HomeMy WebLinkAboutItem 4.05 Sidewalk Safety Repair Accpt Work
STAFF REPORT CITY CLERK
File #600-35
CITY COUNCIL
DATE:October 6, 2015
TO:
Honorable Mayor and City Councilmembers
FROM:
Christopher L. Foss, City Manager
SUBJECT:
Acceptance of Work – Contract No. 15-02, Annual Sidewalk Safety Repair
Program and Curb Ramp Installation
Prepared by William Lai, Assistant Civil Engineer
EXECUTIVE SUMMARY:
The City Council will consider accepting the Annual Sidewalk Safety Repair Program and Curb
Ramp Installation project, which provided for the repair of over 3,800 square feet of damaged
sidewalk, installation of four (4) pedestrian curb ramps, and installation of new sidewalk,
driveway, and curb ramps in front of the Public Safety Complex and Alameda County Fire
District Administration Building. The project also included replacement of wood decking with
concrete surfaces at Dolan Park. In conjunction with accepting the construction work, the City
Council will consider approving a change order.
FINANCIAL IMPACT:
The City Council will consider a change order of $7,761.00 for additional sidewalk repair work.
The total project cost, including the change order, is within the approved project budget.
RECOMMENDATION:
Resolution
Staff recommends that the City Council adopt the Accepting Improvements under
Contract No. 15-02, Annual Sidewalk Safety Repair Program and Curb Ramp Installation;
approve the Change Order; and authorize the City to release retention after 35 days if there are
no subcontractor claims.
Submitted By Reviewed By
Public Works Director Assistant City Manager
DESCRIPTION:
On June 2, 2015, a contract was awarded to JD Partners, Inc. to perform the Annual Sidewalk
Safety Repair Program and Curb Ramp Installation. The annual project improves pedestrian
accessibility throughout the City by repairing damaged sidewalks, curbs, and gutters, and by
installing new curb ramps in accordance with the Americans with Disabilities Act (ADA). The
2015 project also included construction of new sidewalk, driveway, and curb ramps along the
ITEM NO. 4.5
Page 1 of 2
frontage of the Public Safety Complex. On July 21, 2015, the City Council approved a contract
change order that expanded the project to include replacement of a wood deck with concrete
surfacing at Dolan Park.
In the course of construction, City staff identified additional curb, gutter and sidewalk needing
repair at the Public Safety Complex. The replacement work was needed in order to better
conform to the new driveway. During construction the City also received reports of other
damaged sidewalk locations and staff determined some areas that warranted repair. Since the
contractor was already mobilized and sufficient funds were available in the project budget, staff
directed the contractor to complete the additional work. This work will require the approval of
Change Order #3.
The project cost summary is as follows:
Annual Sidewalk Safety Repair Program and Curb Ramp
Installation
Expenditure Budget
Current Project Budget $193,904.00
Total Budget $193,904.00
Funding Sources – General Fund
CIP CI5015 – Sidewalk Safety Repair
Program $146,972.00
CIP GI5015 – ADA Transition Plan $21,177.00
1001-7501, Parks Maintenance Budget $25,755.00
Total Funding Sources $193,904.00
Actual Expenditure
Construction Contract $113,713.00
Change Order #1 $25,755.00
Change Order #2 $19,978.65
Proposed Change Order #3 $7,761.00
Contract Services, Salary, & Testing $9,028.49
Total Expenditure $176,236.14
Remaining Balance $17,667.86
Staff has reviewed the work performed under this contract and has determined that the work is
satisfactory and complete.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
None
ATTACHMENTS:
1. Resolution Accepting Improvements under Contract No. 15-02,
Annual Sidewalk Safety Repair Program and Curb Ramp Installation
2. Change Order #3
Page 2 of 2
RESOLUTION NO. - 15
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
* * * * * * * * *
ACCEPTANCE OF WORK
CONTRACT NO. 15-02, ANNUAL SIDEWALK SAFETY REPAIR PROGRAM AND CURB
RAMP INSTALLATION
WHEREAS,
on June 2, 2015, the City of Dublin entered a contract with JD Partners to
perform Contract No. 15-02, Annual Sidewalk Safety Repair Program and Curb Ramp
Installation; and,
WHEREAS,
said improvements have been completed in accordance with plans and
specifications, and any approved modifications thereof, to the satisfaction of the City Engineer
of the City of Dublin; and
NOW, THEREFORE, BE IT RESOLVED
that the City Council of the City of Dublin does
hereby accept the improvements, Contract No. 15-02, Annual Sidewalk Safety Repair Program
and Curb Ramp Installation, and authorize Staff to file a Notice of Completion with Alameda
County.
BE IT FURTHER RESOLVED
that the City Council of the City of Dublin does hereby
authorize the City Manager or his designee to approve Change Order #3 and to release the
retention, if after 35 days of filing the Notice of Completion there are no subcontractor claims.
th
PASSED, APPROVED AND ADOPTED
this 6 day of October, 2015, by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
________________________________________
Mayor
ATTEST:
_____________________________
City Clerk
CONTRACT CHANGE ORDER
CITY OF DUBLIN
100 Civic Plaza ORDER NO: 3
Dublin, CA 94568
DATE 8-19-2015
CONTRACT CHANGE ORDER STATE
California
CONTRACT FOR: 2014-2015 Annual Sidewalk Safety Repair Program and Curb Ramp Installation COUNTY
CONTRACT NO: 15-02 Alameda
OWNER: City of Dublin
CONTRACTOR: JD Partners Concrete
CURRENT CONTRACT PRICE: $159,446.65
CURRENT CONTRACT TIME OF COMPLETION: August 20, 2015
CURRENT NO. WORKING DAYS 45
TO: JD PARTNERS CONCRETE
(Contractor)
You are hereby requested to comply with the following changes from to the contract plans, specifications, or other contract documents:
Description of Changes DECREASE INCREASE
(Supplemental Plans and Specifications Attached) in Contract Price In Contract Price
1. Additional locations which was necessary for the sidewalk to be removed and replaced
immediately.
2. Additional sidewalk in vicinity of original locations which constituted a potential trip hazard.
$ 0 $ 7,761.00
TOTALS - -
NET CHANGE IN CONTRACT PRICE $ 7,761.00
JUSTIFICATION: Additional curb, gutter, and sidewalk replacement through Dublin which constituted
potential trip hazards.
The amount of the Contract will be increased By The Sum Of: $7,761.00
The Contract Total Including this and previous Change Orders Will Be: $167,207.65
The Contract Period Provided for Completion Will Be Increased : ____0_ Days
Contract Completion
Date 8/20/2015
Upon execution by representatives authorized to bind the parties, this Change Order will become a part of the contract. The consideration specified in this
Change Order (whether an adjustment of the contract price, an adjustment of time, and/or other consideration) is the full and sole compensation owed to the
contractor as a result of the changes and issues described in this Change Order. Such consideration includes, but is not limited to, any and all direct and indirect
costs incurred by the contractor as a result of the changes and issues described in this Change Order for any labor, equipment, materials, overhead (additional,
extended, field and home office), profit, or time adjustments. By signing this Change Order the contractor waives and releases the owner from any and all claims
for additional compensation concerning any of the changes and issues specified in this Change Order.
The undersigned, being the ________________________________ (Title) of the Contractor, by signing this Changer Order declares under penalty of perjury under
the laws of the State of California, and does personally certify and attest that: the undersigned has thoroughly reviewed the attached request for change order
and knows its contents, and said request for change order is made in good faith; that it is supported by truthful and accurate data; that the amount requested and
the additional time requested accurately reflect the allowable expenses that would be incurred, and the time necessary, to perform the change order; and further,
that the undersigned is familiar with California Penal Code Section 72 and California Government Code Section 12650 et seq., pertaining to false claims, and
further knows and understands that the submission or certification of a false claim may lead to fines, imprisonment, or other severe legal consequences.
Requested __________________________________________________
(City) (Date)
Recommended _______________________________________________
(Public Works Director) (Date)
Accepted ____________________________________________________
(Contractor) (Date)
Approved by Agency ____________________________________________
(City Manager) (Date)