HomeMy WebLinkAbout4.06 Dolan Park Improvements No. 88-2 CITY OF DUBLIN
AGENDA STATEMENT
City Council Meeting Date: May 22, 1989
SUBJECT: Acceptance of Work - Contract No. 88-2
Dolan Park Improvements, Phase 2
EXHIBITS ATTACHED: None.
RECOMMENDATION: ..i '''1) Accept improvements under Contract 88-2
y" (jk2) Authorize final payment and retention in the
amount of $15,242.90 to Mori Hatsushi and
Associates.
FINANCIAL STATEMENT:
BUDGET ACTUAL
(TOTALS FOR PHASES I AND II)
Design/Inspection $ 62,620 $ 65,871
Construction 602,475 562,967
Utility Fees (incl. in construction budget) 28,060
Misc. (legal,
printing, postage) (incl. in construction budget) 3,924
Land Acquisition 454,660 454,660
Total: $1,119,755 $1,115,482
FOR FY 1988-89
BUDGET $215,000
ACTUAL $149,549
The total combined phased project is $4,273 under budget and the
expenditures for 1988-89 are also under budget. No transfer of funds is
needed.
DESCRIPTION:
The land for this park was acquired through parkland dedication by the
developer of Tract 5402 (one acre) and purchase of four acres from the
Murray School District.
Phase I of Dolan Park improvements was constructed by Valley Crest Landscape
under City of Dublin Contract 87-7. Construction of Phase I was completed
in the spring of 1988.
In April of 1988, the City Council awarded Contract 88-2 Dolan Park
Improvements Phase 2 to Mori Hatsushi and Associates.
This contract completes the work at Dolan Park, which included grading,
drainage, lawn and irrigation, a children's play area, a sports court, a
parcourse, a group picnic area, a day camp and shelter, pathways, and
pathway lighting.
The City Engineer has reviewed the work on Phase II of the project and
determined that it is complete and in accordance with the approved plans and
specifications. Staff recommends that the City Council accept the
improvements and authorize payment of the final invoice and retention to
Mori Hatsushi and Associates in the amount of $15,242.90.
7
ITEM NO. , ': (Tj� COPIES TO: Mori Hatsushi & Assoc.