 853.60 $ 2.065 ....... $ 801.22 $ 2.04 $ 791.52 $ 3.00 $ 1,164.00 _$ ~ 2.20 $ ...... 853.60
10 Detail 21, Yel_low, Thermo. _. LF %054 -$ "- 1.50 i$ 1,~1.00: $ 1.55 $ 1,633.70 $ 1.445 $ 1,523.03 $ 1.43 $ 1.507.22 $ 1.679 $ 1,769.67 $ 1.50 $ 1,581.00
11 YIELD Legend, Thermoplastic EA 1 $ 100.00 ~ $ 100.00 ~ . 110:00': ~; .11_0.00 ~ $ 103.00 $ 103.00 ' ' $ 102.00' $ 102.0~) ' ' $ 150.00 $ 150.00 $ 110.00 $ 110.00
EA $
12 iSTOPLegend Thermoplastic ' 12 100.00 $ 1,200.00 $ 110.00 $ 1.320.00 $ 103.00 $ 1,236.00 $ 102.00 $ 1,224.00 - ' $ '- 125.00 --$ ~500.00 $ 110.00 $ 1.320.00
13 Reflective Markers (Blue) EA 30 $ 10.00: $ 300.00 I $ 12.00. '$ 3~(~00._ $_ '1-1.~.33 ~$ 339_90 .............. $ 11 22 $ 33660 $ 17.00 $ 510.00 $ 11.00 $ 330.00
..... TOTAL:]" f i $ 390,976.02 $ 398265,40 $ 419,517.30 - $ 433,977.63 ' $ 448,809.88 $ 458,830.13
~,~?.4~.~2002 - 2003 Annual Street Overlay Program
'~,~? Location Map
~ I I IM~ -- Streets Illl Pavement Resurfacing - Overlay
0.126 0,25 0.5 0,76 1