HomeMy WebLinkAbout4.09 G&O Update CITY CLERK # 100-80 AGENDA STATEMENT CITY COUNCIL MEETING DATE: November 8, 2000 SUBJECT: 2000-2001 Goals & Objectives Status Report & CIP Schedule Prepared by: Richard C. Ambrose, City Manager ATTACHMENTS: Goals & Objectives Status Report Capital Improvement Program Schedule RECOMMENDATION: ~ Receive the Report \ FINANCIAL STATEMENT: None DESCRIPTION: On February 29, 2000, the City Council adopted the Goals & Objectives Program for Fiscal Year 2000- 2001. In order to keep the City Cotmcil abreast of Staff progress towards the objectives assigned by the City Council, Staff has prepared a bi-monthly status report for the period ending October 31, 2000. As of that date, a total of 32 of 117 objectives (28%) have been completed. With respect to high priority objectives, a total of 25 out of 88 (29%) have been completed. Of the 88 high priority objectives, only 6 have yet to be started. There have been two major additional assignments since February 2000. In June 2000, the Council established a Capital Improvement Program (CIP) for Fiscal Years 2000-2005 and appropriated funds for Fiscal Year 2000-2001. The attached CIP schedule lists 56 projects that received funding in Fiscal Year 2000-2001 and identifies an estimated start and completion date for each project. The schedule only includes a time frame for those projects that are funded in Fiscal Year 2000- 2001. Subsequent phases and future projects included in the 5 year CIP but not funded in Fiscal Year 2000-2001 are not listed on the schedule. Projects that have a portion of the construction costs appropriated in Fiscal Year 2000-2001, but will continue for several years (Library, Emerald Glen Fire Station etc.) include notes indicating estimated final completion dates. The City has completed 2 CIP projects since the program was approved in June 2000. RECOMMENDATION: It is Staff's recommendation that the City Council receive the report. H/cc-forms/agdastmt.doc COPIES TO: ITEM NO. ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10131100 PAGE 1 # I. 1. COUNCIL PERSON PRIORITY RESPONSIBLE GENERAL GOVERNMENT A. ADMINISTRATION High Carter YEAR 1998 2. High Herma 1998 3. High Herma 1999 High High High High High Carter Thompson/ Pappa Ambrose Keck Keck 1995 1999 2000 2000 2000 ADDITIONAL OBJECTIVES (ADMINISTRATION > I I I H~ B. FINANCE ::1> 1. High lAmbrose 2000 "r'_ :~: 2. High Perry 2000 ITI. Z PROPOSED OBJECTIVE FOR ACCOMPLISHING GOAL ESTIMATED START ~ Renegotiate Cable Television Franchise Agreement 1999 Complete Civic Center Modifications to accommodate growth in City Complete Schematic Design, Design Development and Construction Documents for Civic Center Library Update Performance Evaluation Process Develop a Geographic Information System (GIS) including the integration of existing City information systems Provide level of funding for "Computers for Our Schools". Appoint Council Subcommittee to Investigate Expanding Sister City Program with trade opportunities Photographs of Mayor & City Council in City Offices Negotiate Tax Sharing Agreement with BART and City of Pleasanton to facilitate development of Western Dublin/Pleasanton BART Station Initiate an on-going audit program for the Transient Occupancy Tax to ensure proper collection and compliance with the tax Sept. 1999 Aug. 1999 1998 July 2000 Sept. 2000 Oct. 2000 ESTIMATED STATUS COMPLETION Dec. 2000 UNDERWAY; Introduction of Ordinance/Agreement tentatively scheduled for December 2000 Council Meeting; negotiation still underway. Nov. 2000 NEARLY COMPLETE Construction UNDERWAY; Bid set on schedule for Documents Jan January 2001 2001 Jan./Feb. 2001 UNDERWAY; document under development Feb. 2001 UNDERWAY: Implementation plan drafted. Awaiting approval of contract with Calif CAD Solutions. COMPLETE COMPLETE; Lockhart and McCormick , appointed 4/18/00 Nov. 2000 UNDERWAY; Individual Council ' appointments to be scheduled mid to late November. I COMPLETE Dec. 2000 UNDERWAY. Field work should be completed by 11/00; with final audit report in 12/00 # COUNCIL PERSON YEAR PRIORITY RESPONSIBLE 3. Medium Peabody 1996 4. Medium Ambrose 1999 ADDITIONAL OBJECTIVES (FINANCE) ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF I0/3t/00 PAGE 2 PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED GOAL START Report on cost effective alternatives for processing small purchases. (Cal Card Program- Sponsored by the State of California) Undertake Formation of Dublin Ranch Infrastructure Financing District and issue Bonds D. PUBLIC RELATIONS 1. High J Carter 2000 2. High Carter 1999 C. INTERGOVERNMENTAL RELATIONS 1. High J Peabody I 2000 Participate in Tri-Valley Vision Project I 2. Medium Thompson 1999 Work with Zone 7 Flood Control and other cities to update and fund major Valley storm facility improvements ADDITIONAL OBJECTIVES (INTERGOVERNMENTAL RELATIONS) I 3. High 4. High Carter 2000 Pappa 2000 Produce Video newsletter Support Sponsorship of Teacher Participation in League of CA Cities "Participating in Local Government Program" Publish a City Newsletter Expand City's Website Information 5. Medium Carter 1999 ~ Develop a plan to implement "Know Your City Week" ADDITIONAL OBJECTIVES (PUBLIC RELATIONS) July 2000 Mar. 2001 July 2000 Mar. 2001 ESTIMATED STATUS COMPLETION COMPLETE NO PROGRESS; Property owner has notified the City there is no interest in proceeding with the Assessment District at this time I July 2001 p UNDERWAY; monthly meetings - 3 task forces COMPLETE -Advisory Committee has completed work. June 2001 NO PROGRESS COMPLETE ' Oct. 2000 COMPLETE; Pending public distribution June 2001 i UNDERWAY; Continuing Updates By · Consultant NO PROGRESS COUNCIL PERSON J YEAR PRIORITY RESPONSIBLE E. CONTRACT ADMINISTRATION High 2000 Carter ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF I0131/00 PAGE 3 IPROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED GOAL START Perform Contract Evaluation on the following services: Crossing Guards 5. Medium Peabody Cunningham Ambrose/ Cunningham Ambrose Building & Safety Animal Shelter Services Police Services 1996 i Report to Council on Countywide review of Library Services ADDITIONAL OBJECTIVES (CONTRACT ADMINISTRA'I"ION) II. I J I COMMUNITY DEVELOPMENT A. PLANNING 1. !High Peabody 2000 2. High Peabody 1999 3. High Peabody 1999 4. High Peabody 1999 5. High 6: High 7. High 8. High 9. High 10. High 11. High 12. High Peabody/ 1999 Thompson Peabody 1999 Thompson 1998 Peabody 2000 Peabody 2000 Peabody 2000 Peabody 1999 Peabody 2000 Process $175 million in new building valuation Village Parkway Specific Plan Western Bart Station Specific Plan Downtown Core Shopping Area Specific Plan (Montgomery Wards Shopping Center) Downtown Physical Improvements Plan Implementation Program for Inclusionary Housing Ordinance (include review of Senior Housing) Street Landscape Master Plan for eastern Dublin Update Housing Element Identify & Expand Alternative Funding Sources for Purchase of Open Space and/or Development Rights Evaluate the desirability of detaching lands West of Skyline Ridge (with the exception of Schaefer Ranch) from the City's Sphere of Influence General Plan Study of proposed western Dublin Urban Limit Line Complete annexation request for Tassajara Road properties (Quarry School, etal) FY 1999-2000 July 2000 FY 1999-2000 FY 1999-2000 FY 1999-2000 Sept. 2000 FY 1999-2000 FY 1999-2000 Mar. 2001 O~.2000 FY 1999-2000 FY 1999-2000 FY 1999-2000 ESTIMATED STATUS COMPLETION Jan. 2001 COMPLETE; Except for review of additional crossing guard as warranted COMPLETE UNDERWAY COMPLETE NO PROGRESS; Pending reporting from County Library I July 2001 UNDERWAY; $85.7 million as of 10131/00 Oct. 2000 UNDERWAY; CC 11/21 Oct. 2000 UNDERWAY; CC 11/21 Oct. 2000 UNDERWAY; CC 11/21 April 2001 UNDERWAY; CC 11/7 for award Jan. 2001 UNDERWAY; Back to CC 1/2001 Jan. 2000 UNDERWAY Dec. 2001 NO PROGRESS Feb. 2001 UNDERWAY; 212001 target to CC Feb. 2001 UNDERWAY; To be completed after Open Space Implementation Mar. 2001 UNDERWAY; CC approval 11/21 ;-LAFCO target March 2001 Dec. 2000 UNDERWAY; implementation after election # COUNCIL PRIORITY 13. High PERSON YEAR RESPONSIBLE Peabody 1996 14. Medium Peabody 15. Medium Peabody 16. Medium Peabody 17. Low Peabody 18. Low ;Peabody I 19. Low ] Peabody 1999 1997 1999 2000 1999 1998 ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10131100 PAGE 4 PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED GOAL START Develop City Telecommunication Policy beyond FY 1999-2000 Zoning Ordinance amendments for wireless communication Undertake General Plan Amendment for eastern FY 1999-2000 Dublin Transit Center Update & conduct 5 year review of Dublin's General Plan Revise General Plan and Zoning Maps and create new City maps Develop View & Solar Access Ordinance Study establishment of a Redevelopment Design Review Committee for project areas identified by City Council Study feasibility of developing a recreational vehicle storage facility in Dublin ADDITIONAL OBJECTIVES (PLANNING) I ESTIMATED STATUS COMPLETION June 2001 UNDERWAY Mar. 2001 UNDERWAY NO PROGRESS; Not funded COMPLETE NO PROGRESS Project abandoned per Council direction; redevelopment not legally feasible at this time. NO PROGRESS June 2001 UNDERWAY; 2 of 3 completed as of 10/31/00 July 2001 B. BUILDING & SAFETY 1. High i Thomas 2000 2. High 'Thomas 2000 Provide three building code seminars for the counter Staff and Inspectors Complete ADA Evaluation of City buildings 3. High Thuman 2000 Develop Program to Encourage Homeowners to Put House Numbers on Residence through Neighborhood Watch Program & Website 4. Medium Thompson ~ 2000 Develop Curb Address Painting Program ADDITIONAL OBJECTIVES (BUILDING & SAFETY) C. ENGINEERING 1. High Thompson 1996 Update and expand standard street improvement details (street lights, decorative paving, median landscaping) July 2000 July 2000 July 2000 Jan. 2001 July 2000 Ongoing UNDERWAY; Consultant selected & report underway. UNDERWAY; Community Safety Assistants, during Neighborhood Watch Meetings, routinely stress importance of house numbers on residences. June 2001 UNDERWAY Mar. 2001 UNDERWAY I # I COUNClL PERSON YEAR PRIORITY RESPONSIBLE ADDITIONAL OBJECTIVES (ENGINEERING) I I D. ECONOMIC DEVELOPMENT 1. High J Foss 2000 2. High Foss 2000 3. High Foss 2000 4. High Foss 2000 ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/00 PAGE 5 PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED GOAL START Make 400 business recruitment and retention contacts for the City of Dublin Target 200 mailings to attract businesses to Dublin Prepare and distribute Space Available report 3 times per year Implement 2000 Farmers' Market July 2000 July 2000 July 2000 5. High Foss 1999 Complete City Promotional Video 6. High Foss 2000 Prepare Comprehensive Economic Development Marketing Program for the City 7. Medium Foss 2000 Participate in selected Trade Shows to market properties in Dublin ADDITIONAL OBJECTIVES (ECONOMIC DEVELOPMENT) Oct. 2000 July 2000 III. 1. = CULTURE & LEISURE A. PARKS & COMMUNITY SERVICES High Peabody 1999 Complete Open Space Study as directed by City Council for land outside the Urban Limit Line in Western Dublin High Thompson 1992 Complete development of Iron Horse Trail High Lowart 1995 High Ambrose/ 1997 Lowart Develop a Parks Implementation Plan for eastern Dublin Work with U.S. Army to secure conveyance/lease for additional park land at Camp Parks FY 1999-2000 FY 1999-2000 Jan. 2000 ESTIMATED 1STATUS COMPLETION I June 2001 UNDERWAY - Staff has made 175 business contacts to date. June 2001 June 2001 UNDERWAY; Staff has prepared 95 letters to date. UNDERWAY - 1-~t report completed City Council action on 3/7/2000 directed that the Farmers' Market be placed on hold for an indefinite period. COMPLETE Video complete; 250 copies have been distributed. Feb. 2001 UNDERWAY; Council approved consultants in September, 2000. Project is expected to take 15-20 weeks. June 2000 NO PROGRESS - No funding was included in the FY 2000-2001 budget for this activity. I I July 2000 June 2001 COMPLETE UNDERWAY; City's portion is under design, Award is targeted for March 2001 COMPLETE TBD NO FURTHER ACTION POSSIBLE; proposal submitted to Army in January.- Army not interested in conveying parkland. # 5. 6. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. COUNCIL PRIORITY High High High High High High High High High High High High Medium Medium Medium PERSON RESPONSIBLE Lowart Lowart Lowart Thuman/ Lowart Ambrose/ Lowart Thompson/ Lowart/ Peabody Thompson Lowart Lowart Lowart Lowart Lowart Lowart Lowart Lowart YEAR 2000 2000 2000 2000 2000 2OOO 20OO 2O00 2000 2OOO 2000 2OOO 2O00 1999 1999 ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/00 PAGE 6 PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED GOAL START Conduct a dedication/grand opening celebration for Emerald Glen Park Investigate feasibility of expanding afterschool Aug. 2000 recreation program to Dougherty Elementary School if space permits Undertake an evaluation of park play areas to Sept. 2000 determine compliance with state and federal safety criteria and ADA accessibility Develop an enhanced park security program for Emerald Glen Park Update Use Agreement with Dublin Unified School District to maintain District Fields/Playgrounds and use of School Facilities iDevelop Public Information Program for bicycle & pedestrian routes/paths/facilities through out Dublin Install Second Kiosk along Iron Horse Trail Expand teen programming to include summer camp/excursion programs for middle school teens Expand programming to include monthly special events for middle and high school teens Expand summer playground program to Emerald Glen Park in Summer 2001 Evaluate locations for a Community Garden Explore feasibility of purchasing a 15 passenger van for the Senior Center Evaluate the need for a youth/teen center Report to Council on a "kick-off' concert to the summer concert series Undertake feasibility study for BMX park May 2000 Oct. 2000 Nov. 2000 Oct. 2000 Jan. 2001 Aug. 2000 Sept. 2000 ) ESTIMATED STATUS COMPLETION ~COMPLETE Nov. 2000 UNDERWAY; program will be implemented upon completion of classroom construction estimated for November, 2000. Nov. 2000 UNDERWAY; consultant contract awarded 9-20-00. ! COMPLETE; additional police officers , included in the FY2000-2001 budget. I June 2001 UNDERWAY; Parks &Community Services Commission input on agreement obtained in May 2000 and subsequent meetings will be scheduled with District. Dec. 2000 i Map COMPLETE. To be included in City- wide newsletter.' 'June 2001 UNDERV%TAY; Ordered; expected delivery & installation by January 2001 COMPLETE; R.A.F.T. Daycamp program introduced in Summer 2000 with average weekly attendance of 14 participants. June 2001 UNDERWAY; newly seated Youth Advisory Committee will provide input on events. June 2001 UNDERWAY; funding included in FY 2000- 2001 Budget; planning for program will begin in January 2001 and implemented in June 2001. Mar. 2001 UNDERWAY; data collection initiated. Dec. 2000 UNDERWAY; Staff is conducting survey of other senior centers. Study is scheduled for completion Dec 2000 NO PROGRESS; not funded in FY 2000- 2001 budget. ' COMPLETE _ i NO PROGRESS_._ ....... # COUNCIL PERSON YEAR PRIORITY RESPONSIBLE 20, Low Thompson 2000 21, Low Lowart 2000 22, Low Lowart 2000 PROPOSED OBJECTIVE FOR ACCOMPLISHING GOAL Implement a Community Wildflower Planting along Dougherty Road Identify potential income generating activities using City facilities Undertake feasibility study for dog park ADDITIONAL. OBJECTIVES (PARKS & COMMUNITY SERVICES) ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10131/00 PAGE 7 ESTIMATED START 1, High 2, High 3, High 4, High 5. High 6. High 7. High 8, High 9, Medium 10, Medium HERITAGE & CULTURAL ARTS }Lowart 1999 Lowart 1999 Lowart 2000 Lowart 1999 Lowart 1999 Lowart Lowart/ Thompson 1999 2000 Lowart/ 2000 Thompson Lowart 2000 Lowart 2000 Pursue construction of a storage unit on the Dublin Heritage Center grounds Undertake an assessment of community interest in arts and heritage programming Develop a long-range plan for heritage and cultural arts Work with Dublin Fine Arts Foundation to complete Art in the Park projects for Mape Memorial and Kolb Parks Evaluate what hours the Heritage Center should be open to maximize public visits and increase open hours Revise/amend Public Art Policy to identify alternate funding sources and approval process for Public Art Fund Freeway Underpass Art at Dublin BIrd & Amador Valley Blvd Develop a maintenance program for Public Art owned or on-loan to the City Establish a policy for acquisition/acceptance of museum artifacts Develop plans for documentation, certification and cataloging of City's collections (historical and art) Nov. 1999 Aug. 2000 Sept. 1998 July 2000 Dec. 1999 May 2000 Mar, 2000 ESTIMATED STATUS COMPLETION NO PROGRESS; Not funded NO PROGRESS. COMPLETE Mar. 2001 UNDERWAY; plans &specifications are being developed. COMPLETE Dec. 2000 UNDERWAY; draft plan under development by the Heritage & Cultural Arts Commission. Oct. 2000 COMPLETE Mar. 2001 UNDERWAY; hours have been changed to reflect assessment results. Staff is monitoring attendance to determine if additional hours are required. Feb. 2001 UNDERWAY; research involving Bay Area cities and counties completed. May 2002 UNDERWAY; Initial meeting with Caltrans completed. Art consultant contract approved. Selection Committee appointed. Nov. 2000 COMPLETE. NO PROGRESS NO PROGRESS ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10131100 PAGE 8 # COUNCIL PERSON ~ YEAR ~ PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED PRIORITY RESPONSIBLE GOAL START ADDITIONAL OBJECTIVES (HERITAGE & CULTURAL ARTS) 11. Lowart 2000 Develop a plan and a schedule to proceed with the Sept. 2000 replacement of three bus shelters in downtown Dublin. IV. PUBLIC SAFETY A. POLICE 1. High Thuman 2000 Increase Neighborhood Watch participation at the July 2000 Arroyo Vista development by at least 20 participating units 2. High Thuman 2000 Reduce vehicular accidents by 10% at major July 2000 intersections in the City 3. High Thuman 2000 Pursue funding for School Resource Officer 4. High Thuman 2000 Develop and implement a Citizen Volunteer Mar. 2001 Academy 5. High Thuman 1997 6. Medium Ambrose/ 1999 Cunningham 7. Medium Thuman 1999 8. Low I Thuman 1999 ADDITIONAL OBJECTIVES (POLICE) I B. ANIMAL CONTROL ADDITIONAL OBJECTIVES (ANIMAL CONTROL) Develop a Police Officer Trading Card Program (ADOPT-A-COP) Report to Council on Police Dispatch Service alternatives Revisions to Parking Citation Program to comply with current law Complete Evaluation of Smart Kids/SafeKids Program July 2000 ESTIMATED COMPLETION STATUS Nov. 2001 UNDERWAY; plan and schedule being developed in consultation with LAVTA. June 2001 June 2001 May 2001 Nov. 2000 UNDERWAY; As of October 30, 2000, Neighborhood Watch participation has increased by 15 units, from 4 to 19. UNDERWAY; increased traffic enforcement efforts in progress. COMPLETE; notification received on 9/15100 that federal COPS grant for SRO had been awarded to the City of Dublin; SRO began to work Oct. 16,2000. UNDERWAY; Curriculum for program has been developed and course is scheduled to begin in March, 2001, upon completion of the Youth Academy. COMPLETE; trading cards have been received and distributed to sponsors in the community. COMPLETE UNDERWAY; document revisions and form development in progress. COMPLETE # I COUNCIL PERSON I YEAR PRIORITY RESPONSIBLE C. FIRE SERVICES 1. High Ambrose/ 1998 McCammon 2. High Ambrose/ 1999 McCammon 3. High Herma/ 1999 McCammon ADDITIONAL OBJECTIVES (FIRE SERVICES) 4. Foss i2000 I D, DISASTER PREPAREDNESS 1. High Carter 2000 2. High Carter 2000 3, High Carter 2000 4. Low Carter 1997 ADOPTED 2000-2001 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10131100 PAGE 9 IPROPOSED OBJECTIVE FOR ACCOMPLISHING GOAL Finalize future locations for fire stations in eastern Dublin Establish financing time line for new fire station construction Complete joint fire station prototype design process with Alameda County and the City of San Leandro FY 1999-2000 TBD Aug. 1999 STATUS UNDERWAY; Emerald Glen Fire Station site ~nalized; Fallon Road Station will be finalized once Dublin Ranch receives Army Corp of Engineers report COMPLETE COMPLETE Acquire Fire Station site from Alameda County July 2000 Feb. 2001 UNDERWAY Undertake multi-functional disaster training Develop a Call List of Emergency Professionals (i.e. Doctors, Nurses, Fire, Police, etc)living in Dublin Conduct City Council Standardized Emergency Management System (SEMS) and EOC Training Develop a formal Disaster Service Worker Program Feb. 2001 Jan. 2001 Jan. 2001 April 2001 Mar. 2001 Jan. 2001 NO PROGRESS; Countywide disaster exercise is scheduled for April NO PROGRESS NO PROGRESS NO PROGRESS ADDITIONAL OBJECTIVES (DISASTER PREPAREDNESS) E. WASTE MANAGEMENT 1. High Carter 1999 Monitor and evaluate effectiveness of the expanded Commercial Recycling Program 2. High Carter 2000 3. High Carter 2000 Implement the Construction & Demolition Ordinance Monitor City Diversion rate and conduct a new Diversion Study 4. High Carter 2000 Discuss a Project with Camp Parks & Waste Management Authority to Implement Recycling of Demolition Materials at Camp Parks Ongoing Sept. 2000 Mar. 2000 Mar. 2001 TBD by Camp Parks UNDERWAY; Program was extended through June 2001. Next report to Council January 2001 COMPLETE UNDERWAY; Waste audits are nearly complete. New base year numbers will be ready for 2000 annual report due August 2001. UNDERWAY; Preliminary discussions with ACWMA and Camp Parks have begun; waiting for response from Camp Parks on feasibility. # COUNCIL PERSON YEAR PRIORITY RESPONSIBLE 5, Medium Carter/Marsh 2000 ADOPTED 2000-200'1 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/3'1/00 PAGE 10 PROPOSED OBJECTIVE FOR ACCOMPLISHING GOAL Develop administrative guidelines for implementing the new recycled content procurement policy JESTIMATED START Sept. 2000 6. Medium Carter i 2000 Evaluate effectiveness of purchasing 64-gallon recycling carts ADDITIONAL OBJECTIVES (WASTE MANAGEMENT) V. TRANSPORTATION A. MAINTENANCE 1. High Thompson 2000 ; Implement 5 new community volunteer projects Sept. 2000 July 2000 2. High Ambrose/ 2000 Thompson 3. Medium Thompson/ 1992 Peabody ADDITIONAL OBJECTIVES (MAINTENANCE) I ) I B. TRANSPORTATION 1. High Thompson 1997 2. High Ambrose/ 1997 Thompson/ Silver 3, High Thompson 1995 4. High Thompson 1999 5. High Thompson/ 1988 Peabody 6. Medium Thompson 2000 Work with Dublin Housing Authority to investigate options to improve the overall appearance of Arroyo Vista Identify potential locations for new City maintenance yard facility Work with Caltrans & ACTA to open downtown hook ramps' Complete negotiations with Contra Costa County to pay for needed roadway improvements in Dublin Complete alignment studies for eastern Dublin major arterials (Fallon Road) Participate in development of Measure 'B' Reauthorization Program Report to City Council on Downtown Traffic Impact Fee Develop a policy with respect to allowing street- naming through non-profit organizations ADDITIONAL OBJECTIVES (TRANSPORTATION) I I Jan 2001 FY 1997-1998 FY 1999-2000 Nov. 2000 ESTIMATED COMPLETION Oct. 2000 June 2001 STATUS UNDERWAY; Guidelines have been drafted; procedures now in place to order recycled products UNDERWAY; First month indicates 37% increase in collected recyclables I May 2001 June 2001 UNDERWAY; Intedor of Alamo Park restrooms painted by Eagle Scout in August 2000 (2 projects pending) NO PROGRESS NO PROGRESS I FY 2001-2002 Fallon-Mar 2001 Gleason-Dec 2001 UNDERWAY; (2 of the 3 ramps opened) COMPLETE UNDERWAY; Have Draft of Fallon Road COMPLETE Mar. 2001 UNDERWAY; Land use study for Impact fee started 10/2000. UNDERWAY; Proposed to go to Council on November 21 st I F:\G&O\BI-MONLY~2000\as of 8-31-00 bi-monthly.doc m z -I ID 1 10 11 12 13 14 15 Start Men 7/3/00 Men 7/3/00 Men 7/17/00 Tue 7/18/00 Tue 7/25/00 Tue 8/1/00 Tue 8/8/00 Wed 8/30/00 Fri 9/1/00 Men 9/25/00 Men 10/2/00 Men 10/16/00 Men 12/11/00 Tue 5/1/01 Men 7/3/00 Finish Fri 6/29/01 Fri 6/29/01 Fri 12/29/00 Men 2/12/01 Fri 2/16/01 Fri 12/29/00 Men 4/9/01 Wed 1/31/01 Wed 1/3/01 Tue 7/31/01 Fri 12/22/00 Wed 2/28/01 Fri 2/2/01 Fri 6/29/01 Men 7/3/00 No~s Complete Februa~ 2003 te April 2003 COMPLETE Predecessors CITY OF DUBLIN FY 2000-2001 CIP SCHEDULE General 200 l Jun "3'Ui']TTd¥'' SOD': Oc: Nov ' D~c Jan :1 eb Mar Ap' May _. Complete February 2003 Complete April 2003 ............. e COMPLETE ID 1 5 6 7 8 9 10 11 12 13 14 Number 94192 94960 94226 94701 Project Name Dougherty Road Tree Planting Street Name Identification Sign Replacement Freeway Underpass Art (Design) Downtown Improvements Plan 94230 Arroyo Vista Roof Repair 94250 Sidewalk Safety Repair (Grinding) 94641 Irrigation Controller Upgrade (MCE) 94250 Sidewalk Safety Repair 94051 Iron Horse Trail Amenities 94251 Widen Village Pkwy Sidewalks 94615 Village Pkwy Median Landscaping 94255 Sidewalk Reconstruction under 1-680 94956 Eastern Dublin Banner Additions 94290 Audible Pedestrian Signals CITY OF DUBLIN FY 2000-2001 CIP SCHEDULE Community Improvements Duration Jun Jul Aug ~ Sep Oct N3v Dec daq 137 days 131 days 110 days 151 days 46 days 40 days ............................... 118 days 43 days Feb Ma, Ap' MayI Jun ! Jul 0 days ......................~ Awaiting City Council Action on Village Parkway Specific Plan 0 days 0 days .............. Awaiting City Couqcil Action on Village Parkway Specific Plan 4el> Awaiting artist selection for Freeway Underpass Art. 0 days 0 days ................... + Awaiting response from DUSD regarding student participation in banner p'~:~'~'~ ............................ ~ ................... ............... ........................................................................................:""'i ID 1 10 Number 95911 95635 95501 95830 95600 95405 95461 Project Name Swim Center Painting & Fence Replacement Park Play Area Fvaluabon Heritage Center Storage Building Dublin Sports Ground Renovation Emerald Glen Park (Phase II Design & Construction Documents) Shannon Center Parking Lot Paving Shannon Center HVAC 95930 Senior Center (Conceptual Design) 95451 Shannon Center Doors 95110 Community Gym at Valley high CITY OF DUBLIN FY 2000-2001 CIP SCHEDULE Parks Duration Jun 105 days ; 35 days 147 days 298 days 185 days 172 days 138 days 173 days 61 days 0 days J I ~A~ Apr. May Jun ,)t.I Aug: Sep ) Oct ) Nov ) Dec. ~0a0n2 ......................................................................................:.-,=m=-~.--.-,: ~ ..x-.-, ,.....,-.,..-~. ............................................. i ....................i .............~ .............................i ....................~ ..................~- ...................i ................... year project funding to be completed in FY 2001-2002 ID 1 9 10 11 12 13 14 15 16 17 Number Project Name 96400 Eastern Dublin Arterial Street Improvements 96380 1-580/San Ramon Intemhange Improvements (PSR/PR/ED) 96430 1-580/Fallon Interchange Improvements (Design, Plans & Specs) 96890 Dublin BIvd. Widening- Dougherty to Scarlett 96920 Dublin Blvd. Improvements- Village to Sierra (Construction to begin FY 2001-2002) 96770 Alamo Canal Bike Path - AVB to Iron Home 96561 Traffic Signal-Hacienda Drive @ Summerglen 96420 1-580/Tassajara Interchange Improvements (Design, Plans & Specs) 96560 Traffic Signals - Village Parkway 96410 1-580/Hacienda Interchange Improvements 96580 Annual Street Overlay 96015 AVB/Starward Safety Improvements 96021 Bedford Court Subdrain 96023 Hansen Dr. Drainage Improvements 96080 Dublin Blvd. Underground Utilities (Construction to begin FY 2001-2002) 96772 Alamo Canal Bike Path- Iron Home to 1-580 96852 Dougherty Rd Improvements- Houston to 1580 (Environmental Documents) CITY OF DUBLIN FY 2000-2001 CIP SCHEDULE Streets 2001 . Duration Jun Jul ' Aug , Sep; Oct ' I~v ':"IS'~E" 248 days L'~,;' .... -' .................... "-- ........... :,. .-. J Complete Sept. 2002 123 days 133 days ................ 136 days ................... 229 days ................ 191 days 187 days ..................... 187 days ..................... 195 days I __'" '. :'. ] Complete Sept. 2002 262 days 185 days