HomeMy WebLinkAboutReso 191-00 HQE I580/SRRd/FoothRESOLUTION NO. 191 - 00
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
APPROVING AMENDMENT TO AGREEMENT WITH HQE, INCORPORATED
FOR ENGINEERING SERVICES
WHEREAS, the City Council of the City of Dublin approved an agreement for engineering services
with HQE, Inc. for the preparation of a Project Study Report (PSR) for the 1-580/San Ramon Road-
Foothill Road Interchange Improvement on February 1, 2000; and
WHEREAS, HQE Inc. had completed the PSR and Caltrans has tentatively approved the report;
and the next step in acquiring Caltrans approval is the preparation of the Project Report/Environmental
Documentation (PR/ED); and
WHEREAS, HQE's Scope of Work is proposed to be expanded to include the preparation of the
PR/ED and the not-to-exceed amount to perform this task is $160,972, and
WHEREAS, the Cities of Dublin and Pleasanton had previously agreed to equally share the cost of
preparing the PSR, and similarly Dublin had requested Pleasanton to equally share the cost of preparing the
PR/ED, through a funding agreement that has not yet been completed.
WHEREAS, the City of Dublin desires to advance the project, and to do so it is necessary for
Dublin to fully fund the cost of preparing the PR/ED.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does hereby
approve Amendment No. 1 to the agreement with HQE, Inc. to include the preparation of the Project
Report/Environmental Document, which is attached hereto as "Exhibit A" .
BE IT FLIRTHER RESOLVED that the Mayor is authorized to execute the amendment.
PASSED, APPROVED AND ADOPTED this 21~ day of November, 2000.
AYES:
Councilmembers Howard, McCormick, Zika, Vice Mayor Lockhart and Mayor
Houston
NOES: None
AB SENT: Non e
ABSTAIN: None
ATTEST: C~C~it~ .er~kkL
C 1
K2/G/11-21-00/reso-hqe.doc (Item 4.2)
g :\engfihqeXreso I stanmdNov21-2000
Mayor
e
e
;;. z6:3 /)
EXHIBIT "A" OF RESOLUTION' -00
AMENDMENT TO AGREEMENT
BETWEEN CITY OF DUBLIN AND HQE, INCORPORATED
FOR ENGINEERING SERVICES
WHEREAS, the City of Dublin (hereinafter referred to as II CITY") and HQE, Inc.
(hereinafter referred to as "CONSULTANT"), entered into an agreement on February 1, 2000 to prepare a .
Project Study Report for the I-S80/San Ramon Road-Foothill Road Interchange Improvement; and
WHEREAS, the Scope of Work to be performed is proposed to be extended; and
WHEREAS, the not-to-exceed contract amount is proposed to be increased to cover the
cost of the additional work; .
NOW, THEREFORE, the parties hereto agree as follows:
Scope of Work
The Scope of Work shall be extended to include preparation of the Project Report/Environmental
Documentation as described in HQE's Revised Scope of Work/Fee Estimate dated September 21, 2000
(Phase 1) for the I-580/San Ramon Road-Foothill Road Interchange Improvement Project (attached).
Extension of Term
The to~ cost for time-and-materials work under this amendment shall not exceed an additional
$160,972.
CITY OF DUBLIN
Mayor
ATTEST:
City Clerk
HQE, ll)JCORPORA TED
4~~.~
.' . Heidi M. Duren
Date: /0 /2. 7 ~C'
, (
I
II. 2./~ oCt
tI,,-
e
e
EXHlBIT A
SCOPE OF SERVICES .AND SCHEDULE
:S ":31
PER HQE, Inc., Revised Scope ofWorklFee Proposal dated January 19,2000 for the San Ramon
RoadlI-S80 Interchange Modifications Project Study Report (ATTACHED).
Exhibit A
p.,,,,... 1 ",f' 1
~ ,
e
e
b ~:31
City of Dublin
San Ramon RoadlI-SSO Interchange Modifications
Project Study Report - Scope of Work
The existing San Ramon RoadlI-580 Interchange is a four quadrant cloverleaf (Caltrans Type L-
10) interchange providing free flow characteristics for all movements. It is limited in it's
capacity, however, due to the short weaving distances between loop ramps. It also limits the
available weaving distance for the 1-580 westbound to San Ramon Road northbound movement
due to its close proximity to the Dublin Boulevard/San Ramon Road Intersection, causing
. potential safety issues.
In order to address these issues, the City of Dublin proposes to modify the interchange by
realigning the westbound and eastbound diagonal off-ramps to a tee intersection "with San Ramon
Road/Foothill Boulevard.
Major features of the proposed project include:
. Realignment of the westbound 1-580 off ramp terminus to a tee intersection at San
Ramon Road and installation of a new signal;
. Realignment of the eastbound 1-580 offramp terminus to a tee intersection at Foothill
Road (San Ramon Road) and installation of a new signal;
. Potential removal of westbound 1-580 to southbound San Ramon Road loop ramp;
. Potential removal of eastbound 1-S80 to northbound 'San Ramon Road loop ramp.
The Scope of Work for this effort will require preparation of a Project Study Report (PSR) in
accordance with Caltrans' standards. .
The detailed Scope of Work will include the following tasks:
Task 1- Preliminary Data Preparation/Collection
a. Site Visits
The project team will conduct site visits as necessary to identify and understand
existing field conditions. Assumes two site visits.
b. Prepare/submit Encroachment Permit Application for field work
An encroachment permit application will be prepared for the City's signature to obtain
right of entry for site visits. .
C:\City ofDublin\sanramonscopepsr.doc
Page 1 of7
01/19/00
e
e'
? ~ ~1
City of Dublilz
HQE, Inc.
San Ramon Road/I-S80 Interchange
Project Study Report Scope of Work
c. Traffic Data/Forecasts (Existing and 2025 traffic volumes)
This task includes collecting eXisting traffic data from Caltrans and the Cities of
DublinlPleasanton, and projecting peak hour traffic volumes for the design year 2025
using the Tri- Valley model developed by others.
AM and PM peak two-hour period traffic counts will be performed at the following
locations:
. I-5801F00thilllSan Ramon Interchange - all 8 ramps plus through movements on
Sam Ramon RoadIFoothill Boulevard
. Sam Ramon RoadlDublin Boulevard intersection
. Foothill Boulevard/Canyon Road intersection
The traffic forecasting methodology will be confirmed with Caltrans prior to use of the
forecasts for the traffic operations analysis.' The most current version of the Tri-
Valley EMME/2 Transportation Model that is consistent with a current version of
ABAG Projections land use will be obtained, checked for accuracy, and adjusted as
necessary. The model will be applied to generate 2025 traffic forecasts for the
freeway mainline, ramps, and adjacent intersections. The model results \vil1 be
adjusted based on observed traffic counts using a procedure approved by Caltrans.
d. Aerial Photos
Obtain aerial photographs of the interchange for use in preparing the conceptual
geometry for two alternatives.
e. Collect all available information
Includes construction record drawings ("as-builts"), bridge plans, geotechnical
information, utility information, Right of Way Record Maps, Hard Copy maps,
Floodplain Data, etc.
Task 2 - Project Management
a. Administration
Includes monthly Invoicing, Progress Reports and Contract Compliance.
b. Schedule/Budget Control
Prepare initial PSR schedule and budget and monitor them as necessary to continually
reflect project status. Update Schedule only if impacts become significant.
r..\r:itv nfDnhlin\samamonscouensr.doc
Page 2 of7
01/19/00
e
San Ramon RoadlI-580 Intercltange
Project Study Reporl Scope of Work
e
rt ~ 'g'1
City of Dublin
HQE, Inc.
c. Agency Coordination
Coordinate with the City of Dublin, Caltrans, City of Pleasanton and Utility
Companies as necessary.
d. Subconsultant Coordination
Manage and monitor all subconsultant services for contract compliance and prepare
Subconsultant Agreements.
Task 3 - Meetings
a. Kick-off Meeting with Caltrans/City ofDub1inlCity of Pleasant on
Key project team members will attend this introductory meeting to discuss overall
project goals, schedules, and requirements. HQE shall prepare meeting minutes for
distribution to all attendees.
b. PDT Team Meetings
Monthly meetings will be held to discuss project progress and resolve outstanding
issues. HQE will prepare meeting minutes for each meeting for distribution to
attendees and pertinent team members. Assumes 8 meetings.
c. Technical Coordination meetings
Meetings will be held as necessary to discuss technical issues such as geometry,
environmental concerns, traffic proj ections, etc. Assumes a total of six (6) meetings.
d. Meetings with Cities of Dublin and Pleasanton
Assumes four (4) meetings to provide project status updates and present outstanding
issues, if any.
Task 4 - Draft PSR
a. Prepare preliminary horizontal geometry
Graphical layouts of the proposed project will be prepared on aerial photos to show
the baseline features of the project. The geometry will be used to assess
environmental impacts, impacts to utilities, and confirm that the proposed project lies
within existing right of way. It is assumed that there will be only two Project
Alternatives.
C:\City ofDublin\sanramonscopepsr.doc
Page 3 of?
01/19/00
e
e
9c131
City of Dublin
HQE, Inc.
San Ramon Road/I-580 Interchange
Project Study Report Scope of Work
b. Draft Construction Cost Estimates
Prepare PSRlevelcost estimates according to Caltrans standards. -
c. Right of Way Data Sheets
Prepare right of way data sheets in accordance with Caltrans standards. Utility
relocation information is included in the data sheets.
d. Environmental' Analysis
The environmental processing for the proposed project is designed to fulfill
requirements specified in CEQA, the CEQA. Guidelines, NEP A and other applicable
regulations. The appropriate environmental document for this undertaking is assumed
to be a Categorical Exemption (CE) under CEQA and a Categorical Exclusion
(CATX) under NEP A. The CE/CATX will not be prepared until the Project
Report/Environmental Document Phase of the. project. No formal public meetings are
anticipated at this time.
. PAR staff anticipates attendance at one initial project initiation meeting.
Additional meetings can be attended- on a time-and-materials basis.
. PAR will conduct a preliminary environmental assessment consisting of a
windshield reconnaissance and record searches.
. Documentation will consist of a memorandum including the findings of the record
,searches, results of the windshield surveys, a listing of the required technical
studies and a recommendation of the anticipated environmental document type
required should the PSR advance to a formal project.
. Since it is anticipated that a CE/CATX will be prepared, the report will not address
mitigation costs. If the Preliminary Environmental Assessment concludes that a
more lengthy and formal environmental process is required, the scope may require
-adjustment to include a discussion of mitigation costs and timelines.
. PAR will rely on information contained in the City of Dublin's General Plan and
any updates and will request a records search of the archaeological information
maintained at the Northwest Information Center of the California Historical
Resources Information System. Other repositories of data sensitive species
(California Natural Diversity Data Base) and other resource areas will be contacted
as appropriate.
. PAR will conduct record searches and windshield surveys for the disciplines listed
below. Additional analyses needed to provide detailed information regarding
r".\r;n, "f" Tl,,'hl;,"\c~n~TT"\n" c::~nnp..n~ .nor.
Pa2:e 4 of 7
01/19/00
e
San Ramon RoadlI-580 Interchange
Project Study Report Scope of Work
e,
/0 1/-:31
City of Dublin
HQE,Inc. .
wetlands, biological resources, cultural resources, noise, visual and socioeconomic
conditions are not included in this PSR scope.
Biological Resources
Record searches of the California Natural Diversity Data Base (CNDDB) will be
assessed for plant and animal species of special concern that might occur in the
project area and a preliminary assessment as to whether habitat exists in the project
area. This work does not include full protocol surveys, a wetlands delineation or
detailed surveys of wildlife or vegetation mapping.
Noise
.A..n assessment of the potential for noise impacts will be based on identification of
potentially sensitive receptors during the windshield survey. No modeling analysis
will be provided.
Visual
A brief assessment of potential for impacts to scenic resources will be made based
on a windshield survey of the site and surrounding land uses.
Land Use/Socioeconomic Issues
A brief assessment of potential for land use and socioeconomic impacts will be
made based on a windshield survey of the site and surrounding land uses and on
information contained in the City's General Plan.
Cultural Resources
PAR will request a record search be conducted at the California Historical
Resources Information System, Northwest Information Center maintained by
Sonoma State University, Robnert Park. The examination of records at this
institution will' provide data on known site locations within or adjacent to the
project. A windshield survey of the area will be conducted to identify thepotential
for or presence of historic buildings or obvious prehistoric and historical features
or sites along the existing right of way.
C:\City ofDublin\sanramonscopepsr.doc
Page 5 of7
01/19/00
e
e
II ct 1; '7
City of Dublin
HQE, Ine.
San Ramon Roadll-580 Interchange
Project Study Report Scope of Work
Other disciplines, including air quality, will be addressed based on documentation
available in the City of Dublin General Plan and General Plan EIR or other
recently prepared studies for the area.
e. Accident Data Review
Obtain the most recent TASAS output from Caltrans to quantify accidents per million
vehicle kilometer and compare those to statewide averages for similar facilities.
f. Traffic Operations Analysis'
Perform traffic operations analysis for the No Build and one Project Alternative
(preferred Alternative) for existing and design year 2025 conditions. The analysis
includes intersection levels of service, ramp junction analysis and queuing analysis for
intersections and ramp metering operations at on-ramps. Information will be provided
in Draft, Final Draft, and Final Traffic Operations Analysis Report.
g. Design Exception Fact Sheets
Prepare fact sheets for approval by Caltrans for all non-standard design features. It is
anticipated that three fact sheets will be required (Mandatory, Advisory and Ramp
Metering/HOV By-pass).
h. Initial Site Assessment (ISA)
Includes: site visit to review existing conditions, record evaluation of Federal, State
and County environmental databases to search for hazardous substance releases in the
vicinity of the project site; review of historical aerial photographs to evaluate previous
land uses; review of Record Drawings to develop a preliminary assessment of
anticipated geotechnical conditions and investigations requirements; and a letter-report
summarizing the results of the site visit and records review activities.
1. DraftMOU
Coordinate the preparation of the Draft Memorandum of Understanding (MOD), and
between Caltrans and the City of Dublin.
J. QAJQC of Draft PSR prior to submittal
Perform internal quality control check of Draft PSR to assure that all elements of the
report have been adequately and properly addressed.
r.\r,tv nfnnhlin\sanramonscouensr.doc
Page 60f 7
01/19/00
San ~amon RoadlI-580 IrChange
Project Study Report Scope of Work
e
J) ~" J?
City of Dublin
HQE,Inc.
Task S - Final Draft PSR
a. Prepare Response to Comments received from Cities/Caltrans
b. 1dentifyIResolve Outstanding issues, if any
c. Incorporate Comments as appropriate
d. Submit Final Draft PSR
TaSk 6 - Final PSR
a. Incorporate any remHinlng comments
b. Submit Final PSR for approval & signature
Assumptions.
· Right of way acquisition is not requir~d for the proposed modifications.
· No impacts to Dublin Creek or the Cemetery on the north side ofI-580.
· CTC Action is not required.
- Revised Freeway Agreement is not required (Le. no change in access points).
- Potholing of existing utilities is not required (no high risk facilities).
- Processing time of 9 months.
- Traffic Data includes only existing and design year (2025) analysis.
· No exceptions to Caltrans Longitudinal Encroachment permit policy are required
(utilities).
- All agreements will be coordinated- only; actual preparation is by Agencies.
- Appropriate Environmental Documentation is Categorical Exemption/Exclusion.
· Traffic model will come from Dowling; will use only one model (Tri- Valley or Dublin).
-No metric mapping will be required at this stage; aerial photographs will be used for
geometric exhibits.
ProDosed Project Team
CCS Planning & Engineering, Inc.
P.A.R Environmental Services, Inc.
The Mark Group, Inc.
C:\City of Dublin \sanramonscopepsI.doc
Traffic DataIForecasts & Traffic Operations .Analysis
Environmental
,Initial Site Assessment (ISA) - Geotechnical
Page 7 of7
01/19/00
-
) S 4 1;7
Task Number/ Project Project Design CADD/ Office I Total
Description Manager Engineer Engineer Designer Admin Hours
$ 120.00 $ 100.00 $ 66.00 I $ 65.00 $ 50.00
Task 1- Preliminarv Data PreoarationlCollection I
a. Site Visits 2 6 6 2 01 ]6
b. Encroachment Permit Application 1 0 0 0 1 2
c. Traffic Data/Forecasts CCS Planning & Engineering - $12.160 0
d. Aerial Photos 0 2 4 0 0 6
e. Collect all available information 0 8 16 0 41 28
Task 1 Total 3 16 26 2 5 -..,
::1_
I
Task 2 - Proiect Management
a. Administrati01l 9 6 0 0 18j 33
b. SchedulelBudget Control 24 12 0 0 0 36
c. Agency Coordination 24 12 4 0 0 40
d. Sub consultant Coordination 24 15 12 0 0 51
Task 2 Totall 81 45 16 0 181 160
Task 3'- Meetinas I I
I
a. Kick-off Meeting I 3 5 3 01 ] 12
b. PDT Team Meetim!s I 161 241 01 0 81 48
c. Technical Coordination meetin!!s I 12 12 181 01 61 48
d. Meetin!!s with City 8 16 0 01 4 28
, Task 3 Total I 39 571 211 0 191 136
Task 4 - Draft PSR I 1 .
I I
a. Conceutua1 GeometrvlDraft Reuort 41 40 80 30 01 154
b. Draft Construction Cost Estimates 3 16 32 0 01 51
c. Ricl1t of Way Data Sheets 2 4 8 0 01 14
d. Environmental Documentation -\ PAR - $5,000 0
e. Accident Data Review 0 41 81 or 0 12
f. Traffic Operations Analvsis I CCS Planning & Engineering - $16,740 0
2. Desi!!II Exception Fact Sheets, ifreouired 2 4 8 4 41 22
h. Initial Site Assessment (ISA) The Mark Group - $3,500 0
i.MOD 2 2 0 0 0 4
;. QAiOC of Draft PSR 4 21 0 0 0 6
Task 4 Total 17 72 136 34 4 263
Task 5 -' Final Draft PSR I
I
a_ Preuare Response to Comments 1 3 8 12 01 31 26
b. Identifv/Resolve Outstanding issues, if any . 2 4 0 0 0 6
c. Incoroorate Comments as appropriate 2 121 24 81 01 46
d. Submit Final Draft PSR/PR 1 3 3 0 0 7
Task 5 Total 81 27 39 81 3 85
Task 6 - Final PSR I 1 I I
I ,
a. L,coroorate any remaining comments I 21 6 12 41 2 ... "
..0
b. Submit Final PSRlPR for approval & signature 1 2 3 0 01 6
Task 6 Total 3 8 15 4 2 .....,
::J~
, TOTAL HOE HOURS 151 225 253 48 51 i28
TOTAL HQE COST 1 $ 18,120 $ 22.500 $ 16,698 $ 3,120 I $ 2.550 I S 62.988
e
City of Dublin
e
San Ramon RoadlI..580 Interchange Modifications
Project Study Report
Fee Estimate Summary
High Quality Engineering - Prime Consultant $
CCS Planning & Engineering - Traffic $
PAR Environmental - Environmental $
The Mark Group, Inc. -Geotechnical $
TOTAL COST $
Estimated Direct Costs
Reproduction
MailJDelivery Charges
$
$
Total Direct Costs $
66,188
28,900
5 ;000
3,500
103,588
2,700
500
3,200
It! ~:31
Note: Reproduction Costs assume the following number ofPSR copies for each submittal:
City of Dublin
CAL TRANS
City of Pleasanton
Project Team
Total Copies
All Direct Costs will be billed at actual cost
sanramoncostpsr.xls
1 of 1
5
10
5
7
27
1/19/00