Christopher L. Foss, City Manager J
Project Clover (IKEA) Status Report and Consideration of a Consulting Services
Agreement for CEQA services (PLPA- 2016 - 00016)
Prepared by Kristi Bascom, Principal Planner
EXECUTIVE SUMMARY:
The City Council will receive an overview of a new retail shopping center proposed for the 27.5 -
acre site formerly known as "The Green ", south of Martinelli Way between Arnold Road and
Hacienda Drive. The proposed project, currently referred to as "Project Clover', is proposed to
be comprised of a 377,479- square -foot IKEA retail store, a 75 -room hotel or 16,400- square -foot
retail building (either one or the other), and three additional buildings with up to 19,600 square
feet of retail and restaurant uses. The City Council will also consider approving a Consulting
Services Agreement with FirstCarbon Solutions (FCS), an environmental consulting firm, to
prepare a Supplemental Environmental Impact Report (SEIR) for the proposed project. The
SEIR shall be completed in accordance with the California Environmental Quality Act, for an
amount not to exceed $377,850 (project budget amount of $343,500 plus additional 10%
contingency fund to be spent only with authorization of the City).
FINANCIAL IMPACT:
There is no financial impact to the City. All costs associated with the contract to prepare the
Supplemental Environmental Impact Report, if authorized by the City Council, would be borne
by the Applicant. The tasks described in the Scope of Work will not begin until the Applicant has
funded the developer deposit account to pay the cost of the contract.
RECOMMENDATION:
Staff recommends that the City Council receive the project overview and adopt the Resolution
Approving a Consulting Services Agreement with FirstCarbon Solutions (FCS) to Prepare a
Supplemental Environmental Impact Report for the Project Clover (IKEA) Retail Center and
Authorizing the City Manager to Sign the Agreement on Behalf of the City.
Submitted By Reviewed By
Community Development Director Administrative Services irector
Page 1 of 4 ITEM NO. 8.2
DESCRIPTION:
The vacant 27.5 -acre project site is located at the southwest corner of Hacienda Drive and
Martinelli Way (Figure 1 below). The project site has General Plan and Eastern Dublin Specific
Plan land use designations of "General Commercial ". The land use designation accommodates
a range of regional and community serving retail, service, and office uses. The site has Planned
Development Zoning (Ordinance 34 -08). The existing Planned Development Zoning District
was approved in 2008, and allows the development of a 305,000- square -foot commercial
center.
Entitlements for several previous projects have been considered for this property, including the
original IKEA project approved by the City Council in 2004, which permitted the development of
a 317,000- square -foot IKEA store on the westerly portion of the site and a 137,000- square -foot
retail shopping center on the easterly portion of the site. Construction of the project did not
proceed. In 2008, the property owners proposed a different commercial project on the site,
which was a 305,000- square -foot retail center. Referred to as "The Green on Park Place," the
project was expected to be anchored by a grocery store and have several other larger retail
tenants. Due to the timing of the project at the beginning of the economic downturn, this project
did not move forward either. Lastly, in 2013, the property owners filed an application for a
General Plan and Eastern Dublin Specific Plan amendment to allow a mixed -use (commercial
and residential) project on the site. "The Green" project proposal was for up to 400 medium -
high density residential units and up to 40,000 square feet of retail and restaurant uses. The
City Council did not approve the request when it was presented in 2014, and the project did not
move forward.
Figure 1: Vicinity Map
W�1' ' , U_ ,
* 4
F�
Martinelli Way
Project Site
■ ;.:�
Page 2 of 4
R:
Greenberg Farrow Architects has submitted a pre - application for a retail shopping center that
would be anchored by an IKEA store and would include four additional buildings with yet- to -be-
named tenants. The pre - application includes the following proposed buildings:
• 377,479- square -foot IKEA store;
• 3,600- square -foot retail building;
• 8,000- square -foot retail building;
• 8,000- square -foot restaurant building; and
• 75 -room hotel or a 16,400- square -foot retail building.
The preliminary site plan is included as Attachment 1 to this Staff Report for reference purposes.
A detailed review of the proposed project has not yet begun, and will commence when the
Applicant proceeds with filing a formal application, which is expected to occur in the near future.
However, the proposed retail commercial, restaurant and hotel uses appear to be consistent
with the General Plan /Specific Plan land use designation of General Commercial. Therefore, it is
not anticipated that the proposed project would require any amendments to the General Plan or
Eastern Dublin Specific Plan.
Future project applications are anticipated to include a Planned Development Zoning Stage 2
Development Plan, Site Development Review Permit, Tentative Map to divide the site into
smaller parcels, a Master Sign Program, and a Supplemental Environmental Impact Report.
These future entitlements would require public hearings and review and approval by the
Planning Commission and City Council.
In order to begin the environmental analysis of the proposed project, Staff prepared a Request
for Proposals (RFP) to solicit a qualified consultant to prepare a Supplemental Environmental
Impact Report (SEIR). FirstCarbon Solutions (FCS) submitted a proposal that Staff reviewed.
After engaging with FCS in a discussion about the work tasks, schedule, and corresponding
budget, Staff is recommending approval of the consultant group and the Scope of Work.
The cost of the contract with FirstCarbon Solutions to prepare the SEIR is not to exceed
$377,850 (project budget amount of $343,500 plus additional 10% contingency fund to be spent
only with authorization of the City). This budget figure covers the preparation of the
Supplemental Environmental Impact Report as described in the Scope of Work (Exhibit A to
Attachment 2). The Resolution (Attachment 2) approving the Agreement contains a provision to
allow an additional 20% increase to the scope and budget, should the City and Applicant agree
that additional tasks are necessary to successfully complete the SEIR.
The consultant team has provided a complete list of all public and private clients for which FCS
is currently working, which is shown on pages 28 -32 of the proposed scope of work (Exhibit A to
Attachment 2). The cost to prepare the SEIR, as described in the Scope of Work, will be wholly
paid for by the Applicant (including any scope /budget increases agreed to by the Applicant).
The development of the Supplemental Environmental Impact Report is expected to take
approximately twelve months. Adherence to this timeline assumes that the Applicant will work
closely with the City to reach key milestones throughout the project's duration.
Page 3 of 4
During the processing of the requested entitlements and preparation of the SEIR, Staff will
schedule a Study Session with the Planning Commission and provide a project update to the
City Council.
NOTICING REQUIREMENTS /PUBLIC OUTREACH:
Although a public notice is not required to receive a project update or approve a Consultant
Services Agreement, City Staff published and mailed a courtesy notice to all properties with 1,000
feet of the project site notifying them of this pubic meeting. Because the 1,000 foot radius touched
a portion of both the Esprit townhome development and the Archstone apartments on the
northeast corner of Dublin Blvd. and Hacienda Drive, notices were sent to all residents and owners
within the entire development.
ATTACHMENTS: 1. Preliminary Site Plan
2. Resolution Approving a Consulting Services Agreement with
FirstCarbon Solutions (FCS) to prepare a Supplemental
Environmental Impact Report for the Project Clover (IKEA) Retail
Center and Authorizing the City Manager to Sign the Agreement on
Behalf of the City (Consulting Services Agreement and Scope of
Work attached as Exhibit A)
Page 4 of 4
RESOLUTION NO. xx-16
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
_____________________________________________________
APPROVING A CONSULTING SERVICES AGREEMENT WITH FIRST CARBON
SOLUTIONS TO PREPARE A SUPPLEMENTAL ENVIRONMENTAL IMPACT REPORT FOR
THE PROJECT CLOVER (IKEA) RETAIL CENTER AND AUTHORIZING THE CITY
MANAGER TO SIGN THE AGREEMENT ON BEHALF OF THE CITY
WHEREAS,
Greenberg Farrow Architects submitted a pre-application for the
development of a new retail center on 27.5 acres in the Easter Dublin Specific Plan area at the
intersection of Hacienda Drive and Martinelli Way; and
WHEREAS,
City Staff solicited bids from qualified consultants to prepare the necessary
environmental documentation in accordance with the California Environmental Quality Act
(CEQA) to analyze the impacts of the proposed project, which, in concept, will be comprised of
a 377,479 square foot IKEA retail store, a 75-room hotel or 16,400 SF retail building (either one
or the other), and three additional buildings with up to 19,600 square feet of retail and restaurant
uses; and
WHEREAS,
FirstCarbon Solutions prepared a detailed scope of work and fee proposal to
prepare a Supplemental Environmental Impact Report for the proposed project that was best
suited to the needs of the project; and
WHEREAS
, FirstCarbon Solutions has shown that they have the ability to perform the
planning and environmental consulting services required; and
WHEREAS
, a budget not to exceed $377,850 (project budget amount of $343,500 plus
additional 10% contingency fund to be spent only with authorization of City) has been
established for the Supplemental Environmental Impact Report. Furthermore, in the event that
both the City and the Applicant agree that additional tasks are necessary to successfully
complete the SEIR, the City Council authorizes the City Manager to approve an increase to the
scope and budget not to exceed 20%; and
WHEREAS
, FirstCarbon Solutions will perform the work outlined in the Scope of Work
and Fee Proposals once the contract is executed and once the Project Applicant has funded the
Developer Deposit Account to complete the work described in the Scope of Work; and
WHEREAS
, all costs associated with the preparation of the Supplemental Environmental
Impact Report shall be borne by the Applicant; and
NOW, THEREFORE, BE IT RESOLVED
that the City Council of the City of Dublin does
authorize the City Manager to execute a Consulting Services Agreement with FirstCarbon
Solutions, attached hereto as Exhibit A to prepare a Supplemental Environmental Impact Report
for a fee not to exceed $377,850 (project budget amount of $343,500 plus additional 10%
contingency fund to be spent only with authorization of City).
th
PASSED, APPROVED AND ADOPTED
this 15 day of March, 2016, by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
__________________________________
Mayor
ATTEST:
City Clerk
Project Clover/IKEA Status Report
CEQA Consulting Services Agreement
City Council
March 15, 2016
Project
Site
Hacienda Crossings
Transit
Center
BART
garage
SAP
Persimmon Place
Boulevard
(Dublin Crossing)
Project Summary
Development of the site may include:
•377,479 square foot IKEA retail store
•Four additional pad buildings for retail, restaurant, potential hotel
No formal application on file.
Future project applications will be:
•Stage 2 Development Plan (PD Rezoning)
•Site Development Review (site and architectural approval)
•Tentative Map to divide site into multiple commercial parcels
Staff will schedule a Study Session with the Planning Commission at some
point later this year and also provide a status update to the City Council.
Further Details
•The Applicant will fund the costs of the CEQA work.
Dublin’s “cost recovery” approach to processing development
applications ensures that the Project Proponent covers both the direct
costs for contracts and staff time.
•No project approvals granted.
Authorizing a firm to prepare an environmental document in no way
obligates the City Council to take any particular action on a future
project .
•City’s Superstore Ordinance does not apply.
“Superstore” means a store that exceeds one hundred seventy
thousand (170,000) square feet of Gross Floor Area and devotes at
least ten (10) percent of the total sales floor area to the sale of non-
taxable merchandise.
Tonight’s Considerations
•State law requires that an environmental impact analysis be
completed for new projects in many circumstances. Beginning this
work is usually the first step in the process.
•City Staff does not have the expertise to complete complex technical
analyses (e.g. traffic, air quality, etc.) and relies on specific experts for
this type of work.
•Proposal were solicited for a qualified environmental firm to provide a
scope of work and budget to complete the environmental document.
•Consideration of the project itself will happen at a later date.
Recommendation
Staff recommends that the City Council receive the status report on
the project and Adopt a Resolution approving a Consulting Services
Agreement with FirstCarbon Solutions (FCS) to prepare a
Supplemental Environmental Impact Report for the Project Clover
(IKEA) Retail Center and authorizing the City Manager to sign the
Agreement on behalf of the City.