CITY COUNCIL MEETING DATE: June 2003
SI.IBJECT: Amendment to Consulting Services Agreement with CCS Planning
& Engineering, Inc., for the 1-580/Fallon Road Interchange
Improvements Project (Modification to Scope of Work and
Additional Compensation)
Report Prepared by: Lee S. Thompson, Public Works Director
ATTACHMENTS: 1) Resolution Amending Agreement
2) Original Agreement dated May 16, 2000, Amendment #1 & #2
RECOMMENDATION: Adopt Resolution Approving Amendment No. 3 to the Agreement
M with CCS Planning & Engineering, Inc.
FINANCIAL S Contract Amendment #3 will modify CCS' scope of work for an
additional compensation of a not to exceed amount of $383,849.
The Dublin Ranch developer has agreed to contribute $208,829 to
pay for this additional work and will receive additional credit equal
to this amount against payment of future Eastern Dublin Traffic
Impact Fees. Pleasanton will reimburse Dublin $175,020 for the
Pleasanton-related work included in the amendment, per funding
agreement with the City of Pleasanton. The funding agreement is
being brought to the Council as a separate agenda item this evening.
DESCRIPTION: In March 2000, the City contracted with CCS Planning &
Engineering for the design of the 1-580/Fallon Road Interchange Improvements. The contract was
amended in May 2001 (Amendment #1) to include significant additional environmental and design
tasks identified by Caltrans during their review of the draft Project Report/Environmental Documentation
(PR/ED). It was again amended in December 2001 to include additional preliminary design work and
environmental analysis requested by Pleasanton, in conjunction with additional improvements to the
interchange associated with proposed developments in Pleasanton. This additional work includes a
northbound Fallon Road to westbound 1-580 loop to accommodate traffic from the proposed Staples
Ranch development in Pleasanton. The consultant is nearing completion of the Caltrans' required Project
Report/Environmental Document and is now ready to finalize the project plans and specifications
incorporating the Pleasanton-related improvements. Amendment #3 to CCS' consulting services
agreement includes additional services to incorporate these improvements (in the amount of $175,020)
and Dublin will be reimbursed by Pleasanton for these costs.
COPIES TO: Tom Wintch, CCS
g:\engr\ccs\agst_FallonAmendment~3
Several tasks are also being added to Amendment #3. Caltrans has indicated that the Federal Highway
Administration's (FHWA) approval of the project will be required since the project will introduce two
additional access points onto 1-580 by the way of the new eastbound and westbound loops. This
additional effort, which was not included in CCS' original scope, will require preparation of the
"Modified Access Report" and will involve several meetings with Caltrans and FHWA for its approval.
In addition, the original scope of work did not include any geotechnical design work concerning the
pavement of the existing interchange and Caltrans has indicated that the existing pavement will need to be
resurfaced due to its deteriorated condition.
Furthermore, the Dublin San Ramon Services District (DSRSD) has requested the City to incorporate the
design of a 30" welded steel casing into the proposed Fallon Road freeway overcrossing. DSRSD has
issued a purchase order to pay for the DSRSD-related design work and intends to have a funding
agreement with the City on the construction of the steel casing.
Lastly, Amendment #3 will include construction support service to provide assistance to the project
Resident Engineer in responding to Request for Information, Contract Change Orders, and questions from
the City.
The additional Dublin-related work required under Amendment #3, in the amount of $208,829, will be
paid by the Dublin Ranch developer and will receive additional credit against payment of future traffic
impact fees equal to this amount.
Staff recommends that the City Council adopt the resolution approving Amendment No. 3 to the
Agreement with CCS Planning & Engineering, Inc.
Page 2 '"" ~
RESOLUTION NO. - 03
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING AMENDMENT #3 TO AGREEMENT WITH
CCS PLANNING AND ENGINEERING, INC. FOR CONSULTING SERVICES
1-580/FALLON ROAD INTERCHANGE IMPROVEMENTS DESIGN
WHEREAS, future freeway and inter-agency infrastructure is planned to be constructed as part of
the development process in Eastern Dublin, and improvements are required at the Interstate 580/Fallon
Road interchange; and
WHEREAS, on May 16, 2000, the City Council of the City of Dublin approved an agreement for
design services with CCS Planning & Engineering, Inc. (CCS), for the design of salad improvements; and
WHEREAS, on May 1, 2001, the City Council of the City of Dublin approved Amendment #1 to '
the agreement with CCS Planning and Engineering, Inc., to include additional services, and
WHEREAS, on December 18, 2001, the City Council of the City of Dublin approved Amendment
#2 to the agreement with CCS Planning and Engineering, Inc., to include additional preliminary
engineering and environmental services requested by the City of Pleasanton, and
WHEREAS, CCS' scope of work is now being expanded to include the final design of the
Pleasanton-related improvements and additional Caltrans-required tasks in order to complete the plans and
specifications.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby
approve Amendment No. 3 to the agreement with CCS Planning and Engineering, Inc., which is attached
hereto as "Exhibit A".
BE IT FURTHER RESOLVED that the Mayor is authorized to execute the amendment.
PASSED, APPROVED AND ADOPTED this 3rd day of June, 2003.
AYE S:
NOES:
ABSENT:
ABSTAIN:
Mayor
ATTEST:
City Clerk g:\engr\ccs~reso_fallon Amendment #3
EXHIBIT "A" OF RESOLUTION -03
AMENDMENT #3 TO AGREEMENT
BETWEEN CITY OF DUBLIN AND CCS PLANNING AND ENGINEERING, INC.
FOR ENGINEERING SERVICES
WHEREAS, the City of Dublin (hereinafter referred to as "CITY") and CCS Planning and
Engineering, Inc. (hereinafter referred to as "CONSULTANT"), entered into an agreement on May 16,
2000 to design the 1-580/Fallon Road Interchange Improvements; and
WHEREAS, the City Council of the City of Dublin approved Amendment #1 and #2 to the
Consultant agreement to include additional services, and
WHEREAS, the City desires to amend the consultant contract to include additional services, and
the not-to-exceed contract amount is proposed to be increased to cover the cost of the additional work;
NOW, THEREFORE, the parties hereto agree as follows:
Scope of Work
The Scope of Work shall be extended to include additional scope of work as described in
Consultant's letter dated March 6, 2003 for the 1-580/Fallon Road Interchange Improvements Project
(attached).
Extension of Fees
The total cost for time-and-materials work under this amendment shall not exceed an additional
$383,849.
CITY OF DUBLIN
Mayor
ATTEST:
City Clerk
CCS PLANNING AND ENGINEERING, INC.
Tom Wintch
Date:
, ~--~a~ PLANNING AND -~"NGINEERING
I N C 0 R P 0 R A T E D
925/314-1220 · Fax 925/314-1229
March 6, 2003 emait: sRo@ccsoffice, co,~
Mr. Ferd Del Rosario Mr. Eric Cordoba
City of Dublin Cordoba Consulting, Inc.
100 Civic Plaza 5368 Laurel Drive
Dublin, CA 94568 Concord, CA 94521
Subject: 1-580/Fallon Road Interchange
Additional Scope of Work/Design Costs Request No. 3
Gentlemen:
As requested at our status meeting on October 17, 2002; the CCS Design Team has summarized the
significant additional design, geotechnical and management activities required to complete the
contract plans £or the 1-580/Fallon Road interchange project. These additional activities represent
engineering and geotechnical effort that was not included in the original contract scope of work and
Amendments No. 1 and No. 2 £or this project. In addition, at our PDT meeting with Caltrans on
December 13, 2002, Caltrans had raised the issue o£ processing this project through £ederal
requirements since this project will introduce two additional access points onto 1-580. We are also
requesting Engineering Services during Construction which was requested previously but has not
received confirmation.
Each additional management, engineering, geotechnical, environmental, traffic, and construction
support service activity is described and a corresponding cost identified within the text o£ the.
"Additional Scope o£ Work No. 3" attachment. A cost breakdown by activity and team firm is
presented on the accompanying spreadsheet.
Part of these cost increases for the 1-580/Fallon Road Interchange Project are related to the additional
northbound to westbound loop as requested by City o£ Pleasanton, and the design schedule delay
associated with the additional loop. As you know, the additional traffic study, Geometrics Approval
Drawings, environmental updates, and revision to the PSR/PR due to the addition of this NB/WB
loop are covered in our Amendment No. 2 request, this amendment is £or design effort to complete
the contract plans.
The fee proposal prepared in April 2000 anticipated that final design would be completed by early
2001. Due to the extension o£ the design phase, this request is to update the hourly rates to the
current 2003 rates. The new rates to begin in January 2003.
We are also requesting to include Engineering Services during Construction into this amendment.
In March 2001, City o£ Dublin had requested CCS to prepare scope and budget £or this activity since
Construction Support Services is not included in the original scope of work. CCS prepared and
submitted the information to City on March 23, 2001 but has not been submitted as an amendment.
Since this project now includes City of Pleasanton funding portion o£ design and construction, the
attached spreadsheets include segregated City of Dublin's share and City o£ Pleasanton's share. The
P:~98104PSE~kdmin-FallonPS&E\Scoping-Fees~P S & E~Jmendment No.3-030603.doc
T R A N S P 0 a T A Y i O N 0 ; V I C I T S
March 6, 2003
CCS Job #98104
Page 2
percentage allocation to each city for our additional services was discussed at our meetings on
December 19, 2002, and February 20, 2003.
Please feel free to call Jim Pun or me for any additional questions or clarifications that may arise.
Sincerely,
CCS Planning and Engineering, Inc.
Thomas M. Wintch, PE, TE
TMW:ts
Attachment
1-580/Fallon Road Interchange Modification Project
City of Dublin
Additional Scope of Work No. 3
A. Northbound to Westbound loop - This activity will begin with the approval of the
Geometric Approval Drawings (GAD) to completion of the contract plans. This effort
includes additional Layout for the loop, Typical Cross Sections, contour grading,
drainage, signing, striping, electrical including ramp metering, landscaping, erosion
control, and quantities.
(100% allocated to City of Pleasanton)
Cost Increase $53,230.
B. Pavement Rehabilitation of the Interchange - This activity includes providing
geotechnical engineering sendces leading to recommendation and design for pavement
rehabilitation of the existing 1-580/Fallon Road/Et Charro Road Interchange, and
incorporating the recommendation to completion of the contract plans. The original
contract scope-of-work did not include any geotechnical or design work on existing
pavement or ramps that are only being widened and not receiving new pavement. As in
the 1-580/Tassajara Road Interchange Modification project, Caltrans mandated the
existing pavement to be resurfaced due to safety reasons.
(90% allocated to City of Dublin, 10% to City of PleasantOn)
Cost Increase $15,996.
C. Incorporation of DSRSD 30" Welded Steel Pipe Casing - Dublin San Ramon Sanitary
District requested a 30" Welded Steel Pipe casing to be installed into the proposed Fallon
Road Overcrossing. This 30" WSP will accommodate a future 24" water line. At the
time of the DSRSD request, the design of the Fallon Road Overcrossing was completed
to a 65% level awaiting for independent check. This activity included re-designing the
structure to accommodate the additional dead weight from the WSP and the 24" pipe
running full. The notice to incorporate the pipeline into the 1-580/Fallon Road project
was given to us on February 2002. An agreement will be needed between City of Dublin
and DSRSD for DSRSD to fully reimburse the City to cover both design and construction
costs.
(100% allocated to City of Dublin)
Cost Increase $16,270.
D. Additional Traffic Study in conjunction with the Northbound to Westbound loop -
This activity includes the additional traffic study requested by City of Pleasanton beyond
the level of effort estimated under Amendment No. 1. This additional effort has been
discussed with City of Pleasanton and received verbal approval.
(100% allocated to City of Pleasanton)
Cost Increase $16,044.
P:\98104PS EkAdmin-FalloruPS&E\Scop/ng-Fees\P S & E~.mendment No.3-030603.doc
1-580/Fallon Road Interchange
E. Possible Additional Studies and Reports (From 12/13/02 PDT Meeting) - At our PDT
Meeting with Caltrans on December 13, 2002, Caltrans raised the issue the possibility of
processing this project through federal requirements, since this project will introduce two
additional access points onto 1-580 by way of the new eastbound and westbound loops.
Additional federal action could be triggered since a "Modified Access Report" will need to
be prepared with approval from FHWA. This additional effort anticipates environmental
re-evaluation of the project, revision of traffic volume to current year, additional meetings
with Caltrans and FHWA, and other miscellaneous studies and reports.
(50% allocated to City of Dublin, 50% to City of Pleasanton)
Cost Increase $87,286.
F & G Schedule Adjustment and Rate Adjustment - As a result of the decision to study the
need to include the northbound to westbound loop into the project, the overall design
schedule has increased by 19 months (from Jan. 02 Final PS&E submittal to Aug. 03).
This request is to capture additional coordination and meetings.
(50% allocated to City of Dublin, 50% to City of Pleasanton)
Cost Increase $33,212.
The fee proposal prepared in April 2000 anticipated that final design would be completed
by early 2001. Due to the extension of the design phase, this request is to update the
hourly rates to the current 2003 rates. The cost increases is obtained by taking the
differences between the years 2003 and 2001 rates; and multiply by the hours for 65%,
95%, and 100% submittal as shown in the original 4/00 proposal. The rates adjustment
is to begin in January 2003 through the end of the contract.
(50% allocated to City of Dublin, 50% to City of Pleasanton)
Cost Increase $66,291.
H. Construction Support Service - The original contract scope-of-work did not include any
engineering services during construction. As in the 1-580/Tassajara Road Interchange
project, CCS is involve in providing assistance to the Resident Engineer in shop drawing
reviews, responding to contractor's RFI's, preparing as-needed CCO's, and respond to
questions from the RE.
(90% allocated to City of Dublin, 10% to City of Pleasanton)
Cost Increase $93,520.
I. Additional Direct Expenses - Additional direct expenses due to these additional
Engineering Services.
(30% allocated to City of Dublin, 70% to City of Pleasanton)
Cost Increase $2,000.
Total Additional Scope of Work #3:$383,849
City of Dublin - $208,829
City of Pleasanton - $175,020