Loading...
HomeMy WebLinkAbout4.08 Civic Center Contract Change Order CITY OF DUBLIN AGENDA STATEMENT CITY COUNCIL MEETING DATE: August 8, 1988 SUBJECT Civic Center Project - Contract Change Order EXHIBITS ATTACHED Contract Change Order No. 3 V_) RECOMMENDATION Approve Contract Change Order No. 3 and authorize City Manager to execute same. FINANCIAL STATEMENT: Amount of Change Order is $31,562. Sufficient funding is included in the Civic Center Project Budget to cover this change. DESCRIPTION The adopted City Council policy on change orders requires that the City Council review all changes greater than $25,000. The approved Civic Center Budget included a 5% contingency for changes occuring during the course of construction. The contract change order results from the requirement for the grading subcontractor to remove and recompact soil beneath the building pad. Among the requirement was the need to remove the soil 5 ' in depth and 10' outside the building perimeter. The basic intent was to remove any fill dirt and to reach the native soil . During the grading operations , representatives of Peter Kaldveer & Associates , were on site to inspect on behalf of the City. This firm provided the geotechnical services used in the design of the project. The engineers felt that it was important to provide a minimum of 3 ' of engineered fill under the footings in all locations . Once the building pad was excavated and the elevation of native soil determined, it became apparent that excavation in excess of 5 ' would need to be performed to provide appropriate fill in some areas . The need for this additional excavation further complicated the clarity of the original scope of work. Harris & Associates , acting as the City' s Construction Manager, coordinated the interpretations submitted by the designers and the contractor. The outstanding issue was whether the contractor should have reasonably known that the subexcavation was required by reviewing the bid documents . Staff believed the circumstances presented ambiguity in sufficient depth to warrant a negotiated settlement for . the additional work. Harris & Associates maintained detailed logs on the labor and equipment utilized on the work in question. The Construction Manager also reviewed the submitted cost for its conformity with time sheets and prevailing industry rates . The change order does not provide for any extension in the amount of time required to complete the project, although an 8 day extension was requested by the contractor. The contractor was unable to demonstrate through a revision to the project schedule that the additional work impacted the critical work which was scheduled during that period. .: A summary of the change order negotiations is attached to the Change Order. Staff recommends that the City Council approve the change order and authorize the City Manager to execute the document. COPIES TO: ITEM NO. t, 48 DUBLIN _CIVIC CENTER • CONTRACT CHANGE ORDER NO. 3 DATE: May 27 , 1988 OWNER: City of Dublin Mr. Richard Ambrose . . 40/12 (415 ) 826-4900 � CONTRACTOR: Dickman-Nourse, Inc. : Mr. Henry K. Nourse, III 4\ \��5 (415 ) 967-7866 3 -ivz- CONSTRUCTION Harris & Associates . MANAGER: Ms. Susan Hyler (415 ) 828-1571 ARCHITECT: George Miers & Associates Mr. William Hoffmann (415 ) 986-0305 • I . DESCRIPTION OF CHANGE: The Contractor was required to 'subexcavate under the building pad and ten foot outside the building perimeter from existing fill subgrade to native soil , as determined by Kaldveer Associates with on-site • inspection during excavation. Overall , the Contractor - was required to excavate to a minimum of 327 . 5 in the southern area of the Council Chambers and Police Facility to provide a minimum of three feet of engineered fill under the footings in all locations . This was required because the native soil was very shallow at the southern end and site conditions did not provide the minimum engineered fill as required for the design of the building. This requirement could not have been determined until the building pad had been excavated for and the,_ elevation of the native determined. The additional excavation requirement further complicated the clarity of the original scope of work. Once excavated, the Contractor had to bring the building pad back to the existing subgrade with suitable native soil or engineered . fill with 90% compaction as required by the specification. II . JUSTIFICATION OF CHANGE: The Construction Manager and the Design Team reviewed the Contractor' s request and offered the. City • staff interpretations of the request. The City staff in • consultation with the City Attorney' s office determined that Contract Change Order No . 3 - City of Dublin Page 1 • it would be equitable to proceed with negotiations. The City' s original opinion on this issue was that the subexcavation was part of the contract work. However, after discussions with the City Attorney' s office and a review of the estimated costs to do the work, it was determined that it did not appear the Contractor included the cost to do this work in their bid. This determination was made from the costs provided in the cost loaded construction schedule. The City decided to pursue an equitable settlement for the work performed, since the inclusion of the work in the original scope was somewhat ambiguous . The subcontractor had also indicated that legal proceedings were likely to be pursued if agreement was not reached. III . COST OF CHANGE: Subexcavation of the Building Pad: -TOTAL THIS CHANGE $31 , 562 .00 IV. ADJUSTMENTS IN CONTRACT AMOUNT: A. Original Contract $9 , 695 ,000 B. Previous Change Orders 16 ,094 C . Current Contract $9 , 711 , 094 D. This Change Order $ 31 , 562 E. New Contract Amount $9, 742 ,656 V. ADJUSTMENTS IN CONTRACT COMPLETION: A. Original Duration: 440 Calendar Days B. Original Completion Date : April 10 , 1989 C . Previous Extension: -0- D. Current Duration: 440 Calendar Days E. This Extension: -0- F. New Duration: 440 Calendar Days G. New Completion Date : April 10 , 1989 VI . CONDITIONS OF CHANGE ORDER: It is understood and agreed that this Change Order provides full compensation to the Contractor for all claims arising out of the changes constituting the subject matter of this Change Order and that this Change Order is pursuant to and in accordance with other relevant provisions, conditions and requirements contained in the Contract Documents . Contract Change Order No . 3 - City of Dublin Page 2 • r ' / ACCEPTED: RECOMMENDED FOR ACCEPTANCE: CONTRACTOR: CONSTRUCTION MANAGER: Dickman-Nourse, Inc. Harris : Associate By: i� '� '` 4 /Vt"CCL.,--i.,, By: Ai,axl& 46 Henry A. Nourse, III Susan Hy lrr Date: ii-// rg Date: 54:71' 6 OWNER: ARCHITECT: City of Dublin George Miers & Associates By: By: Richard Ambrose William Hoffmann Date: Date: Contract Change Order No . 3 - City of Dublin Page 3 • • • SUMMARY OF NEGOTIATIONS: • Dickman-Nourse, Inc . in their letter No. 102 , dated 3/24/88 , provided a compilation of the time and material sheets signed by Harris & Associates plus 10% for the costs associated with Joe . Foster Excavating' s work. To this number they added additional layout time and field supervision and their allowed 5% markup for a total of $34 ,105 . 00 . • Harris & Associates met ,with Dickman-Nourse, Inc. and Joe Foster Excavating on May 23 , 1988 to 'discuss the subexcavation of the ' building pad and the costs as presented in DNI ' s letter No . 102 . We reviewed the time and materials sheets presented by Foster and which had been signed by a Harris & Associates' representative during the work to verify the labor and equipment used to do the disputed work. The hours used by Foster were as agreed to and the labor rates were comparable to those calculated by- Harris & Associates , and the equipment rates were well below the maximum rates as allowed by the Contract Documents. It was agreed to accept the costs as submitted by Joe Foster Excavating for their work in doing the subexcavation of the building pad. Harris & Associates , however, objected to the cost . included by DNI to revise the CPM schedule, since the ' schedule has not been revised. In addition, Harris & Associates objected to the field supervision being charged, since these costs are included in the overhead percentage. We did agree to allow eight ( 8 ) hrs for supervision on Sunday February 7 , 1988, since the assistant superintendent was on site and is a working foreman which is allowed to be charged in addition to overhead. We agreed to delete the charge of $100 for revising the CPM schedule and charge eight ( 8 ) hrs at $55/hr for the field supervision on Sunday. The total revised and agreed to price for this change order was $31 , 562 . In DNI ' s letter No . 102 , they requested that an eight ( 8 ). day time extension be granted for this change. Harris & Associates indicated to DNI that in order for a time extension to be considered they needed to submit a time analysis as: specified in Section 1310 , Part 4 , Time Impact Analysis For Changes, Delays , Time Extensions, and Contractor Requests. Harris & Associates also indicated that a time analysis verifying that the job was delayed would be difficult to produce, since the structural steel was the critical activity which was not delayed. • • •