WHEREAS, On September 17, 2001, the City Council entered into an Agreement with,
Blackshear Construction (Contractor) at a base bid of Two Million Eight Hundred Forty Eight Thousand
Dollars ($2,848,000) to complete the improvements for the Dublin Fire Station 17 in accor~ce with
plans and specifications on file with the City Engineer;
WHEREAS, said improvements have been nearly completed in accordance with said plans and
specifications, and any approved modifications thereof, to the satisfaction of the City Engineer and Head
Building Official of the City of Dublin; and
WHEREAS, as a condition of said contract, Contractor is required to guarantee the improvements
for a period of one year follOwing acceptance of the work by the said City of Dublin; and
WHEREAS, the improvements are now complete, and upon completion the original performance
bond security requirement can be reduced, in accordance with the authority contained in Section 66499.7 of
the Government Code of the State of California, to an amount found necessary to guarantee maintenance of
the completed work for the aforesaid one-year period.
NOW, THEREFORE, BE IT RESOLVED the improvements are completed per plans and
specifications except for minor punch list items, and the City Manager has the authority to approve and
accept the improvements upon completion of the remaining punch list items subject to the aforesaid one-
year guarantee; and
Upon approval and acceptance by the City Manager, the aforesaid original security requirement
may be reduced from the amount of $2,848,000 to an amount of $284,800, upon acceptance by Staff of a
replacement maintenance bond for $284,800 as security for the aforesaid one-year maintenance period; and
Upon approval and acceptance by the City Manager, the original performance bond in the
amount of $284,800 posted in connection with the work involved in the construction of said project may be
hereby released upon acceptance of said maintenance bond.
PASSED, APPROVED AND ADOPTED, this 21st day of October 2003.