AGENDA STATEMENT
CITY COUNCIL MEETING DATE: October 30, 1989
SUBJECT: PA 87-031 East Dublin Studies:
- Second Amendment to the Agreement between the City
and Wallace Roberts & Todd for Consultant Services to
complete additional work on the East Dublin Studies
- Second Amendment to the Agreement between the City
and sponsoring property owners for payment of a portion
of the cost to complete additional work on the East
Dublin studies
REPORT PREPARED BY: Rod Barger Senior Planner
EXHIBITS ATTACHED:
Exhibit A: Draft Resolution approving the Second
Amendment to Agreement for Consultant Services between
the City and WRT.
Exhibit B: Draft Resolution approving Second Agreement
Amendment between the City and sponsoring property
owners.
Attachment 1: Draft Second Amendment to the Agreement
for Consultant Services for preparation of the East
Dublin General Plan Amendment Study, Specific Plan and
EIR.
Attachment 2: Draft Second Amendment to the Agreement
between the City and sponsoring property owners for
payment of a portion of the costs of the East Dublin
General Plan Amendment Study, Specific Plan and EIR.
Attachment 3 : Summary of General Plan Amendment cost
to complete additional technical services and task
revisions
Attachment 4: Total East Dublin sponsoring property
owner costs as of October 30, 1989.
RECOMMENDATION:
iF 1) Review agreements.
2) Adopt resolution approving Second Amendment to the
Agreement between the City and Wallace Roberts &V
Todd.
3) Adopt Resolution approving Second Amendment to the
Agreement between the City and sponsoring property
owners.
4) Authorize City Manager to sign the agreements
between:
a) the City and Wallace Roberts & Todd;
b) the City and sponsoring property owners;
all of which should occur after monies have been
received from sponsoring property owners paying
for the additional work.
FINANCIAL STATEMENT: See discussion below
T�
ITEM NO. _, ,
COPIES: East Dublin Sponsoring
.�,�„
Property Owners
File PA 87-031
-1- [a:RB10-30/87-031]
DESCRIPTION:
BACKGROUND
On September 19, 1989, a meeting was held between Staff, WRT and
East Dublin sponsoring property owners. The purpose of this
meeting was to review and discuss the East Dublin Preliminary
Draft General Plan Land Use Alternatives and Policies. During
the meeting, the sponsoring property owners indicated several
concerns with the content of the preliminary draft land use
alternatives and policies. They identified portions of the
alternatives and policies which they felt were impractical or
unworkable.
They wanted to see more refined alternatives, with increased
yields in some areas and reduced yields in others. They
requested that Staff have WRT revise the documents to produce
more workable alternatives, and they identified the types of
development policies they wanted considered.
At this meeting, the property owners also requested that the
various subcontracting consultants be available at all future
sponsoring property owner meetings to answer technical questions
associated with the work produced. The property owners also
requested that technical work sessions be held. At these
sessions, Staff, WRT, the various subcontractor consultants and
the sponsoring property owners would meet to share and discuss
information important to the production of the General Plan
Amendment.
The addtional work requested by the property owners is not
covered in existing agreements. In order to accommodate their
requests, new agreement amendments must be entered into.
COST FACTORS
The existing agreements between the City and WRT do not include
provisions for more refined General Plan Land Use Alternatives.
Minor modifications were anticipated, but not revisions to the
extent of new and different alternatives, as requested by the
property owners. The existing agreements also do not include
provisions for technical work sessions with sponsoring property
owners at which the various subconsultants were to attend. The
additional cost to cover these items are as follows:
More Refined General Plan Land Use
Alternatives $ 7,592. 00
Technical Meetings $ 7,808.00
Sub-consultants at Sponsoring Property
Owner Meetings $ 11,100. 00
TOTAL $ 26,500.00
THE AGREEMENT AMENDMENTS
Two separate agreement amendments are attached for your review.
Please refer to Attachments 1 and 2. Each of those agreements
must be entered into prior to having WRT and the sub-consultants
perform the additional work. It is recommended that the Council
review Attachments 1 and 2 (the agreements) and adopt Exhibits A
and B, resolutions approving the agreement amendments. In
addition, it is recommended that the Council authorize the City
Manager to sign the agreement amendments. These signings are to
occur after monies have been received from sponsoring property
owners to pay for the additional work.
-2-
It should be noted that of the fourteen different sponsoring
property owners, nine have decided to participate in paying for
their proportional share of the cost to do the additional work.
Approximately $12, 854 remains unsponsored. Typically, the City' s
policy has been to have sponsoring property owners pay for these
unsponsored costs. Attachment 3 provides a breakdown of these
costs.
The additional work applies to the General Plan. Sponsoring
property owners paying for additional work are doing so
voluntarily. There will not be any reimbursement of these costs
since they are applicable to the general plan amendment study.
Finally, with respect to the $50,000 of Staff time the Council
donated to this study, a review by the Finance Director shows
that we are close to or already have exhausted these funds.
Unless otherwise instructed, once the $50,000 is expended, the
sponsoring property owners will be responsible for paying any
additional Staff cost incurred.
-3-
RESOLUTION NO. - 89
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
A RESOLUTION APPROVING SECOND AMENDMENT TO AGREEMENT (EAST DUBLIN)
WHEREAS, the City Manager has presented an Agreement entitled "SECOND
AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES FOR PREPARATION OF THE EAST
DUBLIN GENERAL PLAN AMENDMENT STUDY, SPECIFIC PLAN STUDY AND ENVIRONMENTAL
IMPACT REPORT" ; and
WHEREAS, the City Council is familiar with the provisions of said
Agreement.
NOW, THEREFORE, the City Council does resolve as follows:
The City Council approves said Agreement and authorizes the City Manager
to execute said Agreement.
PASSED, APPROVED AND ADOPTED this 30th day of October, 1989.
AYES:
NOES:
ABSENT:
Mayor
ATTEST:
City Clerk
1011BITA
RESOLUTION NO. - 89
•
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
A RESOLUTION APPROVING SECOND AMENDMENT TO AGREEMENT (EAST DUBLIN)
WHEREAS, the City Manager has presented an Agreement entitled "SECOND
AMENDMENT TO AGREEMENT BETWEEN THE CITY OF DUBLIN AND THE SPONSORING PROPERTY
OWNERS FOR PAYMENT OF A PORTION OF THE COSTS OF THE EAST DUBLIN GENERAL PLAN
AMENDMENT STUDY, SPECIFIC PLAN STUDY AND ENVIRONMENTAL IMPACT REPORT" ; and
WHEREAS, the City Council is familiar with the provisions of said
Agreement.
NOW, THEREFORE, the City Council does resolve as follows:
The City Council approves said Agreement and authorizes the City Manager
to execute said Agreement.
PASSED, APPROVED AND ADOPTED this 30th day of October, 1989.
AYES:
NOES:
ABSENT:
Mayor
ATTEST:
City Clerk
-3- i
SECOND AMENDMENT TO AGREEMENT FOR CONSULTANT SERVICES
FOR PREPARATION OF THE EAST DUBLIN GENERAL PLAN AMENDMENT STUDY,
SPECIFIC PLAN STUDY AND ENVIRONMENTAL IMPACT REPORT
WHEREAS, the City of Dublin ("The City") and Wallace Roberts & Todd
("The Consultants") are parties to an agreement entitled "Agreement for
Consultant Services for Preparation of the East Dublin General Plan Amendment
Study, Specific Plan Study and Environmental Impact Report" , dated August 5,
1988, which agreement was amended by the First Amendment to Agreement for
Consultant Services for Preparation of the East Dublin General Plan Amendment
Study, Specific Plan Study and Environmental Impact Report, (the "Agreement") ;
and
WHEREAS, additional technical services and preliminary draft General
Plan Land Use Alternative revisions are necessary for completion of the work
to be performed under the Agreement; and
WHEREAS, The City and The Consultant desire to amend the Agreement;
NOW, THEREFORE, The City and The Consultant agree to amend the Agreement
as follows:
A. Exhibits "A" and "A-1" are amended by adding thereto the work set
forth on Exhibit "A-2" attached hereto and incorporated herein, to be included
within the scope of work.
B. Paragraph III is amended by deleting the sum of $571,833 and
adding in its place the sum of $598,333.
Except as expressly set forth herein, the Agreement shall remain in full
force and effect.
In witness whereof, the parties hereto have caused this Second Amendment
to the Agreement to be executed the day and year first written below.
The City of Dublin
(a Municipal Corporation)
By:
Richard C. Ambrose, City Manager
Date:
Wallace Roberts & Todd
By:
Title:
Date:
• 3
SCOPE OF WORK AND COSTS FOR ADDITIONAL TECHNICAL SERVICES AND PRELIMINARY
DRAFT GENERAL PLAN LAND USE ALTERNATIVE REVISIONS (EAST DUBLIN)
A. Revision to Preliminary Draft General Plan Land Use Alternatives
Revisions to the East Dublin preliminary Draft General Plan Land Use
Alternatives and Policies (submitted to the City of Dublin on September
8, 1989 by Wallace Roberts and Todd) are necessary. The revised
alternatives will be as follows:
1. The No-Project Alternative: The new Alternative 1 will follow the
same pattern and goals of the original Alternative 1 (as
previously submitted to the City by WRT on 9/8/89) . It will
include any possible increase in residential holding capacity
consistant with all existing General Plan policies. Holding
capacity would likely be in the 8000+ dwelling unit range.
2. The Medium Intensity Alternative: The new Alternative 2 would be
based on the patterns and goals established in the previous
Alternatives 1 and 2 (as previously submitted to the City by WRT
on 9/8/89) . It will adhere to existing General Plan policies
except in the area of mass grading. Holding capacity would likely
be in the 13,000 to 17,000 dwelling unit range.
3. The Medium-High Intensity Alternative: The new Alternative 3
would combine elements of the previous Alternatives 2 and 3 (as
submitted to the City by WRT on 9/8/89) . It will achieve a
holding capacity in the range of 17,000 to 19,000 dwelling units.
COST - $7,592
B. Technical Services at Sponsoring Property Owners Meetings
In order to provide additional technical services to sponsoring property
owners, WRT's subconsultant representatives will attend all future
sponsoring property owner meetings as deemed necessary by City Staff.
This includes Alison Massa of WRT, together with one to three WRT
subconsultant staff members, plus, at those meetings concerning the
specific plan, attendance by a WRT Assistant Planner.
COST - $11,100
C. Technical Coordination Meetings:
In order to provide additional technical services to sponsoring property
owners, two technical coordination meetings will be held. These
meetings will be attended by Alison Massa of WRT, a WRT Assistant
Planner, at least four WRT subconsultant staff as well as City Staff.
All sponsoring property owners and their subconsultants may attend each
session.
Eliiiialge""Rialialkizsiti.fte pi
A rr.LN A-me: i 1_C
AE-
• - NNE �?�;I�1 +
The first session will examine infrastructure needs including
feasibility, timing, probable costs, cost allocation.
The second session will address traffic, circulation and traffic model
assumptions, and the effect of increased residential capacities on
traffic volumes as related to each project alternative.
COST - $7,808
TOTAL ADDITIONAL COST - $26,500
•
SECOND AMENDMENT TO AGREEMENT BETWEEN THE CITY OF DUBLIN
AND THE SPONSORING PROPERTY OWNERS FOR PAYMENT OF A PORTION OF THE COSTS
OF THE EAST DUBLIN GENERAL PLAN AMENDMENT STUDY, SPECIFIC PLAN STUDY AND
ENVIRONMENTAL IMPACT REPORT
WHEREAS, ("the Property Owner") and the
City of Dublin ("The City") are parties to an agreement entitled "Agreement
between the City of Dublin and the Sponsoring Property Owners for Payment for
a Portion of the Costs of the East Dublin General Plan Amendment Study,
Specific Plan Study and Environmental Impact Report, " which agreement is dated
, and was amended by the First Amendment to Agreement
Between the City of Dublin and the Sponsoring Property Owners for Payment of a
Portion of the Costs of the East Dublin General Plan Amendment Study, Specific
Plan Study and Environmental Impact Report, dated
("Agreement") ; and
WHEREAS, additional professional services are required for the purposes
of preparing the General Plan Amendment Study and Environmental Impact Report
("EIR") ; and
WHEREAS, the total costs of such additional services is $26,500; and
WHEREAS, because this Amendment relates only to costs for the General
Plan Amendment and EIR, the agreement of all Sponsoring Property Owners is not
required to the amendments set forth herein; and
WHEREAS, the Property Owners and The City hereby agree to amend the
Agreement as follows:
A. Section 2 is amended by deleting Section 2 and adding Section 2 to
read as follows:
2. Payment to the City. The Property Owner will pay The City the
following amounts as its proportional share of the cost of preparing the
General Plan Amendment, the Specific Plan, the Environmental Impact Report and
related documents as more fully described above:
General Plan
(The Property Owner's property only) $
Supplemental General Plan
(Geotechnical and biological) $
Supplemental General Plan (2)
(Additional Technical Services and
Task Revisions) $
ATIACHMENT
Additional General Plan Costs
(The Property Owner's proportional
share of the costs ascribed to the
parcels owned by non-participating
property owners) $
Total $
B. Section 3 is amended by adding thereto the following sentence:
"The sum indicated in paragraph 2 as "Supplemental General Plan (2)
(Additional Technical Services and Task Revisions)" is Property Owner' s
proportionate share of $26,500 and shall be paid by the Property owner to the
City within twenty (20) days of execution of this Amendment. "
Except as expressly amended, the Agreement shall remain in full force
and effect.
The Property Owner The City of Dublin
(a Municipal corportion)
By: By:
Richard C. Ambrose, City Manager
Printed Name:
Date: Date:
GENERAL PLAN AMENDMENT COST
TO COMPLETE ADDITIONAL TECHNICAL SERVICES
AND TASK REVISIONS
NON-SPONSORED TOTAL
SPONSOR SPONSOR COST SHARE COST ADDITIONAL COST
Alameda County $ 3,437 $ 3,238 $ 6,675
Crosby/Bank of the West 668 631 1,299
Doolan East Assoc/D.Wilson 3,169 2,985 6,154
Doolan West Assoc. 1,108 1,044 2,152
Fallon Investors 554 522 1,076
Chang Su-O-Lin et al 3,318 3,123 6,441
Mission Peak Homes 245 230 475
Pappas 572 538 1,110
Redgwick Construction 575 543 1,118
TOTAL $13,646 $12,854 $26,500
There will not be any reimbursement of General Plan costs
All ;
[summary costs:10/26/89] `'
Paw"
,e.
TOTAL EAST DUBLIN PROPERTY OWNER COSTS AS OF OCTOBER 30, 1989
Original* Addtn'l General* Addtional**
General Plan* Additional Plan Costs for Specific Plan* Additional* General Plan t
(Property Owners General Geotechnical and (Property Owners Specific Technical
Property Only) Plan Costs Biological Work Property Only) Costs Services Costs TOTAL
Alameda County $32,483 $ -0- $17,411 $67,796 $12,520 $ 6,675 $136,885
;rosby/Bank of the West 6,309 5,639 3,384 -0- -0- 1,299 16,631
loolan East Assoc./D.Wilson 29,942 26,704 16,053 -0- -0- 6,154 78,853
loolan West Assoc. 10,465 9,336 5,612 -0- -0- 2,152 27,565 RIPIC
'all -nvestors 5,257 4,673 2,813 11,395 2,018 1,076 27,232
;han -0-Lin et al 31,344 27,946 16,793 65,397 12,073 6,441 159,994
fission Peak Homes 2,311 2,064 1,235 4,823 890 475 11,798
'appas 5,408 4,827 2,899 11,271 2,080 1,110 27,595
tedgwick Construction 5,433 4,848 2,914 11,345 2,096 1,118 27,754
'MI/Dublintown Ltd.*** 4,631 4,118 2,479 9,646 1,780 -0- 22,654
inderson*** 1,677 1,489 -0- 3,474 642 -0- 7,282
franaugh*** 1,352 1,212 -0- 2,824 525 -0- 5,913
'. Lin *** 10,390 9,274 -0- 21,691 4,008 -0- 45,363
;ighetti*** 1,677 1,458 -0- 3,474 601 -0- 7,210
TOTAL $148,679 $103,588 $71,593 $213,136 $39,233 $26,500 $602,729
•
*This column represents existing costs covered under previous agreements.
**This column represents additional costs to be covered under second agreement amendment to pay for additional technical services and
amendments to the preliminary draft general plan land use alternatives.
E**Represents sponsoring property owners that chose not to participate in the additional General Plan costs for the additional technical -
services and amendments to the preliminary draft general plan land use alternatives.
[summary costs:10/26/89]