HomeMy WebLinkAbout8.1 Attch 08 PC Reso to Recommend CC Certification RESOLUTION NO. 13- xx
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
RECOMMENDING CITY COUNCIL CERTIFICATION OF A FINAL ENVIRONMENTAL
IMPACT REPORT AND ADOPTION OF ENVIRONMENTAL FINDINGS UNDER CEQA FOR
THE DUBLIN CROSSING SPECIFIC PLAN
PA 08-049
WHEREAS, the Applicant, Dublin Crossing LLC (SunCal Companies) has submitted a
Planning Application to enable private development on approximately 189 acres of property that
is currently part of the Camp Parks Reserve Forces Training Area. The proposal includes the
approval of the Dublin Crossing Specific Plan, General Plan Amendments, Zoning Ordinance
Amendments, Rezoning properties to a new Dublin Crossing Zoning District, and consideration
of a Development Agreement and certification of an Environmental Impact Report, among other
related actions. These planning and implementing actions are collectively known as the "Dublin
Crossing Specific Plan Project" or the "Project"; and
WHEREAS, the Dublin Crossing Specific Plan (DCSP) project area is approximately
189 acres in size and is generally bound by 5th Street to the north, Scarlett Drive to the
west, Dublin Boulevard to the south, and Arnold Road to the east. The Project Area
includes properties identified by Assessor Parcel Numbers 986-0001-001-15 (partial), 986-
0034-002-00, and 986-0034-006-00; and
WHEREAS, the California Environmental Quality Act (CEQA), together with the State
guidelines and City environmental regulations require that certain projects be reviewed for
environmental impacts and that environmental documents be prepared. It was determined that
an Environmental Impact Report (EIR) be prepared to analyze the Dublin Crossing Specific Plan
Project; and
WHEREAS, the City circulated a Notice of Preparation, dated June 4, 2012, to public
agencies and interested parties for consultation on the scope of the EIR. The City also
conducted a public scoping meeting on June 20, 2012; and
WHEREAS, the City prepared a Draft Environmental Impact Report (EIR) dated June
2013 for the proposed Project that reflected the City's independent judgment and analysis of the
potential environmental impacts of the Project. The Draft EIR is incorporated herein by
reference; and
WHEREAS, the Draft EIR was circulated for public review from June 24, 2013 to August
8, 2013 (45 days); and
WHEREAS, the City received comment letters from State, regional, and local agencies
as well as interested individuals and organizations during the public review period. In
accordance with the requirements of CEQA, the City prepared written responses to all the
comments received during the public comment period. The City prepared a Final EIR (that
includes the Responses to Comments), dated October 2013, for the proposed Project, which
1 ATTACHMENT 8
included an annotated copy of each comment letter identifying specific comments, responses to
each specific comment, and clarifications and minor corrections to information presented in the
Draft EIR. The Final EIR is attached as Exhibit A to this Resolution and is incorporated herein
by reference (Exhibit A also contains the complete EIR — Draft EIR, Appendices, and Final EIR
combined — on a CD within the document). The complete Dublin Crossing Specific Plan EIR
incorporates the Draft EIR and the Final EIR together. The responses to comments provide the
City's good faith, reasoned analysis of the environmental issues raised by the comments; and
WHEREAS, the City carefully reviewed the comments and written responses and
determined that the Final EIR, including the clarifications and minor corrections to the Draft EIR,
do not constitute significant new information requiring recirculation of the Draft EIR under the
standards in CEQA Guidelines section 15088.5; and
WHEREAS, a Staff Report, dated October 22, 2013 and incorporated herein by
reference, described and analyzed the Project for the Planning Commission and contained
information on the Final EIR; and
WHEREAS, the Planning Commission reviewed the Staff Report, the Final EIR, including
comments and responses, at a noticed public hearing on October 22, 2013 at which time all
interested parties had the opportunity to be heard; and
WHEREAS, the Final EIR, including comments and responses, reflects the City's
independent judgment and analysis on the potential for environmental impacts from the Project;
and
WHEREAS, the Final EIR identified several potentially significant impacts that will be
reduced to a less than significant level with specified mitigation measures. Approval of the
project by the City Council will therefore require adoption of findings on impacts and mitigations
and a Mitigation Monitoring and Reporting Program; and
WHEREAS, the Final EIR/EIS identified significant and unavoidable environmental
impacts of the project and approval of the project by the City Council will therefore require
adoption of Findings and a Statement of Overriding Considerations: and
WHEREAS, the Final EIR and all of the documents relating to the Project are available
for review in the City Planning Division at the Dublin City Hall, file PA 08-049, during normal
business hours. The location and custodian of the Final EIR and other documents that
constitute the record of proceedings for the Project is the City of Dublin Community
Development Department, 100 Civic Plaza, Dublin, CA 94568, file PA 08-049.
NOW, THEREFORE, BE IT RESOLVED THAT, the Dublin Planning Commission hereby
makes the following findings and recommendations to the City Council on the Final EIR and the
environmental review of the Project under CEQA:
A. The foregoing recitals are true and correct and made a part of this resolution.
B. The Final EIR has been completed in compliance with CEQA, the CEQA Guidelines and
the City of Dublin Environmental Guidelines.
2
C. The Planning Commission has independently reviewed and considered the information
contained in the Final EIR, including the written comments received during the Draft EIR
review period and the oral and written comments received at the public hearing, prior to
making its recommendation on the proposed Project.
D. The Final EIR reflects the City's independent judgment and analysis on the potential
environmental impacts of the proposed Project. The Final EIR provides information to
the decision-makers and the public on the environmental consequences of the proposed
Project.
E. The Final EIR adequately describes the proposed Project, its significant environmental
impacts, mitigation measures and a reasonable range of alternatives to the proposed
Project.
BE IT FURTHER RESOLVED the Dublin Planning Commission hereby recommends
that, prior to the approval of the Project, the City Council certify the Final Environmental Impact
Report as complete, adequate and in compliance with CEQA, the CEQA Guidelines, and the
City of Dublin Environmental Guidelines. The Planning Commission further recommends that
the City Council make all required, mitigation and alternatives findings, adopt a Statement of
Overriding Considerations, and adopt a Mitigation Monitoring and Reporting Program, all in
compliance with the requirements of CEQA.
PASSED, APPROVED, AND ADOPTED this 22nd day of October, 2013 by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Planning Commission Chair
ATTEST:
Assistant Community Development Director
G:1PA#120081PA 08-049 Camp Parks Dublin Crossing12011 RestartlPC Mtg 10.22.20131PC Att 8-Reso FEIR.docx
2185663.1
3