HomeMy WebLinkAbout4.06 SwimCntrWaterslideAICITY CLERK # 600-35 AGENDA STATEMENT CITY COUNCIL MEETING DATE: January 16, 2001 SUBJECT: Acceptance of Work- Contract No. 99-15, Dublin Swim Center Waterslide Installation Project Report Prepared by Paul McCreary, Recreation Supervisor ATTACHMENTS: 1. Budget Change Form RECOMMENDATION: e Accept improvements under Contract No. 99-15 and authorize the release of retention in the amount of $19,268.10 after 35 days if there are no subcontractor claims. Approve a Budget Change of $29,107 from Unappropriated Reserves. FINANCIAL STATEMENT: Salaries and Benefits Engineering Inspection & Testing Construction Miscellaneous TOTAL Tot~ Budget FY 99/00 FY 00/01 FY 00/01 Project ~ Award Actual Budget Actu~ Total $2,000 $89O $0 $0 $89O $0 $2,199 $0 $2,336 $4,535 $203,390 $166,445 $0 $26,771 $193,216 $890 $244 $0 $0 $244 $206,280 $169,778 $0 $29,107 $198,885 This project was carried over to FY 2000/2001 because of the need to complete some remedial work to the plaster after the swim season. Although the total project is under budget, a budget change is needed because the budget was based upon the project being completed during the prior fiscal year. DESCRIPTION: On January 18, 2000, the City Council awarded Contract No. 99-15, the Dublin Swim Center Waterslide Installation Project, to Tricon Construction, Inc. The project improvements included the installation of a 100-foot long, double-loop waterslide. The installation of the waterslide was completed and turned over to the City for operation in early July. During the construction the Contractor left stains on the surface of the plaster. The pool needed to be drained to remove the stains. Therefore, the City required the contractor to return after the swim season to complete the work. The contractor completed the repairs in November 2000. Staff inspected and approved the work as complete. Staff recommends that the City Council accept the improvements under Contract 99-15, the Dublin Swim Center Waterslide Installation Project, and authorize the release of the retention in the amount of $19,268.10 after 35 days if there are no subcontractor claims. Further, Staff recommends that the City Council approve the budget change form in the amount of $29,107. G:\COUNCIL\I-16-01 waterslideacceptance.doc COPIES TO: Triton Construction, Inc. ITEM NO. CITY OF DUBLIN BUDGET CHANGE FORM New Appropriations (City Council Approval Required): X From Unappropriated Reserves CIf Other than General Fund, Fund No - From New Revenues !-' :~DECREASE BIJDG~T AC;CO!.INT ' ' AI~iO(jNT Name: CHANGE FORM # Budget Transfers: From Budgeted Contingent Reserve (1080-799.000) Within Same Department Activity Between Departments (City Council Approval Required) Other ':" iNE"R~AS'!i'ii/DGET ACCOUNT ~: .! A~IOUNT Name: Engineering Inspection $2,336.00 Account #: Account #: 001.95910.740.079 Name: Name: Improvements $26,771.00 Account #: Account #: 001.95910.750.050 Name: Name: Account #: Account #: Name: Name;. Account #: Account #: Name: Name: Account #: Account #: City Manager: Date: Signature Signature REASON FOR BUDGET CHANGE ENTRY: This project was carried over to FY 2000/2001 to repair stains in the pool plaster. MaWr: Signature Date: Posted By: Date: Signature G:\COUNCIL\I-16-01 waterslidebudgetchange.doc ATTA.CHMENT I