HomeMy WebLinkAboutItem 6.2 Planning Review Backlog D uB I
�� 15D r
AGENDA STATEMENT
Meeting Date: December 13, 1982
SUBJECT : Planning Review Backlog
EXHIBITS ATTACHED : Survey
QAuthorjze RECOMMENDATION Staff to secure services of contract
planning assistance on as needed basis, not to exceed
20 hours per week.
2) Authorize budget transfer of $2 ,000 from contingent
reserve to planning contract services account.
FINANCIAL STATEMENT: Total estimated cost $17,700 for remainder of fiscal year
1982-83. Funds remaining in planning contract services
budget $15,700 .
DESCRIPTION : On October 11, 1982 the City Council authorized Staff
to secure the services of a part-time planning consultant
for a period up to 6 weeks. This action was taken in
order to reduce a backlog of planning applications which
resulted at the time that the City assumed planning review
from the County. The planning consultant assisted Staff
from October 20, 1982 through November 29, 1982. During
that time 29 applications were on file (17 pending on
October 11, 1982 and 12 new applications submitted during
that period) . The status of the 29 applications is as
follows:
18 - Processed to hearing (or action) with an average processing time of
5 - 6 weeks.
2 - Continued at applicant' s request.
1 - Withdrawn
1 - Incomplete and in need of additional information.
7 - To be reviewed by Staff.
Between November 29, 1982 and December 8 , 1982 , 1 application was processed
and 3 additional applications were submitted. As of December 8, 1982 , a
total of 9 planning applications were pending review. Shown below is a
summary of the applications.
COPIES TO:
ITEM NO. 6. .2
AGENDA STATEMENT - Planning Review Backlog
Page 2
PENDING APPLICATIONS (December 8 , 1982)
* PROCESSING
PROJECT APPLICATION SUBMITTED TIME TO DATE
Frumenti CUP 7/6/82 22 weeks
(Recreational Vehicle and Boat Storage)
McClure SDR 9/3/82 13 weeks
(Low Profile Sign in C-2-B-40 District)
•
HMH, Incorporated (Woodhill) Time 10/13/82 8 weeks
(Tract Map Time Extension) Extension
Armer/Norman SDR 10/18/82 7 weeks
(Accessory business sign in Agricul-
tural District)
Boyles VAR 11/4/82 4 weeks
(Carport; side yard setback variance)
City of Dublin Env.Rev. 11/8/82 4 weeks
(I580/Dougherty Road Traffic Signal)
Castle Green P.D. 11/30/82 1 week
(128 Unit residential planned developmt)
The Gregory Group (Rancho Diablo) ACUP 12/1/82 1 week
(Renewal=Sales office & model home)
Pet Prevent-A-Care CUP 12/3/82 0 week
(Outdoor pet clinic)
*
CUP = Conditional Use Permit
SDR = Site Development Review
VAR = Variance
P.D. = Planned Development
ACUP =Administrative Conditional Use Permit
ENV.REV. = Environmental Review
As shown on the information above, the 9 applications have been in pro-
cessing for an average of approximately 7 weeks to date. The median
processing time to date has been 4 weeks.
In order to provide some perspective of the planning review backlog, Staff
conducted a survey of planning activities in other Bay Area jurisdictions
including local cities and cities of similar size or development activity.
The findings of the survey are shown on the attached chart. The results
are summarized and compared to Dublin as follows:
1. Staff Size:
a. Local cities: 3 to 4 planners
AGENDA STATEMENT - Planning Review Backlog
Page 3
b. Cities of similar size or development activity: 1 to 3 planners
c. Dublin: 1 planner
2 . Approximate number of planning applications:
a. Local cities - ranges from 1 to 20 routine items per month
b. Cities of similar size or development activity - ranges from 2
to 20 routine items per month
c. Dublin - 6-7 routine items per month
3 . Processing time to hearing (or action)
a. Local cities - minimum of 32-4 weeks for routine items
b. Cities of similar size or development activity - ranges from
21-8 weeks for routine items
c. Dublin - 5-6 weeks for routine items since July 1, 1982
In addition to the survey, Staff has kept the following workload statistics
for the planning department.
Dublin Planning Activity Indicators
July 1, 1932
to Per Month Average
Dec 7, 1982
1. Phone inquiries 675 + 130 ±
2. Counter inquiries 320 - 370 60 - 70
3. Meeting with applicants/developers 55 10 - 11
4 . Council, Commission, Zoning Admin Mtgs 24 4 - 6
5 . Planning applications 35 6 - 7
6 . Completed applications 25 4 - 5
7 . Zoning approvals on bldg permit apps 202 38
8 . Reported code violations 8 1 - 2
In addition to the planning applications and the items identified above,
the Planning Director has responsibility for working on the General Plan,
ordinance review, and review of development adjacent to the City which
could have an impact on Dublin.
Improvements have been made or are in progress. These improvements are
identified below.
1. Application .Review Process: Staff has established a planning application
review process to coordinate input from police, fire, building, engin-
eering, flood control, and water and sewer. This process should improve
when the City Engineer and building inspection contractors have been hire
2 . Planning Secretary: The Planning Secretary started work on Nov 8, 1982 .
She has organized the files inherited from the County. She is currently
establishing a filing system for the new files . In addition to her
other secretarial duties, the Planning Secretary is becoming familiar
with the complexities of the Zoning Ordinance and has begun fielding
some of the routine zoning inquiries.
C
AGENDA STATEMENT - Planning Review Backlog
Page 4
3 . Microfische Reader/Printer: Staff has purchased a microfische
reader/printer. This equipment has facilitated quicker review of
past files and notification of property owners.
4 . Application Forms: Staff has prepared an application form with a
checklist of requirements .
As indicated from the statistics above, the workload of the planning
department has been quite heavy. Although workload and processing time
of planning applications is fairly comparable (with. the exception of
development of the General Plan) to those cities surveyed, the Dublin
Planning Staff size is in most cases smaller. Dublin has been able to
maintain an average processing time of 5-6 weeks only with the assistance
of a part-time planning consultant.
If Staff could be certain that development activity would continue at its
present rate, Staff would recommend that the City Council seriously con-
sider hiring an additional full-time planner. However, because of the
backlog which the City inherited from the County and the rather limited
workload data (6 months) which the City has at this time, it is Staff' s
opinion that the City should wait until fiscal year 1983-84 in order to
ascertain whether or not the level of development activity will be
maintained, before hiring an additional planner. In the interim, it is
Staff' s recommendation that the City Council authorize Staff to continue
to use the services of a part-time planning consultant on an as-needed
basis not to exceed 20 hours per week. This will enable the City to
provide a better level of service to the public. The estimated cost of
such service for the remainder of the fiscal year would not exceed $17 ,700.
The funds remaining in the Planning Department' s contract services account
is approximately $15,700 . Therefore, it is further recommended that the
City Council authorize a budget transfer of $2 ,000 from the contingent
reserve to the Planning Department contract services account.
AGENDA STATEMENT - Planning Review Backlog
ATTACHMENT
SURVEY OF PLANNING ACTIVITIES IN OTHER CITIES
12/82
AVERAGE
SIZE OF STAFF APPROX # OF PROCESSING
CITY POPULATION PLANNERS SUPPORT PLANNING APP TIME TO HEARING
LOCAL CITIES
Pleasanton 35,160 4 1 14-20 per mo: 32 wks to PC
(1 Dir. ) routine items
(3 Plan. ) major items 10-12 wks to CC
Livermore 48 ,105 3 2 1-2 routine
(1 Dir. ) items per mo. 4-6 wks to PC
(2 Plan. ) 12-18 growth 16-20 wks
mgmt items per
year
subd w/o EIR 8-12 wks
Commer/ind 4 wks
site plan
CITIES OF SIMILAR
SIZE OR DEVELOPMENT
ACTIVITY
Pinole 14 , 288 1 1 6-10 routine 4 wks
(City Plan) items per mo
Albany 15 ,130 1 2-3 routine 22 wks
(City Plan) items per mo
Morgan Hill 16 ,600 3 80 routine items 8 wks
(1 Dir) per year (6-7/mo)
(2 Plan) w/Neg Dec
(2 HCD) w/EIR 16 wks
Martinez 22 ,000 3 20 routine items 3 wks min
(1 Dir) per mo
(2 Plan) Major items 6-12 mo
(2 Intern)
(z Graphics)
Gilroy 23 ,000 3 2 7 routine items 5 wks
(1 Dir) per mo
(2 Plan) Major items 7-9 wks
Foster City 24 ,600 3 2 4-6 routine 6 wks
(1 Dir) items per mo
(2 Plan) Major items 6 wks - 6 mos
DUBLIN
13 , 496 1 1 6-7 routine items 5-6 wks *
(Plan Dir) per mo
7+wks (pending
applications)
NOTE:
1. Routine items include use permits , variances , site/design reviews .
Major items include rezonings , subdivision maps , Planned Developments ,
EIRS , items that require City Council hearing, items of controversy,
items requiring special study, items appealed.
2 . Processing time is calendar weeks (or months) to initial hearing or
action; it does not include appeal time. The time indicated is a
rough estimate of average processing time . All cities have had excep-
tional applications which have far exceeded the average processing time.
* 80% of the applications processed since 7/1/82 were processed with the
assistance of the planning consultant.