HomeMy WebLinkAboutItem 8.3 580/680ConstrSched CITY CLERK
File# J$"Jc Io- l ol
AGENDA STATEMENT
CITY COUNCIL MEETING DATE' April 7, 1998
SUBJECT:
I-580/I-680 Flyover Project- Construction Scheduling
Report Prepared by: Lee S. Thompson, Public Works Director
EXHIBITS ATTACHED:
Letter from the Alameda County Transportation Authority (ACTA)
dated March 10, 1998, including a Tentative Construction Schedule
RECOMMENDATION' 'ept
.~/~Aec information
FINANCIAL STATEMENT: The project is anticipated to disrupt business in the area south of
Dublin Boulevard between Amador Plaza Road and Golden Gate
Drive during the proposed project construction. However, it is
further anticipated that the new ramps, when complete, will ease
access to Dublin's Central Business District and provide the area
with an economic boost.
DESCRIPTION: Staff originally directed an inquiry to ACTA on whether the
contractor would be required, by specification, to follow certain time scheduling constraints. Staff was
informed by ACTA that there would not be any mandatory scheduling as the contractor will plan the
project to incur the least expense to the contractor and, in mm, to ACTA.
ACTA has subsequently developed a "probable" schedule, which is attached to this agenda statement.
The work taking place in Dublin has been broken down into four phases or stages projected to cover a
little over 4 years.
It appears that ACTA anticipates the bulk of the Dublin street connection work to occur within Stage 1,
which is to start in July of 1998 and is projected at 360 working days (or about 17 months).
At this time, ACTA is proposing to pay Shamrock Ford to add display space during construction and
allow parking under the flyover structure once completed. The lost vehicle storage space behind Crown
Chevrolet is proposed to be compensated by including payment so that additional space can be leased in
the general area.
The letter from ACTA does point out that this schedule is tentative and is not binding on the contractor.
g:\agenmisc\\flyover
COPIES TO:
Christine Monsen, ,ACTA
ITEM NO.
Alameda
Transportation
Authority
1401 Lakeside Drive
Suite 600
Oakland, California
94612-4305
Telephone
510/893-3347
Facsimile
510/893-6489
E - A la il
ACFA2002@aol.com
Wcbpage
x~cw. ACT.*2002.com
:rk Green
Mayon Union City
Scott Haggerty
~ Sce-Chairman
Supervisor
Keith Carson
Supervisor
Wiima Chan
Supervisor
Roberta Cooper
Mayor, Hayward
Nora Davis
\:ice-Mayor, Eme ,ryvilie
Elihu M. Harris
Mayor, Oakland
MaD, V. King
Supervisor
Gall Steele
Sup~'rvisor
Christine Monsen
Execmiv~' Dire=or
March 10, 1998
Mayor Guy Houston
City of Dublin
City Offices
100 Civic Plaza
Dublin, CA 94568
1-580/680 Direct Connector Project
Tentative Construction Schedule in City of Dublin
Dear Mayor Houston:
You have previously requested that we provide a schedule showing the tentative
construction staging for the project. We have included in this letter an outline schedule
that a contractor may follow. It should be noted that the contractor may follow a different
schedule that best suits his/her abilities and resources. So, tiffs is a tentative outline,
subject to change.
It is presently anticipated that the project will be constructed in four stages. In addition,
there may be multiple phases within one stage. The main items of work under each stage
within the City of Dublin are summarized as follows:
Stage 1 (approx. 360 wortdng days)
· Widen Southbound (SB) 1-680 from Alcosta to 1-580
· Construct ramps at Amador Plaza and connect to Golden Gate
· Construct ramp at Village Parkway, including widening ofi-680 at this vicinity
· Start construction of the south-to-east connector (SEC)
· Reconstruct westerly portion of Arnador Plaza
· Install drainage near the south-to-west ramp (SWS)
Stage 2 (approx. 33 0 working days)
· Constx act ramps at Amador
· Construct SWS
Stage 3 (approx. 270 working days)
· Construct SEC
· Construct SWS
S*?ge 4 (approx. 120 worldng days)
· Widen SB 1-680 over 1-580
· Construct SWS
· Complete Amador Plaza on-ramp and sig-nals
ACTA means Action
Alameda County Transportation Authority.
1-580/680 DCP- Tentative Construction Schedule
March 10, 1998
Page 2 of 2.
In addition to the above work, the contractor may carry out other miscellaneous work, use certain
areas for sta~ng the work, and to stockpile materials and dirt. In particular, the contractor may need
to re-sequence work to balance the amount of dirt needed for the project. For planning purposes, it
is suggested that you assume there to be seventeen (17) working days per month.
We understand that you are concerned over the potential impacts on local businesses. It would be
very difficult, if not impossible, to selectively delay the availability of any portion of the site to the
contractor. To do so at this point may expose the project to significant risk as the potential impacts
to the contractor is unknown. A more workable alternative would be for the individual business
ovmer to work directly with the contractor to lease any necessary land.
We have attempted to show the sequencing of work in the north-west quadrant of the Interchange
in more detail as attached. Again, the schedule is tentative and the actual construction is likely to
deviate from the schedule.
'It is the intention of the Authority to work with Caltrans and the local jurisdictions to minimize the
negative impacts of the project. If you have any other questions, please call myself or Francis Lo of
our office.
Sincerely
Christine Monsen
Executive Director
Encs.
C.C.
Patrick Pang/Rubin Woo, Caltrans (w/encs.)
Richard Ambrose, City of Dublin (w/encs.)
Lee Thompson, City ofDubtin (w/encs.)
John Fenstermacher, Ala Co PWA (w/encs.)
Tom Wintch, URS Crreiner (w/encs.)
Francis Lo (w/encs.)