AGENDA STATEMENT
City Council Meeting Date: October 13, 1986
SUBJECT: Grant Application to CalTrans for
Fuel-Efficient Traffic Signal Management Program
EXHIBITS ATTACHED: 1) Grant Application.
2) Resolution Authorizing Fuel-Efficient Traffic
Signal Management Program Grant Application.
3) Notice of Exemption Under the California
Environmental Quality Act of 1970.
RECOMMENDATION: 1) Adopt Resolution Authorizing Fuel-Efficient
Traffic Signal Management Program Grant
Application.
2) Declare this study program as categorically exempt
under CEQA.
FINANCIAL STATEMENT: This grant application is for $12,600 to fund the
necessary traffic study. It is estimated that about
$2,200 of in-house Staff time will be required to
monitor this program.
DESCRIPTION:
CalTrans has a program to aid cities and counties in studying and
optimizing signal timing so as to minimize the motorists' use of fuel as they
pass through a local signal system.
Staff has completed this application so that its timing will
coincide with the signal interconnection project on Dublin Blvd. This program
grant, if approved by CalTrans, will pay $12,600 toward vehicle counts and
study for optimizing the new system.
Authorization for this grant application by the City Council is
necessary to complete the request and must be submitted by October 15, 1986,
for this year's funding.
----------------------------------------------------------------------------
ITEM NO. `�° '� COPIES TO: TJKM
Attachment 1
Application Summary
1 . Applicant Name and Address: Ci tv of Dublin
TJKM Transportation Consultants
- -
... 4637 Chabot Drive, Duite 214
Pleasanton, CA 94566
2. Applicant Population: 17,377
3. Applicant Per Capita Income: $8,033
(From 1980 Census)
4. Project Grant Manager: Richard Ambrose, City Manager
Phone: (415) 829-4600
5. Project Traffic Engineer: Elizabeth A. Walukas
Phone: (415) 463-0611
6. Budget Summary:
Total Project Cost: $12,600
State Share (Grant) : $12,600
Local Share: none
Consultant Budget ( If Applicable) : $12,600
7. Number of Signalized Intersections:
In Your Jurisdiction: 15 installed, 3 to be installed
In Coordinated Systems: none
In Your Proposed Project: 8 installed, 1 to be installed
A-1
8. Who currently makes the decisions on how to set your signals?
Traffic signal maintenance technician
Field operations engineer
Traffic Engineer
_Other (Describe) City Engineer/Consulting Traffic Engineer
Approximately how many local staff person—years (or fraction
thereof) are currently devoted -t-o t-raffi-c- signal -tiiaiag—"" ---
in your jurisdiction? none
(Include all categories of effort, including data acquisition,
plan development, implementation, checking--and--surveil-Tance.-'r:__..
Comments: All traffic Pnginaarinq -,Pr vicPs arP contracted to TJKM
Transportation Consultants.
9. Who currently is responsible for maintaining your signals?
County of Alameda, CALTRANS
10. Do you have plans for major capital improvements to upgrade
your proposed project network? Yes X No
If "Yes" , do you have a schedule, budget proposal or funds
already committed?
Details: 1 ) Install new signal at Sierra Court (under construction) .
2) Interconnect signals on Dublin Boulevard (will be in
place by February; 1987. - Funds are committed) . .
11 . Do you anticipate significant changes in traffic levels or
patterns in the project area as a result of new development,
road improvements, etc. ? -
Yes No X - -
Details: No substantial developments are expected to occur during
the study grant year. However, in the Dublin Boulevard
corridor, a total of 26 developments are identified for
construction over the next 20 years These developments
are estimated to generate an additional 35,650 vehicle trips
per day.
A-2
12 . List below specific local agency staff that would be assigned to
this project. Outline local staff traffic engineering
-experience, prior training in and use of the TRANSYT 7F signal
timing program, and . role in this project.
(Note: Prior experience with the TRANSYT model is not required. )
Chris D. Kinzel - 21 years of traffic engineering experience. Formerly City
`-Traffic Engineer-of Hayward.`-Holds M.S. degred from U.C. Berkeley. Principal-in-
charge on many-signal timingprojects, including--TRANSYT projects in Oakland,
Santa Monica, and Walnut Creek. -Registered Civil Engineer and Traffic Engineer
in California.
John Y. Sun - Served as the project engineer on our TRANSYT project for the
City of Pleasanton. He prepared the computer input and implemented the
TRANSYT optimized output on the traffic signal master controller in Pleasanton.
He has also manually developed and implemented signal timing on master
controllers. His earlier experience includes work at ITS where he processed 1980
MTC Travel Survey data on the UC IBM computer. He holds a M.S. degree from
U.C. Berkeley, and he has applied TRANSYT to San Pablo Avenue in the East Bay
as part of his work at UC.
Elizabeth A. Walukas -.-Ser.ved as project-engineer on. a--TRANSYT project for the
City of Menlo Park. She was employed by the Institute of Transportation Studies
at U.C. Berkeley as a research assistant where she served as a technical assistant
for Northern Californian cities using the TRANSYT 7-F model.
i
A-3 -
13 . Supply any additional information that would be useful for the
State' s review of this application. Also, you may use this
space to expand any of your .answers to the previous questions.
TJKM Transportation Consultants currently is under contract to the City of Dublin
as their City Traffic Engineer. In this capacity, TJKM handles all traffic related
work for the City. ' Enclosed is a copy of that contract.
The City of Dublin, through TJKM, is in the process of designing an interconnect
system for all signals on Dublin Boulevard between Dougherty Road and San
Ramon Boulevard. The City is planning to have the system installed by
February, 1987. It would be designed so that all City signals could eventually
connect to it. The master controller would be located on the southwest corner of
Sierra Court which is immediately adjacent to the future Civic Center site.
A-4
Attachment 2
Project Area Maps
Please submit two 8-1/2 by 11 maps as described below.
A. A map showing the location of each proposed system within your
jurisdiction.
B. A map showing the signalized intersections of each system
with the following information:
1 . Average daily traffic
2. Circulation pattern ( identify one-way streets)
3 . A scale or identification of the distance between adjacent
signals
A-5
v
A o
� c
N �
Z �
ti
4u
Lv O ::::•:" A`q � � 9R�rT
y �VBCIN Cr
1p
guN •
,f
.j
:A
TRAFFIC SIGNAL
0
OA
s
r� 8
SIGNAL LOCATION
PROJECT AREA MAP FIGURE
ATTACHMENT 2 7
v TRAN!►ORTATION CONlULTANTS
n► c
n
z �
0980 S�FRRq �,N• v
2
/000
p
\8 Ott. f //s 20,7
3 ft
\ a vu et
9pp apptt N cr,
22,000 —ADT
'O-- '—TWO WAY TRAFFIC
800 ft. — DISTANCE BETWEEN SIGNALIZED
INTERSECTIONS
AVERAGE DAILY FIGURE
TRAFFIC CIRCULATION PROJECT AREA MAP
DISTANCE TANT� 2
711AN�►OIITATION COMtUI
Attachment 3
Description of Project Signal System
System Name: Dublin Blvd. No. of Intersections: 9*
System Configuration: Grid *One Arterial entXy under construction
System Coordination: Hardwire X Time Based
System Controller: Type _Mul ti soni 911/820 (see 0-13 Attachment 1 )
Maximum # of Time-of-Day Plans: 6
Current # of Time-of-Day Plans: none
System Cycle Length or Running Free:
AM Period running free Mid-Day Period runninq free PM Period running free
Last Date Timing Plans Revised for the entire system: not applicable
Complete the items below for the system. Under "Special Features"
indicates any special phasing (split, lead-lag, etc. ) , signals owned by
other agencies, master controller, special pre-empt feature, etc.
Continue items on another sheet if necessary.
Pretimed/ No. of Special
Intersection (Street Names ) Actuated Phases Features
1. Dublin Blvd./Dougherty Rd. Actuated 4 right turn overlap
split 9 on both sides
2. Dublin Blvd./Dublin Ct. Actuated 5 emergency vehicle
pre-emption
3. Dublin Blvd./Sierra Ct.* Actuated 5 emergency vehicle
pre-emption
4. Dublin Blvd./Clark Ave.. Actuated 5 emergency vehicle
pre-emption
5. Dublin Blvd./Village Pkwy. Actuated 6 split Von cross st.
6. Dublin Blvd./Amador Plaza Rd. Actuated 5
7. Dublin Blvd./Golden Gate Dr. Actuated 5
8. Dublin Blvd./Regional St. Actuated 5
9. Dublin Blvd./San Ramon Rd. Actuated 6 state owns
170 controller
* Signal under construction split,6'
A-6
Attacnment 4
Fuel Efficient :affic Signal Management TSIM) Program
Budget Form
Applicant Financial Contact: Richard Ambhose Phone:(415) 829-4600
State Share Local Share
DIRECT COSTS
Personnel Services
Salaries and Wages (List by
position, salary rate, arid 'hours )
City Manager $ 300.00
Assistant City Manager 1 ,100.00
City Engineer 800.00
Benefits (at %) (included)
Total Personnel Services $2,200.00
Operating Expenses
Travel
Other:
Other:
Total Operating Expenses
Miscellaneous Items (List)
Total Miscellaneous Items
INDIRECT COSTS (At %)
SUBCONTRACTS
Consultant Services $12,600
Data Collection Contract -
State Share' (Grant ) $12,600
Local Share $2,200.00
TOTAL PROJECT COST $14,800.00
A-7
Attachment 5
Project Task Responsibi .:y
(Please check appropriate agency or if joint responsibility, enter
percentage for each. )
Responsible Agency Task
Local Staff Consultant
0% 100% o Field check equipment
50% 50% o Attend Orientation Workshop
0s0 100% o Develop network diagram showing
node numbers, link numbers and
link _lengths
0% 100% o Collect field data (Includes
data for timing, speeds,
volumes, saturation flows, lost
time, green extension, midblock
flow profiles, and queue
lengths
0% 100% o Transfer raw data to data
reduction sheets
0% 100% o Code data in computer and
complete initial simulation run
50% 50% o Attend Calibration Workshop
0% 100% o Calibrate model
50% 50% o Attend Implementation Workshop
20% _80% o Complete TRANSYT optimization
runs and selection of plans
0% 100 010 o Complete "before" field
evaluation
80% 20% o Implement timing plans
50% 50% o Fine tune timing plans
0% 100% o Complete "after" field
evaluation
0% 100% o CompletA TRANSYT simulation of
Plans implemented n" " field
10% 90% o Complete final report per
__... ..�.__,__,... Caltrans guidelines
50% 50% o Attend User Workshop, make
presentation of project
NOTE: TJKH Transportation Consultants results, and . turn in final
serve as designated City Traffic report
Engineer.
A-8
Attachment 6
FETSIM PRWE)CT SCHEDULE
TASKS Feb 87 Mar 87 A r 67 May 87 Jun 87 jJul 87 Aug 7 Oct Nov Dec g7 Jan gg
Orientation Workshop
Link/Node Diagram
Data Collection
Data Coding
Model Application
Calibration Workshop
Model Calibration
Implementation Workshop
FTransyt Optimization
.......:....
Before Field Evaluation
Field Implementation/
Fine Tuning
After Field Evaluation/
Analysis of Results ::•`'`+t':`•`?<:':
t
User Workshop/
? Final Report
I. Link/Node Diagram due March 31, 1987
2. Data Reduction Sheets due May 1.5, 1987
3. Calibrated Siinulation Runs/Field Calibration Data due August 15, 1987
4• SimulEtion Ruhs of Fine Tined Field Plans due December 1, 1987
6• Final Report due at the User Workshop in January 1988
A-9
RESOLUTION NO. -86
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
AUTHORIZING A FUEL-EFFICIENT TRAFFIC SIGNAL
MANAGEMENT PROGRAM GRANT APPLICATION
WHEREAS, the City of Dublin recognizes that it is in the interest
of the national economy to promote the conservation of energy resources and to
reduce our nation's dependence on costly foreign oil; and
WHEREAS, fuel efficient traffic signal management by the City of
Dublin will provide benefits to the local community in the form of improved
traffic flow, reduced fuel consumption, reduced vehicle operating costs,
reduced air pollutant emissions, and improved safety due to smoother flow; and
WHEREAS, funds have been established and are available through
the California Department of Transportation for grants to local governments
for efficient traffic signal management projects;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City
of Dublin authorizes the submittal of an application to the California
Department of Transportation for a Fuel-Efficient Traffic Signal Management
grant and the Mayor of the City of Dublin is hereby authorized and empowered
to execute in the name of the City of Dublin all necessary applications,
contracts, and agreements to implement and carry out the purposes specified in
this resolution.
PASSED, APPROVED, AND ADOPTED this 13th day of October, 1986.
AYES:
NOES:
ABSENT:
Mayor
ATTEST:
City Clerk
G~��of DU�C�y
111 �� X11
19 -�� 82 CITY OF DUBLIN
P.O.-Box 2340 DUBLIN, CALIFORNIA 94568
CITY OFFICES
6500 DUBLIN BLVD.
NOTICE OF EXEMPTION
ADMINISTRATION
829-4600 T0: County Clerk - County of Alameda FROM: City of Dublin
1225 Fallon Street Planning Dept.
BUILDING INSPECTION Oakland,-' California 94612 6500 Dublin Blvd.
829-0822 Suite D
Dublin, CA 94568
CITY COUNCIL
829-4600 PROECT TITLE: Fuel-Efficient Traffic Signal Management Program
Study
CODE ENFORCEMENT PROJECT LOCATION: Dublin Boulevard
829-0822 Dublin, Alameda County, CA 94568
ENGINEERING PROJECT DESCRIPTION; Grant application for the study of signal timing
829-4927 to minimize motorists' use of fuel as they pass throughthe City's
street signal system.
FINANCE The City of Dublin, on September 29, 1986, found that the above
829-6226 approved project has the following exempt status:
PLANNING Categorical Exemption, Class 1 (c), Section 15301 and Class 6,
829-4916 Section 15306.
Reasons why project is exempt: The project consists of basic data
POLICE collection and research and may involve alteration to existing public
829-0566 street signal timing. It will not result in serious or major
disturbance to environmental or scenic resources.
PUBLIC WORKS
829-4927
TELEPHONE: (415) '829-4916
RECREATION
829-4932
SIGNATURE:
Laurence L. Tong, Planning rector
DATE OF SIGNATURE: September 29, 1986