HomeMy WebLinkAbout8.2 Attch 6-Reso rec CC Adopt Reso Sub 3 Addendum RESOLUTION NO. 14-XX
A RESOLUTION OF THE PLANNING COMMISSION
OF THE CITY OF DUBLIN
RECOMMENDING THAT THE CITY COUNCIL ADOPT A RESOLUTION ADOPTING A CEQA
ADDENDUM FOR THE DUBLIN RANCH SUBAREA 3 PROJECT
PLPA 2013-00033
WHEREAS, the Applicant, Kevin Fryer, has submitted a Planning Application for
residential development on Dublin Ranch Subarea 3 (Subarea 3) which would result in future
development of up to 437 single family residences on an approximately 64 acre site. The
project proposes General Plan and Eastern Dublin Specific Plan amendments to reallocate
existing High Density Residential and Medium Density Residential land uses, to reduce and
change Open Space land uses to Rural Residential/Agriculture and to increase the Stream
Corridor designation. The application also proposes a Planned Development rezoning with
related Stage 1 Development Plan. The applications are collectively referred to herein as the
"Project"; and
WHEREAS, the Project is in the General Plan Eastern Extended Planning Area and the
Eastern Dublin Specific Plan area, for which the City Council certified a Program Environmental
Impact Report by Resolution 51-93 ("Eastern Dublin EIR" or "EDEIR", SCH 91103064) on May
10, 1993 (resolution incorporated herein by reference). The Eastern Dublin EIR identified
significant impacts from development of the Eastern Dublin area, some of which could not be
mitigated to less than significant. Upon approval of the Eastern Dublin General Plan
Amendment and Specific Plan, the City Council adopted mitigations, a mitigation monitoring
program and a Statement of Overriding Considerations (Resolution 53-93, incorporated herein
by reference); and
WHEREAS, the Project is located in Dublin Ranch Area B. On November 18, 1997, the
City Council adopted a Negative Declaration (ND) for the Area B-E project (Resolution 140-97,
incorporated herein by reference). The ND concluded that the potentially significant impacts of
developing Areas B-E had been adequately described and analyzed in the Eastern Dublin EIR
and that no new or more severe significant impacts would result from future development in
Areas B-E; and
WHEREAS, the Eastern Dublin EIR identified significant unavoidable impacts from
development of the Eastern Dublin area, some of which would apply to the Project; therefore,
approval of the Project must be supported by a Statement of Overriding Considerations; and
WHEREAS, for the Subarea 3 Project, the City prepared an Initial Study to determine if
additional review of the proposed Project was required pursuant to CEQA Guidelines section
15162. Based on the Initial Study, the City prepared an Addendum dated January 2014
describing the Subarea 3 Project and finding that the impacts of the proposed Project were
adequately addressed in the prior EIR and ND; and
WHEREAS, on January 28, 2014, the Planning Commission held a properly noticed
public hearing on the Subarea 3 project, at which time all interested parties had the opportunity
to be heard; and
Page 1 of 3
Attachment 6
WHEREAS, a staff report dated January 28, 2014 and incorporated herein by reference
described and analyzed the Subarea 3 project, including the related Addendum, for the
Planning Commission and recommended adoption of the CEQA Addendum and approval of the
Project; and
WHEREAS, the Planning Commission considered the CEQA Addendum as well as the
prior CEQA documents, and all above-referenced reports, recommendations, and testimony
before making any recommendation on the Project.
NOW, THEREFORE BE IT RESOLVED that the foregoing recitals are true and correct
and made a part of this resolution.
BE IT FURTHER RESOLVED that the Planning Commission makes the following
findings to support the determination that no further environmental review is required under
CEQA for the proposed Project. These findings are based on information contained in the
CEQA Addendum, prior CEQA documents, the Planning Commission staff report, and all other
information contained in the record before the Planning Commission. These findings constitute
a summary of the information contained in the entire record. The detailed facts to support the
findings are set forth in the CEQA Addendum and related Initial Study, the prior CEQA
documents, and elsewhere in the record. Other facts and information in the record that support
each finding that are not included below are incorporated herein by reference:
1. The proposed Project does not constitute substantial changes to the previous projects
affecting the Project site, as addressed in the prior CEQA documents, that will require major
revisions to prior documents due to new significant environmental effects or a substantial
increase in severity of previously identified significant effects. Based on the Initial Study, all
potentially significant effects of the proposed Project are the same or less than the impacts for
the Eastern Dublin and Areas B-E projects which were previously addressed. The proposed
Project will not result in substantially more severe significant impacts than those identified in the
prior CEQA documents. All previously adopted mitigation measures continue to apply to the
proposed Project and project site as applicable.
2. The Initial Study and Addendum did not identify any new significant impacts of the
proposed Project that were not analyzed in prior CEQA documents.
3. The City is not aware of any new information of substantial importance or substantial
changes in circumstances that would result in new or substantially more severe impacts or meet
any other standards in CEQA Section 21166 and related CEQA Guidelines Sections 15162/3.
BE IT FURTHER RESOLVED that the Planning Commission recommends the following
to the City Council:
1. No further environmental review under CEQA is required for the proposed Project
because there is no substantial evidence in the record as a whole that any of the standards
under Sections 21166 or 15162/3 are met.
2. The City has properly prepared a CEQA Addendum and related Initial Study under
CEQA Guidelines section 15164 to explain its decision not to prepare a subsequent or
supplemental EIR or conduct further environmental review for the proposed Project.
2 of 3
3. The City Council adopt the resolution attached as Exhibit A (incorporated herein by
reference) adopting the CEQA Addendum and related Initial Study (Attachment 1 to Exhibit A)
pursuant to CEQA Guidelines Sections 15162 and 15164 for the Project and make any further
required CEQA findings.
PASSED, APPROVED AND ADOPTED this 28th day of January 2014 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
Planning Commission Chair
ATTEST:
Assistant Community Development Director
G:IPA#120131PLPA-2013-00033 DUBLIN RANCH Subarea 31PC Mtg 01.28.14wc reso_recom_addendum.doc
3 of 3
CEQA ADDENDUM FOR THE DUBLIN RANCH SUBAREA 3 PROJECT
PLPA-2013-00033
JANUARY 28, 2014
On May 10, 1993, the Dublin City Council adopted Resolution No. 51-93, certifying an
Environmental Impact Report for the Eastern Dublin General Plan Amendment and Specific
Plan ("Eastern Dublin EIR, SCH#91103064). The certified EIR consisted of a Draft EIR and
Responses to Comments bound volumes, as well as an Addendum to the Eastern Dublin EIR
dated May 4, 1993, assessing a reduced development project alternative. The City Council
adopted Resolution No. 53-93 approving a General Plan Amendment and Specific Plan for the
reduced area alternative on May 10, 1993. On August 22, 1994, the City Council adopted a
second Addendum updating wastewater disposal plans for Eastern Dublin. The Eastern
Dublin EIR evaluated the potential environmental effects of urbanizing Eastern Dublin over a
20 to 30 year period. Since certification of the EIR, many implementing projects have been
proposed, relying to various degrees on the certified EIR.
In 1997, a Negative Declaration was prepared for a General Plan Amendment, Specific Plan
Amendment and Planned Development rezoning for approximately 453 acres of land,
identified as Dublin Ranch Areas B-E and including Subarea 3 of Area B. The ND was
approved by the City Council on November 18, 1997 by Resolution No. 140-97. The 1997
General Plan and Specific Plan amendments did not affect Subarea 3; the PD rezoning
supplemented the prior prezoning and adopted a District Planned Development Plan and Land
Use and Development Plan, in accordance with then-existing PD requirements (Resolution
141-97). The PD rezoning also included permitted uses, development standards and design
guidelines applicable to Areas B-E, including Subarea 3.
This Addendum has been prepared pursuant to CEQA Guidelines Section 15164 for the
project, as described below.
Project Location and Description
The project is located in the southeastern portion of the Eastern Extended Planning area of the
City of Dublin as identified in the Dublin General Plan. More specifically, the project site is
located south of Central Parkway, west of Fallon Road and north of Dublin Boulevard.
Lockhart Street forms the western boundary of the site. The Alameda County Assessor's
Parcel Number for the site is 985-0027-12.
The current application includes construction of up to 437 Medium and Medium-High
Density dwellings on the site, reserving 14.5 acres of the site for Rural
Residential/Agriculture, a 2.0-acre stream corridor and a 2.0-acre Neighborhood Park on
the site. The project would include grading of the site, extension of utilities and related
improvements.
Requested land use approvals include amendments to the Dublin General Plan and Eastern
Dublin Specific Plan, a Planned Development rezoning and related improvements.
Prior CEQA Analyses and Determinations
As summarized above and discussed in more detail in the attached Initial Study, Subarea 3 of
the Dublin Ranch property has been planned for urbanization since the Eastern Dublin
approvals in 1993 and has been the subject of one subsequent Negative Declaration adopted in
1997. The Eastern Dublin EIR identified numerous environmental impacts, and numerous
mitigations were adopted upon approval of the Eastern Dublin General Plan Amendment and
Specific Plan. For identified impacts that could not be mitigated to insignificance, the City
Council adopted a Statement of Overriding Considerations. No additional mitigation measures
were included in the 1997 Negative Declaration. All previously adopted mitigation measures
for development of Eastern Dublin identified in the Eastern Dublin EIR,that are applicable to
the project and project site continue to apply to the currently proposed project as further
discussed in the attached Initial Study.
Current CEQA Analysis and Determination that an Addendum is Appropriate for this
Project.
Updated Initial Study. The City of Dublin has determined that an Addendum is the appropriate
CEQA review for the Project, which proposed a minor amendment to the approved General Plan,
Eastern Dublin Specific Plan and Planned Development zoning. If approved, the proposed
project would change land uses on the project site as identified above.
The City prepared an updated Initial Study dated January 28, 2014, incorporated herein by
reference,to assess whether any further environmental review is required for this Project
Through this Initial Study, the City has determined that no subsequent EIR or Negative
Declaration is required for the plan and zoning amendments or the refined development
details.
No Subsequent Review is Required per CEQA Guidelines Section 15162. CEQA Guidelines
Section 15162 identifies the conditions requiring subsequent environmental review. After a
review of these conditions,the City has determined that no subsequent EIR or negative
declaration is required for this project. This is based on the following analysis:
a) Are there substantial changes to the Project involving new or more severe significant
impacts? There are no substantial changes to the Project analyzed in the Eastern
Dublin EIR, as supplemented by the 1997 Negative Declaration. The project is
similar to land uses for the project site analyzed in the 1997 Negative Declaration. As
demonstrated in the Initial Study,the proposed land uses for the site is similar to
previously approved land used on the site and will not result in additional significant
impacts, and no additional or different mitigation measures are required.
b) Are there substantial changes in the conditions which the Project is undertaken involving
new or more severe significant impacts? There are no substantial changes in the conditions
Page 2
assumed in the Eastern Dublin EIR or the 1997 Negative Declaration. This is documented
in the attached Initial Study prepared for this Project dated January 28, 2014.
c) Is there new information of substantial importance, which was not known and could not
have been known at the time of the previous EIR that shows the Project will have a
significant effect not addressed in the previous EIR; or previous effects are more severe;
or,previously infeasible mitigation measures are now feasible but the applicant declined
to adopt them; or mitigation measures considerably different from those in the previous
EIR would substantially reduce significant effects but the applicant declines to adopt
them? As documented in the attached Initial Study, there is no new information showing a
new or more severe significant effect beyond those identified in the prior EIRs. Similarly,
the Initial Study documents that no new or different mitigation measures are required for
the Project. All previously adopted mitigations continue to apply to the Project. The
previously certified EIRs adequately describe the impacts and mitigations associated with
the proposed development on portions of the Subarea 3 property.
d) If no subsequent EIR-level review is required, should a subsequent negative declaration
be prepared?No subsequent negative declaration or mitigated negative declaration is
required because there are no impacts, significant or otherwise, of the project beyond
those identified in the Eastern Dublin EIR and previous CEQA documents for the site, as
documented in the attached Initial Study.
Conclusion. This Addendum is adopted pursuant to CEQA Guidelines Section 15164 based
on the attached Initial Study dated January 28, 2014. The Addendum and Initial Study review
the proposed General Plan and Eastern Dublin Specific Plan Amendments and the Planned
Development rezoning amendment. Through the adoption of this Addendum and related
Initial Study, the City determines that the above minor changes in land uses do not require a
subsequent EIR or negative declaration under CEQA Section 21166 or CEQA Guidelines
Sections 15162 and 15163. The City further determines that the Eastern Dublin EIR and the
1997 Negative Declaration adequately address the potential environmental impacts of the land
use designation change for the project site as documented in the attached Initial Study.
As provided in Section 15164 of the Guidelines, the Addendum need not be circulated for
public review, but shall be considered with the prior environmental documents before making
a decision on this project.
The Initial Study, Eastern Dublin EIR, the 1997 Negative Declaration and all resolutions cited
above are incorporated herein by reference and are available for public review during normal
business hours in the Community Development Department, Dublin City Hall, 100 Civic
Plaza, Dublin CA.
Page 3