Loading...
HomeMy WebLinkAbout7.2 G&O CIP Sched FY 03-04 CITY CLERK File # 110-80 AGEN DA STATEMENT CITY COUNCIL MEETING DATE: November 18, 2003 SUBJECT: Fiscal Year 2003-2004 Goals & Objectives Status Report Schedule Prepared by: Richard C. Ambrose, City Manager ATTACHMENTS: RECOMMENDATION: Goals & Objectives Status Report Capital Improvement Program Schedule /~ Receive the Report FINANCIAL STATEMENT: None DESCRIPTION: On March 31, 2003, the City Council adopted the Goals & Objectives Program for Fiscal Year 2003- 2004. In order to keep the City Council abreast of Staff progress towards the objectives assigned by the City Council, Staff has prepared a bi-monthly status report for the period ending October 31, 2002. As of that date, a total of 14 of 117 objectives (12%) have been completed. With respect to high priority objectives, a total of 13 out of 95 (14%) have been completed. There have been 5 major additional assignments since March 2003. In the attached report, shaded items denote a status change since the last update. In June 2003, the City Council approved an Update to the Capital ImProvement Program (CIP) for Fiscal Years 2002-2007 and appropriated funds for Fiscal Year 2003-2004. The attached C~ schedule lists 48 projects that received funding in Fiscal Year 2003-2004. The schedule shows the status for each project and also identifies an estimated start and completion date. The schedule only includes a time frame for those projects that are funded in Fiscal Year 2003-2004. Subsequent phases and future projects included in the 5 year CIP but not ftmded in Fiscal Year 2003-2004 are not listed on the schedule. Two additional schedules have been included in this update, which provide more detailed information for the Downtown Improvement Implementation and Eastern Dublin Arterial Street Improvements CIPs. Five projects have been completed since the program was approved in June 2003. RECOMMENDATION: Staff recommends that the City Council receive the report. H/cc-forms/agdastmt.doc COPIES TO: ITEM NO. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 1 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS I PRIO~,~Y t. RESPONSIBLE GOAL ~ [START COMPLETION [ 3. High Pattillo 2003 Renegotiate new Electric & Gas Franchise Agreement COMPLETE; Franchise Agreement re- with PG&E. negotiation no longer needed. 4. Low Ambrose 2002 Participate in City Council Team Building Retreat. NO PROGRESS; Not funded in FY 2003-04. ADDITIONAL OBJECTIVES (ADMINISTRATION) 2. High Pattillo 2002 Investigate feasibility of implementing an e-commerce Sept 2003 Nov 2003 UNDERWAY; Staffis evaluating various policy for citizen use of City services, services that would be most appropriate for e- commerce (Business license, building permits). "3. High Perry 2002 Update study for indirect charges for development Dec 2003 Aug 2004 NO PROGRESS; Initial step will be to develop services (ex: evaluate city's overhead rate charged on an RFP for a consultant with expertise in this development projects) and on impact fees area. 4. Medium Perry 2002 Complete feasibility analysis for the DBX Bond re- NO PROGRESS financing. EADDITIONAL OBJECTIVES(FINANCE) 1. High Lowarff 2002 Work with Alameda ~ounty Open Space Committee to Aug 2002 Mar 2004 UNDERWAY ~ .-~ Peabody establish open space acquisition priorities. ] I I ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 2 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIB1,E GOAL START COMPLETION 2. High Peabody/Foss 2003 Participate in Th-Valley Vision Project. July 2003 June 2004 UNDERWAY; Participating in monthly committee meetings. 3. Medium . Peabody 2003 Work with cities in the Tri.Valley to establish a July 2003 TBD UNDERWAY; Participating in monthly clearinghouse to develop & maintain affordable housing meetings to review funding opportunities. opportunities & publicize & coordinate the region's housing. ADDITIONAL OBJECTIVES (INTERGOVERNMENTAL RELATIONS) ! ~DITION~ OBJECTIVES (P~LIC ~LATIONS) Perfo~ con~act evaluations on the following se~ices: 1. High Thompson 2003 · MCE Maintenance Con~act COMPLETE 2. High Ca~er 2003 · Crossing Guards Mar 2004 June 2004 NO PROG~SS; Scheduled for May 2004 3. High Peabody 2003 · Building & SafeW April 2004 June 2004 NO PROG~SS; Scheduled for May 2004 4. High Pe~ 2003 · Auditor Con~act J~ 2004 Apr 2004 NO PROG~SS: Cu~ent plan is to develop an ~P for auditing semces (~TER c~ent se~ice con~act expires at the end of this calendar year). ~D~ION~ OBJECTIVES (CO~CT ~M~IST~TIO~ ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 3 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBLE GOAL START COMPLETION 1. High ~ Peabody 2002 Finalize Housing Element. COMPLETE 4. Hie Peabody/ 2003 Evaluate Dublin Ranch Affordable Housing COMPLETE Ambrose Proj ecffProposal. 5. High Peabody 2002 Complete Reso~ce Management Plan (~P) for Eastern July 2003 June 2005 ~ERWAY; ~P m be completed March Dublin prope~ O~ers ~nexation and General Plan, 2004; Work on SPA and General Plan to ; Specific Plan Amendments. follow. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 4 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBLE GOAL START COMPLETION 18. Medium Peabody/Lowart 2003 Complete General Plan Amendment Study on the NO PROGRESS Transportation Corridor Right-of-Way. 19. Medium Peabody 2003 Complete General Plan Amendment on DiManto Property. June 2003 TBD NO PROGRESS; Proposal not yet filed by applicant. :':::'~ :':::[.:':~:.,: :::::::::::::::::::::::::::::::::::: :::: ::: :::: :: : ::i.;:;: ::-.':.':::::f-.:::':~?:..::~::::: :,'."~:: :~:~: ::~:i:::: ~:::: ~ :::ii::::: i ::: :::::::::::::::::::::: [>::: ::::2~:~ :: : :: :: :::::::: :..: ::::::::: ::::::,:: ::.::::::::::'.':::::: :,:::::'.'. ======================================== ::::::::::::::::::::::::::::::::::::::::::::::::::: ======================================================================================================================== :::::: :::<: :,:,::::~::: ............ :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :~¥~lnanc ===================================================================================================================== ========================================:::: ::::::::::::::::::::::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ........................ :::::::::::::::::::::::::::: 21. Medium Peabody 1996 Develop City Telecommunications Policy beyond Zoning TBD NO PROGRESS ::::: Ordinance for Wireless Communications. 22. Medium Peabody 1996 Update City's General Plan. TBD NO PROGRESS 23. Medium Peabody 2001 Develop Ordinance to limit amount of square footage TBD NO PROGRESS increase on remodel of existing houses. 24. Medium Peabody 2003 Investigate Options for Shamrock Village TBD NO PROGRESS 25. Low Peabody 2003 Develop a fee for General Plan revisions. TBD NO PROGRESS 26. Low Peabody 2001 Investigate parking and access alternatives for Village TBD NO PROGRESS Parkway Specific Plan Area. 27. Low Peabody 2003 Open Space Implementation TBD NO PROGRESS 28. Low Peabody 2000 Develop View and Solar Access Ordinance. TBD NO PROGRESS ADDITIONAL OBJECTIVES (PLANNING) 2. High Peabody 2003 Implement First Time Home Buyer Program Jan 2004 July 2004 NO PROGRESS Development. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 5 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBLE GOAL START COMPLETION 3. High Peabody 2003 Undertake Housing Needs Assessment. July 2003 July 2004 UNDERWAY 4. High Peabody 2002 Develop a 5-Year Affordable Housing Program. Apr 2003 Jan 2004 UNDERWAY; Draft report being revised due to priority changes by Council related to Fairway Ranch. ADDITIONAL OBJECTIVES (HOUSING) 3. Low Thompson 2001 Implement C~b Address Painting Pro.am. NO PROG~SS; Not funded in FY 2003-04. ~DITION~ OBJECTIVES (BUILD~G & S~ET~ ; 1. High Thompson 2003 Work wis Se Developer of Dublin Ranch and Se COMPLETE Regional Water Quali~ Consol Boar~Co~ of Engineers to finalize water quali~ issues/desi~ solutions to allow Se Co~s. Pemit to be issued. 2. High Thompso~ 2003 Implement provisions of Se Regional Water Quali~ Feb 2003 Feb 2004 ~ERWAY; RWQCB is still defining Peabody Control Board ~DES Pe~it. provisions. 3. Medium Thompson 2003 Explore feasibili~ of lighting and landscaping Se kon NO PROG~SS; Not funded in FY 2003-04. Horse Trail. ~DITION~ OBJECTIVES (ENG~EER~G) 1. High Foss/Ambrose 2001 Negotiate Lease A~eement and resolve financing s~ategy July 2003 Sept 2004 NO PROG~SS; Pending completion orBiT for the West Dublin B~T Project. Station desi~ to be completed June 2004. 3. High Foss 2003 Work wis Sha~ock Village to ~acilitate improvement to July 2003 June 2004 ~ERWAY; Plans for Casa Orozco Se Center. expansion unde~ay. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 6 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBLE GOAL START COMPLETION :::::G:~::::~ :::: ::::::~:::~;~: ::::~:::~: ;:¢:::5::: :::::::: : ::::::::::::::::::::::::::::::: ::::::::::::::::::::::: : '~:: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::: ====================================== :: ::::::::::::::::::::::::::::::: ................. ~ :: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: 7. High Foss 2002 Develop a plan to at,act and retain independently owned July 2002 J~e 2003 ~ERWAY; Staff has been unable to locate businesses in new projects as well as the domto~ area applicable pro,ams in State. of Dublin and investigate oppo~niW zones. ~D~IONAL OBJECTWES (ECONOMIC DEVELOPMENT) 2. High Lowa~ 2002 Work actively to develop a regional park in the west hills Dec 2002 TBD ~ERWAY; MOU with EB~D approved in open to the public. Dec. 2002; Preliminau desi~ and cost estimate complete; ~itial meeting held with affected lando~ers. Liaison meeting scheduled with EB~D. ~'~::~::~}~:~:~ ~,,.:< ::: ::::::::::::::::::::: ::~ ::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::: :::::::::~::::: :: :: 5::::: :'.:'.: ::::::::::::::::::::::::::: :: :::: :::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::::::::::::::: .:::::7:::?~4:: :::' +;:.,:~:::::~:x~*~ :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ~:.::::::::~:::::: ::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::: ........: ::~:~=====================================::::: :::::-:?~: ::::::::: :::::::::::::::::::::::::::::: ::,:::::::::: :::::::::::::::::::::::::::::::::::::::::: ~-.<:: :::~::: ::::~: ::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: 4. High Lowa~ 2003 Expand use of the CiW's pro,am registration and point of Oct 2003 Mar 2004 NO PROG~SS sale sof~are packages to the Swim Center. 5. High Lowa~ 2001 Explore oppo~niW to use Doughe~ Hills ~en Space Feb 2004 July 2004 NO PROG~SS on Amador Valley Blvd at Stagecoach for Dog Park. : :::::::::::::::::::::: ::::::::::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :~0:: ::::::::~::~::: :~d:~l::g:: ::: :: :: :::::::::::::::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::tlB~:~g~: J'o :::::::::: ::::'::'::::~:~ :;~::~::::~: ::.:: ~::::::::::::~::; ::~: :::~:~ ::::: ::::::5:': :: ::~.::~::::,~:::::5~¢ ::: ~::~:::: ::::::::::::::::::::::::: : :3¢:: ::::: ::~::: ::::: : :::::::: 0:.;:: :: :: :::~ :':: : ::::: ::~:::: ::::::: g:::: :::::.:,::::::: : m :::::::::::::::::::::::::::::::::::::::::::::::: :::::::::::::::::::::::: ::>:;:::: :: ::::::::::::::::::::::::::::::::::::::::::::::::::::::: :~:: ::::::::::::::::::::::::::::::::: ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 7 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBLE GOAL START COMPLETION 9. High Lowa~ 2003 Explore Historic Park on Donlon Way. NO PROG~SS; Will be done in conj~ction Mth Planning Goal g7. 15. Medium Lowa~ 2000 Update Facili~ Use A~eement ~th Dublin Unified 1994 TBD NO P~OO~SS; Despite several meetings with School Dis~ct. DUSD, no pro~ess has been made on revising a~eement. 16. Medium Lowa~ 2003 ~eplace existing marquee at Shannon Communi~ Center · NO P~OO~SS; Not funded in FY 200~-04. with an elec~onic marquee. 17. Low Lowaa 200~ Explore oppoa~ities for Co--unity Oarden. TBD NO P~OO~SS ~DITIONAL OBJECTIVES (P~S & COM~ITY SERVICES) ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 8 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBI,E GOAL START COMPLETION 2. High Lowart 2002 Work with Dublin Fine Arts Foundation to complete Art 2002 Dec. 2003 - UNDERWAY; Fabrication of Emerald Glen in in the Parks projects for Emerald Glen Park, Bray Emerald Glen progress with installation planned for Dec. .. ~.. Commons and Dolan Neighborhood Parks. Spring 2004 - 2003; Artist selection for Dolan Park in progress Dolan with installation planned for Spring 2004; Bray TBD -Bray Commons deferred until completion of park Commons improvements. 3. High Lowart 2001 Develop a Public Art Master Plan. June 2003 Feb 2004 UNDERWAY; Consultant Services Agreement ., and appointments to Public Art Master Plan Task Force approved by Council; Draft Master Plan to HCAC Dec. 2003 and Council Jan. 2004. 4. High Lowart 2000 Complete Public Art/Bus Shelter Project in Downtown Aug 2001 Nov 2003 UNDERWAY; Fabrication in progress; Dublin' Installation scheduled for Nov. 2003. 6. High ~: Lowart 2003 Sponsor programs and exhibits at the Heritage Center that July 2003 May 2004 UNDERWAY; Funding included in FY 2003- will emphasize Dublin's culture and heritage. 04 Budget; Programs and exhibits approved by : HCAC and scheduled for Oct 2003 and May 2004. 7. High Lowart 2003 Sponsor a day in which the community can bring artifacts, Aug 2003 May 2004 UNDERWAY; Funding included in FY 2003- antiques or photographs to the Dublin Heritage Center for 04 Budget; Program approved by HCAC review by local historians and/or antique experts, scheduled for May 2004. 8. High Lowart 2002 Complete the process of placing Old St. Raymond's June 2002 TBD - could take UNDERWAY; Although the State Office of Church and Murray Schoolhouse on the National Register up to 3 years. Historic Preservation initially indicated it could of Historic Places. locate and process applications submitted by previous historical society it has since determined that this is not possible and the process for submittal will need to be reinitiated by City. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 9 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBLE GOAL START COMPLETION 11. High Ambrose 2003 Explore feasibility of regional cemetery. Aug 2003 TBD UNDERWAY; Preliminary meeting held with other Th-Valley cities; Pleasanton to take lead role. 14. High Lowa~ 2003 Expand cult~al a~s class oppo~ifies to the communiw. July 2003 J~e 2004 ~ERWAY; Bitial course offerings in Fall 2003. 17. Medium Lowa~ 2001 hvesfigate the feasibiliW of a Perfoming ~s Center. NO PROG~SS; Not f~ded in FY 2003-04 ~DITION~ OBJECTIVES (HR~TAGE & CULT~L ~TS) 1. High Thman 2003 Conduct two Co~uniW Academies (ParenffChild, Jan 2004 Apr 2004 NO PROG~SS; Academies to be conducted in Youth, etc). Feb and Mar 2004. 2. High Thuman 2003 Develop Web link on CiW's Web Site to pe~it citizens to COMPLETE repo~ ~affic problem areas/issues. 3. High Thuman 2003 Conduct a minimum of 20 seminars (for merchants and July 2003 June 2004 ~ERWAY; Seminars conducted monthly. residents) in regard to the ~owing problem of identiW theft. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 10 ADDITIONAL OBJECTIVES (POLICE) ....................... I [ ] [ No Objectives for 2003 ADDITIONAL OBJECTIVES (ANIMAL CONTROL) ADDITIONAL OBJECTIVES (F~ SERVICES) 1, High Caaer 2003 Unde~ake multi-functional disaster ~aining exercise. Nov 2003 Feb 2004 NO PROG~SS; Awaiting completion of , Emergency Operations Plan. 3. High Caaer 2003 Conduct Ci~ Council EOC Training Nov 2003 Jan 2004 NO PROG~SS; Awaiting completion of Emergency Operations Plan. ~DITIONAL OBJECTIVES (DISASTER P~P~DNESS) 1. High Caaer 2003 Evaluate options for new solid waste kanchise ageement. Sept 2003 Jan 2004 NO PROG~SS; StaffRepoa outlining options to be presented to Council Jan. 2004 2. High Caaer 2003 Re, se and resubmit Year 2000 base year modification. COMPLETE; Repoa has been resubmiaed; Awaiting approval kom State. ~DITIONAL OBJECTIVES ~ASTE MANAGEMENT) ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 11 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS I PraO T¥ I RESPONSIBLE I GOAL I START COMPLETION ~DITION~ OBJECT.ES (MA~TEN~CE) 2. High Thompson 2003 Plan and stage major public improvements to allow July 2003 FY 2006-07 ~ERWAY; Two of the projects (Scarlett development in the Eastern Dublin Transit Center m Dhve Extension and Doughe~ Road Public proceed. Improvements) have been included in the 5- Year C~ to meet this goal; Two more will be proposed in the 2004-05 CIP; Improvements to emend t~ough FY 2006-07. 4. High Thompson 2001 Work with ACT~ for the implementation of the Measure Sept 2002 Jme 2007 ~ERWAY; Prelimina~ engineering to B ~anspo~afion prQect along the Scarle~ Drive condor begin May 2004. between Dublin Blvd. and Doughe~ Road. Dublin is the project sponsor. 5. High Thompson 2002 Work with the developers of the Lin prope~ to adopt a FY 2001-02 May 2004 ~ERWAY; Discussions with Lin's specific ali~ment of Fallon Road from 1-580 to Bent Tree representatives ~de~ay; Final location of the Drive. Spots Park will affect the road ali~ment. ADOPTED 2003-2004 GOALS & OBJECTIVES BI-MONTHLY REPORT AS OF 10/31/03 PAGE 12 # COUNCIL PERSON YEAR PROPOSED OBJECTIVE FOR ACCOMPLISHING ESTIMATED ESTIMATED STATUS PRIORITY RESPONSIBI,E GOAL START COMPLETION 7. High Thompson 2002 Update Tri-Valley Transportation Council Strategic FY 2001-02 Jan 2004 UNDERWAY; SEP is pending final decision on Expenditure Plan (SEP), together with the other 6 agencies Vasco Road funding. in the TVTC. 9. Low Thompson 2003 Evaluate traffic signals north ofi-580 which are currently COMPLETE; 1-580/San Ramon Road signal outside the City's control, will be under Dublin control. The signals at 1- 580 and Dougherty Road, Hacienda Drive and Tassajara Road will remain under Pleasanton control. It is proposed that the future 1-580 Fallon Road signal be under Dublin's control. . ADDITIONAL OBJECTIVES (TRANSPORTATION) ~ G:\G&OkBI-MONLYkFY2003;2004kBi G&O as of 10-31-03.doc Updated: 11/4/2003 8:33 AM CITY OF DUBLIN FY 2003-2004 CIP STATUS AS OF 10/31/03 GENERAL Project Name 2OO4 Number Status Jul I Aug I Sepl Oct I Nov Dec Jan Feb Mar I Apr I MaYl Jun I Jul 93190 ~,-. , ,,-,,,~ :~.,i,..emra,,.,a~a,_rocess,nuo~,s~em UNDERWAY; Enhancements to i Upgrade accounting system under review. : : : : 93192 i Geographic Information System UNDERWAY; Pavement Management i (Phase III) database completed. : : : 93220 !Communications System [ UNDERWAY; Extension of phone I~~i : : Upgrade i system to remote City facilities in : : : , : progress. . ................... _: ..................................................................... ...... 9~2';i ............ E-commerce and Payment .............................. UNDERWAY; Additional functions Processing currently under evaluation. 93510 !Emerald Glen Fire Station Fire COMPLETE i Station 17 93911 Front Counter Upgrade UNDERWAY; Improvements to'start end of Nov. 2003. 93916i ADA. Building confo'~:~'r~e UNDERWAY; Improvements to start ............................. Upgrades Oct. 2003 at Heritage Center. 94510 Fire Fee Study Update NO PROGRESS; Waiting for final costs for Fire Stations 17 & 18. 93';i~'~'5''''''~ CTV Studio Remodel UNDERW'AYi Preliminary design complete; Completion of construction documents underway. 93.174 Emergency Portable Radios ! COMPLETE .... ~':i"~5' "Public Safety Memorial i UNDERWAY; Completion of project i will depend on fundraising currently i underway. Number 94060 Project Name i Downtown Improvement Implementation Phase I CITY OF DUBLIN FY 2003-2004 CIP STATUS AS OF 10/31/03 COMMUNITY IMPROVEMENTS 2004 Status Jul I Aug I SePl Oct I Nov ] Dec Jan FeD I Mar ] Apr I May I Jun ] Jul !UNDERWAY; See attached schedule. 94226 Freeway Underpass Art at NEARLY COMPLETE ., Dublin Boulevard & Amador i Valley Boulevard ~i : 94230 ~, Arroyo Vista Roof Repair i NO PROGRESS; Project Scheduled for ~:~:.:.=.:.:.:~:::::: :::::::::::: Spring 2004. March 2004. installation scheduled for Nov. 2003. : : : under 1-680 12003. : i Landscaping i : CITY OF DUBLIN FY 2003-2004 CIP STATUS AS OF 10/31/03 DOWNTOWN IMPROVEMENT IMPLEMENTATION PHASE I -94060 2004 Project Name Status Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr I May I Jun I Jul Projects Funded in Fiscal Year ' 2003-2004 Gateway Monument @ Dublin BIvdNillage UNDERWAY; Construction documents Pkwy ~95% complete; Construction to begin : i..SeP.'~:. 2OQ.4: . ....... , Pedestrian Improvements @ Village COMPLETE ' : Pkwy/Lewis Ave Arched Gateway Design for St. Patrick UNDERWAY; Preliminary design Way/Amador Plaza Rd, approved by Council; Fin8 design to be : : completed by May 2004; Construction to : : begin Sept. 2004. : Village Pkwy and Lewis Ave Plaza COMPLETE : : : ', Sidewalk Widening & Lighting UNDERWAY; Design to be completed ................................................................................. ' ............. ~ .......... ~ ...... Improvements Winter 2004; Construction to begin : : ~ Spring 2004. : : ' CITY OF DUBLIN FY 2003-2004 CIP STATUS AS OF 10/31/03 Number Project Name Status 95050 Shannon Community Center UNDERWAY; Building evaluation PARKS 2004 ' Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Improvements , complete by March 2004; Painting to be !completed Spring 2004. 95600 Emerald Glen Park Phase 11 i UNDERWAY; Construction complete i December 2003; Maintenance complete i March 2004. : 95600 Emerald Glen Park Phase III iUNDERWAY; Negotiation of consultant :::::::::::::::::::::::::: services agreement in progress. 95635 Park Play Area Renovations UNDERWAY; Kolb Park complete; No progress on Shannon Park. 95640 Dublin Ranch Neighborhood Parks (Bray Commons) UNDERWAY; Construction complete February 2004, Maintenance complete 95830 Dublin Sports Ground Renovation NO PROGRESS Phase III (Lighting) 95850 Parks & Recreahon Master Plan NEARLY COMPLETE; Draft plan to Update PCSC Dec. 2003 and Council Jan. 2004. 95851 Falion SpOrts Park UNDERWAY; RFPs distributed in Nov. Final consultant services agreement to Council Jan. 2004. UNDERWAY; Anticipate bid award Nov. .... ~'~'~'(J'"'""! Senior Center 2003; Construction to begin Jan. 2004. 95551 i Cemetery Planning Study UNDERWAY; Letter sent to DHPA to ~ ascertain interest. 95566 i Murray Schoolhouse Exhibit UNDERWAY; Consultant bids over i Restoration i budget; Re-evaluating approach to i project. : 95692 i Senior Center Van COMPLETE ,, ', CITY OF DUBLIN FY 2003-2004 CIP STATUS AS OF 10/31/03 STREETS Number Project Name Status 96061 Street Light Pole Replacement UNDERWAY; Improvements to start Oct. 2003. 96300 Village Pkwy. & Lewis Ave. i COMPLETE Intersection Improvements 96380 1~580/San Ramon Interchange i UNDERWAY; Construction commenced Sept. Improvements 12003 with completion by Mar. 2004. 96400 Eastern Dublin Arterial Street '~ Improvements 96420 1-580/Tassajara Interchange !Improvements 2004 Jul I Aug I Sepl Oct INov I Dec Jan Feb Mar Apr May i Jun I Jul Amador Valley Blvd. completed Nov. 2003. 96840 Scarlett Drive Iron Horse Trail NO PROGRESS; Design to start May 2004. Extension 96580 !Annual Street Overlay NO PROGRESS; Improvements to start May i 2004. 96585 Annual Slurry Seal Program NEARLY COMPLETE; Improvements to be completed Nov. 2003. .... 96~':~Z~''~ Bike Path- Alamo Creek North of '~'"N'EA~RLY C01~i'P'i~ETEi' ~0'r~'s'i~'U'(J;~i~'"'l~'"~'~ ................................... i attached schedule i NEARLY COMPLETE; Construction to be i completee Dec. 2003. : : ~ Improvements ~ 2004. : : : : : : equ~pmom ~ep~acoment : : : : : ........................................................................ : : ................................... 71 ......................... ....... 9656'~"'"'"~ Traffic Signal Upgrade-Village UNDERWAY; Improvements to start Nov. 2003. Pk~/Amador Valley Blvd ' : : : : : : 9~565 ~Traffic Signal ~ Central Pkwy. & UNDERWAY; Bid awarded; Improvements to ~ lassajara Greok sta~ ~ov. 2003. : ~ ................................................................................................................................. : , ...... , ...... ', ...... ', ..... CITY OF DUBLIN FY 2003-2004 ClP STATUS AS OF 10/31/03 STREETS Number Project Name Status Jul IAuglSeplOct INovlDec 2j0a0n41FeblMarlAprlMaylJunt Jul 96852~!Dougherty Rd mprovements- UNDERWAY; Preliminary engineering and ;~ Houston to 1-580 environmental study to be completed April 2004. i i i i i i i ! i i II i MPL~E Im rovements to be Village Pkwy. to Sierra i completed Nov. 2003. ~ ~ i ' 96566 i Traffic Signal at Dublin Blvd and UNDERWAY Inspiration Dr 96567 Traffic Signal At:AmadorValley BIvd and Starward Dr 96781 i Tassajara Creek Trail ! UNDERWAY; Improvements to be completed Improvements - Dublin BIvd to i April 2004. Gleason Dr 96568 i Traffic Signal Upgrade - Dublin UNDERWAY; Construction to begin Feb. 2004. i BIvd and Scarlett Dr UNDERWAY; Scheduled to be completed with Senior Center. CITY OF DUBLIN FY 2003-2004 CIP STATUS AS OF 10/31/03 EASTERN DUBLIN ARTERIAL STREET IMPROVEMENTS - 96400 Project Name Construction By Tassajara Road from Dublin Ranch Phase I north to Failon Pinn/Lin Road. Four lanes total. Two to be constructed by Pinn, two by Lin. Extend Dubli~ Blvd. and Central Parkway easterly Lin approximately 730 ft. and 830 ft respectively. 2OO4 Fallon Rd. from Tassajara Rd southwesterly to the end of Dublin Ranch improvements. Pinn Complete Hacienda Dr. between Dublin Blvd. and Gleason Transit Center Dr. (ACSPA or their developer) Not anticipated:in FY 2003-04. Developel' has placed in foture phase. Not anticipated;in FY 2003-04. Development behind prop:osed sc~hedule.