HomeMy WebLinkAbout4.04 COI-580Tassajara01-12CITY CLERK
File No. ❑���-0�
AGENDA STATEMENT
CITY COUNCIL MEETING DATE: August 5, 2003
SUBJECT: Change Order Authorization — Contract No. 01-12
Interstate 580/Tassajara Road Interchange Improvement Project
Report Prepared by: Lee S. Thompson, Public Works Director
ATTACHMENTS:
RECOMMENDATION:
FINANCIAL STATEMENT:
Change Order No. 23
Approve Change Order No. 23
Original Project Contract Amount:
Project Bid Contingency Amount:
Total Construction Budget:
Original Project Contingency Amount:
$7,124,198
895,770
$8,019,968
$ 895,770
Total Approved Change Orders to Date: ($ 371,978)
Amount of Change Order No. 23: ( 72,000)
Total All Change Orders: ($ 443,978)
Remaining Project Contingency Amount: 451 792
DESCRIPTION: Construction of the I-580/Tassajara Road Interchange Improvement
project is approximately 90% complete. During a field review with Caltrans representatives, Caltrans
identified the need to revise the finish grade of the embankment of the newly -constructed northbound
freeway overcrossing and requested that the bridge embankment be paved with concrete comparable to the
slope paving on the adjacent existing freeway overcrossing. This slope paving is required to reduce bridge
maintenance and soil erosion underneath the bridge and is a standard Caltrans requirement.
Caltrans has approved the design features of Change Order No. 23, which includes excavation of the
existing abutment embankment, construction of concrete slope paving, caulking of joints, and providing
traffic control to support this work. The not -to -exceed amount of $72,000 for Change Order No. 23 shall
be paid to the contractor from the project contingency fund.
Since the amount of this Change Order exceeds the $25,000 authorization limit granted to the City
Manager, it is necessary for the City Council to approve this Change Order. Staff therefore recommends
that the City Council approve Change Order No. 23 in the total amount of $72,000.
---------------------------------------------------------------
COPIES TO: Tom Brown, DeSilva Gates
10ITEM NO.
g:\miscproj\i-580 Tassajara\project\agst CCO23 Authorization
O�Q
CITY OF DUBLIN I
CONTRACT CHANGE ORDER NO. 23
PROJECT/ROAD: Interstate 580/Tassajara Road Interchange Improvements PAGE 1 OF 7 PAGES
CONTRACT NO. City Project No. 01-12, Federal Aid Project No. RSTPL-5432 (011)
TO: DeSilva Gates Construction LP
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work
not included in the plans and specifications on this contract.
NOTE: This change order is not effective until approved by the Public Works Director.
Description of work to be done, estimate of quantities, and prices to be paid. Segregate between additional work at contract price,
agreed price and force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually
used and no allowance will be made for idle time.
Change requested by: Engineer
The last percentage shown is the net accumulated increase or decrease from the original quantity in the Engineer's Estimate.
Furnish all labor, equipment and materials necessary to revise finish grade of abutment embankment and extend the existing slope
paving underneath Tassajara Rd - Santa Rita Rd OC (Br. 33-0585) as shown on pages 2-7 of this change order.
EXTRA WORK AT AGREED LUMP SUM PRICE:
For the work of excavating the existing.abutment embankanent to the grades shown on pages 2-7 of this change order, including
providing all necessary traffic control, the Contractor will be paid an agreed lump sum amount of $17,000.00. This amount.
constitutes full compensation, including markups, for the work of this change.
AGREED LUMP SUM COST iNCREASE ............ $17,000.00
EXTRA WORK AT FORCE ACCOUNT:
Construct portland cement concrete slope paving, caulk specified joints, construct, maintain and remove concrete washout, and
provide traffic control to support this work, in accordance with the details of this change order and as directed by the Engineer.
Slope paving shall be constructed as per the details shown on pages 2-7 of this change order and in accordance with Section 72-6
"Slope Paving" of the Standard Specifications.
Place caulk between polystyrene and adjacent concrete surfaces at top of slope. Caulk shall be silicone or an alternative approved by
the Engineer. Cured caulk shall be grey, white or clear in appearance. Caulk shall not be applied until at least 7 days after
placement of paving concrete.
ESTIMATE OF COST iNCREASE AT FORCE ACCOUNT .............. $55,000.00
TOTAL ESTIMATED COST INCREASE .............. $72,000.00
BY REASON OF THIS ORDER, THE TIME OF COMPLETION WILL BE ADJUSTED ~ WOP, KING ~/YS
SUBMITTED BY.: ~-------~-- Appj~OVALj~E~L:~.MM~DED BY: AP, .p~ ~(~K,V, ED BY//
/./J~mes E. Sco: D:e F~4i¢~d Del Rosar[o Date / / gee S. T~p~: ' Date
Resident Engineer Sr. Civil Eng~eer P~lic W~kector
We, ~e ~dersigned contractor, have given care~l consideration to Ce ch~ge proposed ~d hereby agree, if this proposal is
approved, that we will provide all equipment, ~rnish all materials, except as may otherwise be noted above, and perfo~ all services
necessary for the work above specified, ~d will accept as ~11 payment therefor the prices sho~ above.
Accepted: D:e ~ /~ ~2003 Contractor: ~t~ ~r
If the Contractor does not sign acceptance of this order, his a:ention is directed to the requirements of the speci:cations as to
proceeding with the ordered work and filing a wri:en protest within the time therein specified.
CHANGE ORDER SUMMARY
DATE: July 22, 2003
PROJECT NAME: 1-580/Tassajara Road Interchange Improvement Project
CIP #: 96420
CONTRACT NO: 00-12
CONTRACTOR: De Silva Gates Construction
~ERCENT COMPLETED: 90%
CONTRACT AMOUNT: $7,054,198.00 + $70,000 Incentive = $7,124,198.00
APPROVED BUDGET AMT: $8,019,968
CHANGE ORDERS:
CHANGE ORDER #1 $5,000.00
CHANGE ORDER #2 $7,974.00
CHANGE ORDER #3 $6,640.00
CHANGE ORDER #4 $6,212.00
CHANGE ORDER #5
CHANGE ORDER #6 $4,645.00
CHANGE ORDER #7 $4,189.45
CHANGE ORDER #8 $18,650.03
CHANGE ORDER #9 ($1,204.00)
CHANGE ORDER #10
CHANGE ORDER #11 $2,095.00
CHANGE ORDER #12 $1,318.26
CHANGE ORDER #13 $245,000.00
CHANGE ORDER #14 ($16,650.50)
CHANGE ORDER #15 $5,000.00
CHANGE ORDER #16 $3,500.00
CHANGE ORDER #17 $2,196.84
CHANGE ORDER #18
CHANGE ORDER #19
CHANGE ORDER #20 $5,540.26
CHANGE ORDER #21 $1,298.07
CHANGE ORDER #22
CHANGE ORDER #23 $72,000.00
CHANGE ORDER #24 $15,540.00
CHANGE ORDER #25 $8,297.21
CHANGE ORDER #26
CHANGE ORDER #27
CHANGE ORDER #28 $24,612.08
CHANGE ORDER #29
CHANGE ORDER #30
CHANGE ORDER #31 $15,500.00
CHANGE ORDER #32 $6,624.00
TOTAL OF CHANGE
[ORDERS: $443,977.70
CURRENT CHANGE ORDER DESCRIPTION:
I See attached memo.
ADJUSTED CONTRACT AMOUNT: $7,568,17,5.70
PROGRESS PAYMENTS MADE:
PAYMENT #1 $122,392.50
PAYMENT #2 $346,304.00
PAYMENT #3 $690,383.20
PAYMENT #4 $650,903.00
PAYMENT #5 $322,915.00
PAYMENT #6 $1,372,198.00
PAYMENT #7 $928,869.00
PAYMENT #8 $555,172.20
~AYMENT #9 $119,545.73
PAYMENT #10 $454,340.40
PAYMENT #11 $125,979.11
PAYMENT #12 $305,032.05
PAYMENT #13 $247,810.80
PAYMENT #14 $450,337.27
ITOTAL PROGRESS
PAYMENTS: $6,692,182.26
IREMAINING BALANCE ON
CONTRACT: $875,993.44
RECOMMENDATION: APPROVED /"~ APPROVED APPROVED
DENIED/,/ DENIED DENIED
SIGNATURES:
... P_j.gdli~ork~ irect~r City Manager Mayor
G:\Miscproj\l-580-Tassajara\Construction\CCO Summary23