Item 6.3 Dougherty Rd Ingerchange Improv
+' i CITY OF DUBLIN AGENDA STATEMENT CITY COUNCIL MEETING DATE: June 23, 1986 • SUBJECT: Public Hearing: Dougherty Road/Hopyard Road Interchange Improvements, Phase 1B: Update on Detour of Offramp Traffic Onto Scarlett Court. EXHIBITS ATTACHED: 1) Proposed Schedule 2) Report from Smith, Gray & Company 3) Map Exhibits Will Be Displayed at the Meeting RECOMMENDATION: ? ) Open Public Hearing and Receive Presentation By Mr. Pat Flynn, Representative of the City of Pleasanton 2) Receive Public Continent 3) Question Staff and the Public 4) Close Public Hearing 5) Direct Staff to Work With the City of Pleasanton In . Accordance With Council Direction FINANCIAL STATEMENT: Minimal Encroachment Inspection Cost to .the City • DESCRIPTION: At a previous City Council meeting, Staff members from Bissell and Karn and from TJKM made a presentation regarding the next. phases of the Dougherty Road/Hopyard Road overcrossing. . At that time, the City Council approved the use of Scarlett Court as an interim bypass for the westbound offramp to facilitate the new offramp configuration, subject to development of a provisional parking lot to replace the on-street parking on Scarlett Court that will be temporarily eliminated during this phase of .construction. The phase of construction which utilizes the Scarlett Court detour has begun, and Staff has requested Pleasanton's representative to update the Council and affected businesses in the area with regard to changes in the proposed details and timing. . i ITEM NO. 643 COPIES TO: City of Pleasanton Smith, Gray & Co. Bissell & Karn TJKM 5-28-86 PROPOSED HOPYARD ROAD/I-580 SCHEDULE PROJECT APPROVAL STAGE Project Report Submitted Supplemental Info for Project Report Submitted Project Approval Report Submitted Supplemental Project Report Submitted 10¥11-84' 11-29-84' 05-07-85* 05-31-85' STAGE iA - RAMP RETAINING WALLS Plans Submitted by City Comments by Caltrans Resubmitta! Comments Resubmittat Comments City Encroachment Permit Contractor's Permit 03-19-85' 04-16-85' 04-29-85* 05-06-85* 05-15-85' 06-19-85- 05-06-85- 06-24-85* STAGE lB - RAMP TERMINAL INTERSECTIONS, SIGNALS Plans Submitted by City Comments by Caltrans Resubmittal with Specifications R/W Certification by City Comments by Caltrans Resubmittal Plans Acceptable to Ca!trans City Encroachment Permit Contractor's Permit Construction Begins Signals Activated Construction Completed 03-10-86' 04-04-86* 05-01-86' 05-20-86* 05-23-86* 05-29-86 05-30-86 05-30-86 05-30-86 06-02-86 05-11-87 06-01-87 STAGE !B - ADDITION OF JOHNSON DRIVE SLIP-RAMP AND APPROACH .~ILLS B & K Starts Design City Obtains Temporary Easement for Owens Drive Extension City Submits Plans to Caltrans Caltrans Issues Supplemental Permits Construction Starts on Johnson Drive Ramp and Approach Fills Johnson Drive Ramp Opens Approach Fills Completed and Settlement Period Ends 04-21-86 07-01-86 07-03-86 O8-O8-86 08-11-86 09-03-86 12-05-86 *Completed 5-28-86 STAGE 2 - OVERCROSSING STRUCTURE City Submits Comments on MOU/~OOP Agreements City Submits Structure PS&E Draft Escrow Agreement to City Caltrans Submits M©U to City City Executes MOU Draft COOP and Escrow Agreements to HQ Submit PS&E to Office Engineer Draft COOP and Escrow Agreements from HQ City Executes COOP & Escrow Agreements Dummy Specs Received from HQ Dummy Specs Returned to HQ Advertise City Deposits Funds in Escrow Open Bids Award Contract Start Construction Construction Completed 04-02-86* 05-01-86' 05-01-86' 06-02-86 06-20-86 06-02-86 07-01-86 07-14-86 08-05-86 08-18-86 08-25-86 09-29-86 10-27-86 10-29-86 11-13-86 12-08-86 08-17-87 STAGE 3 - BRIDGE APPROACHES ROADWORK & AUXILIARY LANES B & K Final Design Starts City Executes COOP & Escrow Agreements B & K Submits PS&E to City City Submits PS&E to Caltrans City Receives Caltrans Comments Final PS&E to Caltrans PS&E to Office Engineer Dummy Received from HQ Dummy Returned to HQ Advertise Open Bids City Deposits Funds~in'Escrow Award Contract Start Construction cf Approaches, Roadways Interchange opened to Traffic Miscellaneous items completed 07-01-86 08-05-86 10-15-86 10-27-86 11-24-86 12-08-86 12-22-86 02-!6-87 02-27-87 04-13-87 05-27-87 05-27-87 06-24-87 07-01-87 09-11-87~ 11-02-87 *Completed TO: FROM: SUBJECT: Smitzh, Gr-'ay and Company Consulting, Civil Engineering & Governmental Relations RECEIVED JUN 18 1986 PUBLIC WORKS DATE: June .1.8, 1986 Lee Thompson, City Engineer - City of Dublin Patrick J. F1ynn, Vice President/~ Background Information for Dublin City Council Meeting on June 23, 1986 regarding Scarlett Court About a year.ago, the City of Dublin approved for temporary use, realignment of the westbound 1-580 off-ramp onto Scarlett Court. This realignment is necessary to reconstruct the Hopyard Road/580 interchange improvements which are now under way. Prior to implementing this realigned off-ramp, the City requested a more soecific timeframe on when this will occur and discussion with the business owners fronting Scarlett Court that we impacted by the realigned off-ramp. Oliver De Silva, the general contractor constructing the interchange project, is scheduling the closure-of the existing off-ramp and rerouting of off-ramp traffic to Scarlett Court for the end of July. The sketch showing the realigned off-ramp is shown on the attached map. Due tc the high volume of off-ramp traffic it is necessary to re-strip Scarlett Court to allow three lanes of traffic, two northbound and one southbound. Adding a third traffic lane requires the removal of parking cn the east side of Scar!err Court. To mitigate and help the businesses adequately maintain parking for their employees and patrons, a temporary parking lot will be constructed as shown on the attached map, which will accommodate approximately 24 vehicles. The original plans for the realigned off-ramp required removal of parking on both sides of Scar!err Court. Recently, the City Engineer, Ty Tekawa of TJKM and the City of Pleasanton's Freeway Project Manager, Pat Flynn of Smith, Gray and Company, reviewed the situation in the field and all agreed that with narrower traffic lanes on Scarlett Court during this interim period, parking will only have to be removed on the east side, There are approximately 24 parking stalls that will be removed on the east side~ which corresponds to the number of stalls provided in the temporary parking lot. As mentioned, the interchange contractor is planning to construct the new temporary off-ramp and remove the existing off-ramp by the end of July. There will be a period of approximately one week when the new cfr-ramp will be in operation with parking removed on Scarlett Court at the same time the new temporary parking lot will be under construction. This is because the temporary parking lot cannot be constructed until the existing off-ramp is closed. The realigned off-ramp to Scarlett Court will be in operation for approximately 10 months, during which time the interchange contractor will reconstruct all on-ramps and off- ramps to new configuration on both sides of the freeway, install 700 Ygnacio Valley Road, Suite 320 Walnut Creek, California 94596-3822 (415) 947-1966 permanent traffic signals for off-ramp traffic onto Hopyard Road and begin construction of the new overpass bridge. Construction of a temporary realigned off-ramp, is also being done on the other side of the freeway in the City of P!easanton, by realigning the eastbound I-§80 off-ramp down Johnson Drive. Both of these realigned off-ramps will minimize the traffic congestion during construction and allow the contractor to construct the interchange improvements much faster. It is estimated that without these realigned temporary off-ramps, the construction of the interchange would take another 3 to 4 months to complete, due to all the additional stages of construction that would be necessary while trying to detour off-ramp traffic around the construction area. PJF:msl TMPRMPS.PJF co: Bill Gray Bob Keller Joe Elliot Bob Okamura Bob McCarrick Tom Wintch RE-CEIVED JUN 1 ]986 PUBLIC WORKS ." J q; Ay t' ,4:4 a4 t,(:a. Yl� e rt' . ,,t:< j , , s�, -;rt I 1 LEGEND : t interim roadway ‘.7",-;7e.'''''- Existing roadway�� �tj^i t- O F•a `She � Temporary roadway 44.4 Y/ . C ,. 3 Zr d New roadway constructed s�tJ3 ' OJ Scarlet during this phase ' ® `� I Court ' •rt-' New roadway constructed• a ,,,, •:�~ " �� in previous phases ';,1s .'-:',�G.. 7e,,�,�,�..- —_..,•alt. • -+3- . -�x • -'- ' -, - ,,w,..: ...0...-r,r, ._,„...„1th_,„., , yak':+. © � �.Z..-•�•�� 5 c� Item constructed during 9 Dublin �� � © at����� r^t`'} �`�Y this phase • 12V x. ■ Nt An fl STAGE tQ �',` PHASE 2 '` a M.. F';. m �� � ��v ��rr A. Dougherty Road I,r ,R9 tJ �/e 1. Construct WB off-ramp detour -I- r.+'" dy , to Scarlett Ct. and shift WB - %".- .y F`` t' off-ramp traffic to temporary jr �; f detour. ;.� ` 2. Remove existing WB oft-rams 3. Construct temporary parking P k i` .. „, t.,,,,-.' I •`."C+r.'.. lot. wi;. A. Reconstruct roadway near _.t.60.06.0 (0,,,..:::,...;r.3•-• "44,1•': `* Pleasanton Dublin Blvd. .∎ / ' ;°''- 44.• B. liopyard Road •� ' ,•�,� ' 1. Reconstruct roadway near �,....-5."-:::.),+7' -�_-- .•a ■ �lj� *N ' ' 2 4� Owens Drive. ` •,4,p.A ' CO TRAFFIC IMPACT Qa,, , " mss¢ 1. Delay to northbound and south- bound ti0 e,. O 1;?- bound Hopyara Road and Aj�dka r ¢`;�; �j Dougherty Road during recon - q C '7,4-:::::••••,::,,y.;.z ;,, struction of roadway at Owens STAGE 1B '4a�, , ' � Drive and at Dublin Boulevard. rJORTH RECEIVED q` " Y3• 2.Delay to westbound off-ramp JUN 18 1986 PHA$E 2 .4,:,-;',.. h4",.,..4.:,,,, ,.. traffic due to temporary detour ;f,° to Scariett Court. N.T.S. wy y/ e,` PUBLIC WORKS is- ESTIMATED TIME OF CONSTRUCTION: 5 WEEKS