HomeMy WebLinkAboutReso 130-95 MOU BartRESOLUTION NO. 130 - 95
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
~:~~
APPROVING A MEMORANDUM OF UNDERSTANDING
BETWEEN THE CITY OF DUBLIN AND
SAN FRANCISCO BAY AREA RAPID TRANSIT DISTRICT
REGARDING MITIGATION MEASURES
WHEREAS, the BART Board of Directors certified an Environmental Impact Report for the
Dublin/Pleasanton Extension Project on February 8, 1990; and
WHEREAS, the BART Board of Directors also adopted a Mitigation Monitoring and Reporting
Plan on February 8, 1990, which provides that BART will contribute 24% of the actual project costs
associated with the Parallel Road southerly of Dublin Boulevard and the Dublin Boulevard Improvements
not to exceed $1 million; and
WHEREAS, these funds are to be contributed only upon implementation of the improvements
prior to January 1, 1996.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin approves the
attached Memorandum of Understanding and agrees to the obligations set forth in the Memorandum of
Understanding.
PASSED, APPROVED AND ADOPTED this 241h day of October, 1995.
AYES:
Councilmembers Barnes, Burton, Howard, Moffatt and Mayor Houston
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST~~
H/cc-mtgs/resobart. doc
K2/oct- 9 5/re sobart. doc
Mayor
MEMORANDUM OF UNDERSTANDING
BETWEEN
CITY OF DUBLIN
AND
SAN FRANCISCO
BAY AREA RAPID TRANSIT DISTRICT (BART)
FOR
CONTRIBUTION OF FUNDS
FOR
TWO CAPITAL IMPROVEMENT PROJECTS,
THE PARALLEL ROAD SOUTHERLY OF DUBLIN BOULEVARD
AND
THE DUBLIN BOULEVARD IMPROVEMENTS
A: \DUB5. MOU
EXHIBIT 1
MEMORANDUM OF UNDERSTANDING
BETWEEN
CITY OF DUBLIN
AND
SAN FRANCISCO
BAY AREA RAPID TRANSIT DISTRICT
REGARDING MITIGATION MEASURES
This MEMORANDUM OF UNDERSTANDING, entered into on
,1995, is between the CITY OF DUBLIN, referred to herein as "CITY" and the SAN
FRANCISCO BAY AREA RAPID TRANSIT DISTRICT, referred to herein as "BART".
RECITALS
WHEREAS, The BART Board of Directors certified an Environmental Impact Report CEIR'')
for the Dublin/Pleasanton Extension Project on February 8, 1990; and
2
WHEREAS, The BART Board of Directors also adopted a Mitigation Monitoring and Reporting
Plan on February 8, 1990, for purposes of monitoring compliance with the mitigation measures
adopted by the BART Board; and
WHEREAS, Section 23 of the Mitigation Monitoring and Reporting Plan provides that BART
will enter into a memorandum of understanding CMOU") with CITY for contribution by BART
of funds for two capital improvement projects of CITY, the Parallel Road southerly of Dublin
Boulevard and the Dublin Boulevard Improvements, of 24% of Actual Project Costs, but not to
exceed $1 million ($ 1,000,000.00); and
WHEREAS, the funds are to be contributed
implementation of the improvements; and
prior to January 1, 1996 and only upon
WHEREAS, the purpose of this MOU is to provide for the payment by BART to CITY of the
funds for the capital improvement projects as contemplated by the EIR and the Mitigation
Monitoring and Reporting Plan.
NOW, THEREFORE, in consideration of the promises and acts described herein, the parties
hereby agree as follows:
3
AGREEMENT
SECTION I
DEFINITIONS:
For purposes of this MOU, the following definitions shall apply:
A. "Actual Project Costs" shall mean the final construction costs including all payments to
contractors for bid items and change orders for the Parallel Road and the Dublin Boulevard
Improvements, plus property acquisition costs required for these projects, plus the cost of all
required utility relocations, plus construction engineering costs, preliminary engineering and
design costs not to exceed 25 % of the final construction costs.
B. "Implementation of the Improvements". The improvements shall be considered to be
implemented when City has committed funding for its share of the Actual Project Costs. In
addition, by January 1, 1996, City shall have begun right-of-way acquisition (including actual
acquisition or filing of a condemnation action, but not appraisals or other preliminary activities),
or construction of the improvements7
C. "Dublin Boulevard Improvements" shall mean those improvements to Dublin Boulevard
between DonIon Way and Village Parkway, consisting of the addition of one travel lane in each
direction; provision of double right turn lanes on the eastbound approach of Dublin Boulevard
to San Ramon Road, triple left turn lanes on the westbound approach lanes of Dublin Boulevard
4
to San Ramon Road, a right turn lane on Dublin Boulevard westbound at Village Parkway; and
attendant signalization improvements.
D. "Parallel Road" shall mean the roadway between Amador Plaza Road and Regional Street
south of and parallel to Dublin Boulevard, the right of way of which will vary in width from
64 to 68 feet in the location established by the plan line adopted by Dublin Ordinance No. 19-88
or as amended, to include, as a minimum, 2 paved travel lanes not less than 12 feet wide plus
curbs, gutters and sidewalks. ~
SECTION II
CITY AGREES:
1. To acquire right-of-way for Dublin Boulevard Improvements and Parallel Road projects.
2. To Provide the preliminary engineering
Improvements and Parallel Road projects.
and final design for Dublin Boulevard
3. To provide BART with four sets of the as-advertised plans, specifications and estimates
of each project and/or phase of each project.
4. To provide or to contract for labor, material, tools and equipment for Dublin Boulevard
Improvements and Parallel Road projects including advertising, award, contract administration,
Resident Engineer, material testing, and other resources including inspection, materials,
construction staking and surveys and staff for satisfactory completion of the Dublin Boulevard
Improvements and Parallel Road projects.
5. To Obtain all Local, State and Federal approvals and permits necessary for construction
of the Dublin Boulevard Improvements and Parallel Road projects.
6. To construct the Dublin Boulevard Improvements and Parallel Road projects by contract
in accordance with plans and specifications approved by BART which approval shall not be
unreasonably withheld. BART shall have 30 working days from receipt thereof to review and
approve plans and specifications. Failure to respond within said 30 day period shall be deemed
approval.
7. To establish separate Dublin Boulevard Improvements and Parallel Road projects
accounts to accumulate charges for all work to be paid by BART pursuant to this MOU.
8. To provide BART written notification that it has acquired property necessary for the
Parallel Road or the Dublin Boulevard Improvements as a condition precedent to BART's
obligation under Section III, Article 1.
6
9. Thereafter, as construction of each project proceeds, to transmit to BART monthly
summary listing of CITY's Actual Project Costs for reimbursement as provided in Section III,
Article 2. Such notification shall provide BART with information regarding the components of
Actual Project Costs and the cost to date for such expenditures. The CITY may request funds
in increments as CITY funds are committed and/or fight of way is obtained. "Funds are
committed" shall mean award of construction contracts, signatures obtained on agreement to
purchase fight of way or condemnation orders of possession granted and payment of other
project costs.
10. To pay for all costs associated with the establishment of electronic fund transfer for
BART and of each outgoing bank wire transfer fee assessed to BART and each incoming bank
wire transfer fee assessed to CITY, should the City wish to receive funds in this manner.
11. At it's option, CITY may elect to construct the Parallel Road in two phases (one from
Areadot Plaza to GOlden Gate and one from Golden Gate to Regional Street).
12. Upon completion of Dublin Boulevard Improvements and Parallel Road projects and all
work incidental thereto, to furnish BART with a detailed statement of the Actual Project Costs
to be borne by BART. CITY thereafter shall refund to BART (promptly after completion of
CITY's audit) any amount of BART's deposits and payments which exceed 24% of Actual
Project Costs not to exceed $1 million or to bill BART for any additional amount required to
complete BART's financial obligations pursuant to this MOU.
7
13. To prepare and submit to BART each month, a construction progress report which
describes the work performed and completed during the reporting period and provides pertinent
contract dam, including, but not limited to items such as: progress payments made (reported in
dollars); contract change orders written; total accumulated costs of contract change orders; the
percentage of elapsed time allotted for completion of construction and cumulative percentage of
Dublin Boulevard Improvements and Parallel projects costs incurred to date; percentage progress
achieved to date; estimated costs and status of protection, rel0cation, or removal of public and
or private utilities; any projected changes in the work schedule or contract claims. In addition,
initial and final reports on participation of Disadvantaged Business Enterprise (DBE) firms by
percentage dollar amount awarded shall be provided to BART in form acceptable to BART.
Insofar as permitted by law, CITY will provide any additional information in its possession
which is reasonably required by BART. All such data shall be in accordance with generally
accepted accounting principles.
14. To establish and maintain records pertaining to the fiscal activities of the Dublin
Boulevard Improvements and Parallel Road projects based upon generally accepted accounting
principles.
SECTION III
BART AGREES:
1. To submit, within thirty (30) days after receipt of written notice by CITY, as set forth
in Section II Article 8, by electronic fund transfer twenty-four percent (24%) of the Actual
Project Costs for the acquisition of the right-of-way necessary for the Dublin Boulevard
Improvements or the Parallel Road project subject to the provisions of Section IV,
Article 1.
2. Thereafter, as implementation of the Dublin Boulevard Improvements and Parallel Roads
projects proceeds and upon receipt by BART of CITY' s monthly summary listing of charges for
Dublin Boulevard Improvements and Parallel Road projects to be paid by BART, BART will
then within five (5) working days, transfer funds by electronic fund transfer in the amount of
twenty-four percent (24%) of the Actual Project Costs of each project to CITY to cover said
charges, subject to the limitation stated in Section IV, Article 1.
3. BART will endeavor to notify CITY in writing with supporting information within seven
working days, but in no event more than 30 days, of receipt of CITY's billing with any part of
which BART disagrees subject to BART's right to review records and to make final
determinations of the acceptability of costs as provided in this agreement.
4. BART reserves the right to review records, reports, payrolls, accounts, documents and
any data relevant to this MOU for purposes of making determinations on the acceptability of any
9
billing submitted to BART by CITY. BART will notify CITY of any billing or portion of a
billing which is deemed not acceptable and may withhold such amounts from any payments due
to be made to CITY or may request reimbursement of such amounts from CITY.
5. To pay CITY, after completion of all work and within twenty-five (25) working days
after receipt of a detailed statement of the final accounting of costs thereof, any amount over and
above the aforementioned payments required to complete BART's financial obligation pursuant
to this MOU as limited by Section IV, Article 1.
SECTION IV
IT IS MUTUALLY AGREED TO AS FOLLOWS:
1. All obligations of BART under terms of this AGREEMENT are limited to 24 % of Actual
Project Costs but in no event shall the total sum paid to CITY under this MOU exceed one
million dollars ($1,000,000.00).
2. Should any portion of the Dublin Boulevard Improvements or Parallel Road projects be
financed with Federal or State funds, all applicable laws, rules and policies relating to the use
of such funds shall apply notwithstanding other provisions of this MOU.
10
3. CITY's goals for utilization of Disadvantaged Business Enterprise (DBE) will be included
in the construction contract. CITY will award Dublin Boulevard Improvements and Parallel
Road projects to the lowest responsible bidder who meets the DBE goals or who made, in the
sole judgment of CITY, a good faith effort to do so.
4. If termination of this MOU is by mutual consent, BART will bear twenty four (24%)
percent of all Actual Project Costs approved by BART and incurred by CITY pursuant to this
MOU at the time of the termination.
5. In the construction of Dublin Boulevard Improvements and Parallel Road projects, BART
may, at no cost to CITY, furnish a representative, if it so desires. Said representative and
CITY's Resident Engineer will cooperate and consult with each other, but the decisions of
CITY' s Resident Engineer shall prevail as final, binding and conclusive in all matters concerning
the Dublin Boulevard Improvements and Parallel Road projects construction contract or its
performance.
6. Upon completion of all work under this MOU, ownership and title to all materials,
equipment and appurtenances installed will automatically be vested in CITY, and no further
agreement will be necessary to transfer ownership to CITY.
7. If CITY materially breaches this MOU, including but not limited to failing to file
required Progress Reports or failing to comply with applicable regulations, BART may
11
suspend payments to CITY until such time as CITY cures such breach. CITY must cure such
breach within a reasonable time period which shall be specified by BART at the time of
suspension of payment. If CITY falls to cure the breach within the specified time period, BART
may terminate this MOU (a) following 60 days' advance written notice to CITY if the' breach
relates to CITY's failure to provide reports and/or other information pursuant to Section II,
paragraphs 3, 7, 8, 9, 10, 12, 13, or 14, or Co) following two years' advance written notice to
CITY if the breach relates to CITY's failure to construct either the Dublin Boulevard
Improvements or the Parallel Road pursuant to Section II, paragraphs 1, 2, 4, or 6, unless City
cures the breach within the 60-day or two-year period. The remedies of BART are cumulative
and in addition to all remedies now or hereafter allowed by law.
8. If BART materially breaches this MOU, including but not limited to falling to meet the
required and agreed upon payment schedule or falling to comply with. any other terms of this
MOU, City may bring an action to enforce the terms of this agreement. If CITY prevails in
such action, it shall recover all sums due from BART together with interest from the date such
amounts were due until paid at City's rate for its invested funds during the same time period,
together with all damages resulting from BART's breach. The remedies of CITY are cumulative
and in addition to all remedies now or hereafter allowed by law.
9. Neither CITY nor any officer, employee, or agent thereof, shall be responsible for any
damage or liability occurring by reason of anything done or omitted to be done by BART in
connection with the Dublin Boulevard Improvement and Parallel Road projects. It is also agreed
12
that, pursuant to Government Code Section 895.4, BART shall fully indemnify and hold CITY,
its officers, employees and agents, harmless from any liability imposed for injury (as defined
in Government Code Section 810.8) occurring by reason of anything done or omitted to be done
by BART in connection with the Dublin Boulevard Improvement and Parallel Road projects..
10. Neither BART nor any Director, officer, employee or agent thereof, shall be responsible
for any damage or liability occurring by reason of anything done or omitted to be done by CITY
in connection with the Dublin Boulevard Improvements and Parallel Road projects. It is also
agreed that, pursuant to Government Code 895.4, CITY shall fully indemnify and hold BART,
its Directors, officers, employees and agents, harmless from any liability imposed for injury (as
defined in Government Code Section 810.8) occurring by reason of anything done or omitted
to be done by CITY in connection with the Dublin Boulevard Improvements and Parallel Road
projects.
11. CITY shall establish and maintain records pertaining to the fiscal activities of the Dublin
Boulevard Improvement and Parallel Road projects. CITY's accounting systems shall conform
to generally accepted accounting principles. All records shall provide a breakdown of total costs
charged to the Dublin Boulevard Improvements and Parallel Road projects, including properly
executed payrolls, time records, invoices and vouchers. CITY shall permit BART and its
authorized representatives to inspect, examine, make excerpts from, transcribe and copy CITY's
books, work, documents, papers, materials, payrolls, records, accounts, and any and all data
relevant to this MOU at any reasonable time and to audit and verify statements, invoices or bills,
13
submitted by CITY pursuant to this MOU, and CITY shall provide such assistance as may be
reasonably required in the course of such inspection. BART further reserves the right to
examine and re-examine said book, work, documents, paper, materials, payrolls, records,
accounts and data during the three (3) years period after the fmai payment under this MOU and
all pending matters are closed, and CITY shall in no event dispose of, destroy, alter or mutilate
said books, work, documents, papers, materials, payrolls, records, accounts and data in any
manner whatsoever for three (3) years after the final payment under this MOU and all pending
matters are closed. Pursuant to California Government Code Section 8546.7, the parties to this
MOU shall be subject to the examination and audit of the State Auditor at the request of BART
or as part of any audit of BART by the State Auditor for a period of three (3) years after final
payment under the MOU. The examination and audit shall be confined to those matters
connected with the performance of the MOU, including, but not limited to, the cost of
administering the MOU.
12. This MOU may be amended at any time by mutual agreement of the parties. No
alteration or variation of the terms of this MOU shall be valid unless made in writing and signed
by the parties thereto and no understanding or agreement not incorporated herein shall be
binding on any of the parties hereto.
13. CITY' s construction contract claims process will be used in consultation with BART.
BART shall abide by the outcome of said process provided that such claims do not result in an
increase of BART's obligation above what is provided in Section IV, Article 1.
14. In the event any claim results in litigation, CITY shall immediately notify BART and
provide BART with copies of all pleaclings. BART shall have the right, but not the obligation,
to join and participate in, as a party if it so elects, any legal proceedings or actions in connection
with the Dublin Boulevard Improvements and Parallel Road projects, but in no event shall BART
be responsible for CITY's litigation costs nor shall CITY be responsible for BART's litigation
costs.
15. Notwithstanding anything to the contrary contained herein, CITY shall not, without the
prior written consent of BART, settle any claim which does not include as an unconditional term
thereof, a release of BART from liability in connection therewith and a dismissal with prejudice
of such suit, claim, action or proceeding.
16.
service (such as Federal Express) or telecopier transmission.
receipt at the following addresses: "
All notices required hereunder may be given by physical delivery, U.S. Mail, courier
Notices shall be effective upon
To BART by US Mall:
Attention:
San Francisco Bay Area Rapid Transit District
P. O. Box 12688
Oakland, California 94604-2688
Richard A. White
General Manager
15
To BART by Personal or
Special Delivery:
Attention:
San Francisco Bay Area Rapid Transit District
800 Madison Street
Oakland California 94607-4406
Richard A. White
General Manager
To CITY:
Attention:
City of Dublin
100 Civic Plaza
P.O. Box 2340
Dublin, Califomia 94568
Richard C. Ambrose
City Manager
14.
Boulevard and Parallel Road projects construction, or on January 1, 1996, whichever is
in time provided, however, that the obligation for any payment due to CITY from
BART or to BART from CITY arising out of this MOU, and the provisions of Article (9) and
(10) of Section IV shall survive such termination.
This MOU shall terminate upon completion and acceptance by CITY of all Dublin
later
16
IN WITNESS WHEREOF,
herei..nabove stated.
the parties hereto have executed this MOU
on the date first
BART
CITY OF DUBLIN
SAN FRANCISCO
BAY AREA RAPID TRANSIT
DISTRICT
By:
General Manager
Date:
Approved as to form
Office of the General Counsel:
By:
Mayor .
Approved as to form
Office of the City Attorney:
By:
Attorney
City Attorney
17