STAFF REPORT
CITY COUNCIL
DATE: December 6, 2016
TO: Honorable Mayor and City Councilmembers
FROM:
Christopher L. Foss, City Manager
SUBJECT:
City Council Chamber Renovations
Prepared by: Hazel L. Wetherford, Assistant to the City Manager
EXECUTIVE SUMMARY:
The City Council will consider approving a budget change to the Civic Center
Modification Design & Construction Project (CIP No. GI4099) based on updated
construction cost estimates for the City Council chamber renovations, approve a related
amendment to the Swatt I Miers contract for design work, and authorize the City
Manager to purchase furniture.
STAFF RECOMMENDATION:
1) Approve a budget change for the Civic Center Modification Design & Construction
Project (CIP No. GI4099); 2) Adopt the Resolution Approving an Amendment to the
Consulting Services Agreement with Swatt I Miers Architects for Design Services for the
Civic Center Modification Design & Construction Project; and 3) Adopt a Resolution
Authorizing the City Manager to Purchase Furniture for the Civic Center Modification
Design & Construction Project.
FINANCIAL IMPACT:
Cost estimates for the project have been refined and exceed the current project budget.
For the design work, the existing Agreement with Swatt I Miers Architects is for a not-to-
exceed amount of $69,940. This Amendment and related budget change will increase
the Agreement by $16,000 for a not -to-exceed amount of $85,940. The construction
costs are estimated to be $122,000 more than what was budgeted in 2014, for a total
construction budget of approximately $377,000. In addition, Staff is recommending
other improvements to the Chamber in the amount of $150,000. A budget change will
be required and sufficient funds are available in the Cable TV Facilities Fund to cover
the adjustments to the project budget.
DESCRIPTION:
Page 2 of 2
On November 4, 2014, the City Council appropriated $325,000 in funding to the Civic
Center Modification Design & Construction Project (CIP No. GI4099) for the City Council
Chamber renovation work. Following that appropriation, the City conducted an RFP
process and selected Swatt I Miers Architects for the design services on October 6,
2015. Swatt’s design services were for a not-to-exceed amount of $69,940. The
Agreement with Swatt was subsequently extended by the City Council on September
20, 2016 through the end of this fiscal year.
Swatt has refined the scope of work for the project and has included upgrades to the
audio/visual and lighting, changes to the dais, replacement of the public podium and
modifications to the staff podium. Additionally, the scope includes changes to the wall
and ceiling finishes for acoustical and aesthetic needs.
In light of the other improvements being made, Staff determined that it would be an
appropriate time to also make other updates to the City Council Chamber to improve its
visual appeal for televised City Council meetings. Staff is recommending an increase to
the project budget to purchase new auditorium seating, replace the carpeting and
related carpentry work. The purchases would be made in compliance with the City
Municipal Code, including the requirements for competitive bidding. Staff is
recommending that the City Council give the City Manager the authority, up to
$100,000, to make the auditorium seating purchase via a cooperative purchasing
agreement (such as that offered through the National Joint Powers Alliance).
In summary, Staff is seeking to amend the project budget by $288,000 to cover the
construction estimate ($122,000), new proposed improvements to the Chamber by Staff
($150,000), as well as additional design work ($16,000) by Swatt for the refined scope
and proposed new improvements.
Should the City Council approve the requested amendments and authorization to the
City Manager, it is expected that new proposed improvements would be complete prior
to the summer break. The upgrades to the audio/visual and lighting, changes to the
dais, replacement of the public podium and modifications to the staff podium, as well as
wall and ceiling finishes would occur most likely during the summer break period.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
ATTACHMENTS:
1. Resolution Approving an Amendment to the Consulting Services Agreement with
Swatt I Miers Architects
2. Exhibit A to the Resolution - Second Amendment to the Consulting Services
Agreement with Swatt I Miers Architects
3. Resolution Authorizing the City Manager to Purchase Furniture for the Civic Center
Modification Design & Construction Project
4. Budget Change Form
RESOLUTION NO. XX-16
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
*********
APPROVING AN AMENDMENT TO THE CONSULTING SERVICES AGREEMENT
WITH SWATT I MIERS ARCHITECTS
FOR DESIGN SERVICES FOR THE CIVIC CENTER MODIFICATION DESIGN &
CONSTRUCTION PROJECT
WHEREAS, on October 6, 2015, the City entered into a Consulting Services Agreement
with Swatt I Miers Architects to provide design services for the Civic Center Modification Design
& Construction Project (GI4099); and
WHEREAS, on September 20, 2016, the City Council approved a First Amendment with
Swatt I Miers Architects to extend the term of the Agreement to June 30, 2017; and
WHEREAS, the existing Agreement with Swatt I Miers Architects is $69,940, and Staff is
seeking City Council approval to increase the existing Agreement by $16,000 to cover
reconfiguration of the project and additional design work for a total not to exceed amount of
$85,940.
NOW THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby approve the Second Amendment to the Consulting Services Agreement between the
City of Dublin and Swatt I Miers Architects for design services for the Civic Center Modification
Design & Construction Project (GI4099); and
BE IT FURTHER RESOLVED that the City Manager is authorized to execute the
Amendment, attached hereto as Exhibit A to this Resolution, in substantially the form attached
with such changes as are deemed appropriate by the City Manager.
PASSED, APPROVED AND ADOPTED this 6th day of December, 2016, by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
_______________________________
Mayor
ATTEST:
______________________________
City Clerk
SECOND AMENDMENT TO
CONSULTING SERVICES AGREEMENT
BETWEEN THE CITY OF DUBLIN AND
SWATTǀMIERS ARCHITECTS
WHEREAS, on October 6, 2015, the City of Dublin (“CITY”) and SwattIMiers Architects
(“Consultant”) entered into a Consultant Services Agreement (“Agreement”); and
WHEREAS, on September 20, 2016, the City entered into a First Amendment to extend
the Term of Services until June 30, 2017; and
WHEREAS, the City and Consultant mutually desire to increase Compensation to a sum
not to exceed Eight-five Thousand Nine Hundred Forty dollars ($85,940), which is an increase
of Sixteen Thousand dollars ($16,000) from the initial Agreement dated October 6, 2015.
NOW, THEREFORE, for good and valuable consideration, the sufficiency of which is
hereby acknowledged, the Agreement is amended as follows:
1) Section 2. Compensation shall be rescinded in its entirety and replaced with the
following:
2. COMPENSATION. City hereby agrees to pay Consultant a sum not to exceed
Eight-five Thousand Nine Hundred Forty dollars ($85,940), notwithstanding any
contrary indications that may be contained in Consultant’s proposal, for services
to be performed and reimbursable costs incurred under this Agreement. In the
event of a conflict between this Agreement and Consultant’s proposal, attached
as Exhibit A, regarding the amount of compensation, the Agreement shall prevail.
City shall pay Consultant for services rendered pursuant to this Agreement at the
time and in the manner set forth herein. The payments specified below shall be
the only payments from City to Consultant for services rendered pursuant to this
Agreement. Consultant shall submit all invoices to City in the manner specified
herein. Except as specifically authorized by City, Consultant shall not bill City for
duplicate services performed by more than one person.
Consultant and City acknowledge and agree that compensation paid by City to
Consultant under this Agreement is based upon Consultant’s estimated costs of
providing the services required hereunder, including salaries and benefits of
employees and subcontractors of Consultant. Consequently, the parties further
agree that compensation hereunder is intended to include the costs of
contributions to any pensions and/or annuities to which Consultant and its
employees, agents, and subcontractors may be eligible. City therefore has no
responsibility for such contributions beyond compensation required under this
Agreement.
2) Except to the extent inconsistent with this Second Amendment, City and Consultant
ratify and confirm all of the terms and conditions of the Agreement and its First Amendment.
3) All requisite insurance policies to be maintained by the Consultant pursuant to the
Agreement, as may have been amended from time to time, shall include coverage for the
amended term, as described above.
RESOLUTION NO. XX-16
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
*********
AUTHORIZING THE CITY MANAGER TO PURCHASE FURNITURE FOR THE CIVIC
CENTER MODIFICATION DESIGN & CONSTRUCTION PROJECT
WHEREAS, the Civic Center Modification Design & Construction Project (GI4099)
includes the purchase of new furniture; and
WHEREAS, the City seeks to procure furniture outside of construction contracts where it
makes financial and operational sense to do so; and
WHEREAS, the City Manager’s purchasing authority for general services, supplies, and
equipment is limited to less than $45,000; and
WHEREAS, the purchase of auditorium seating for the Project will exceed the City
Manager’s purchasing authority.
NOW THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin does
hereby authorize the City Manager to purchase furniture for the Civic Center Modification
Design & Construction Project (GI4099) up to $100,000.
PASSED, APPROVED AND ADOPTED this 6th day of December, 2016, by the
following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
_______________________________
Mayor
ATTEST:
______________________________
City Clerk
Budget Change Reference #:
From Un-Appropriated Reserves X Budget Transfer Between Funds
From Designated Reserves Other
Account Amount Account Amount
GI4099.9200.9201 - Contract Services General $16,000
GI4099.9400.9401 - Improvements - Not Bldg $272,000
3300.9301.49999 (Transfers In)$288,000
GI4099.2811 (2811.9301.89101) - Transfers
Out $288,000
12/6/2016
Posted By:Date:
As Presented at the City Council Meeting
**********Finance Use Only**********
CITY OF DUBLIN
Increase in Swatt I Miers Architects consulting services cost due to change in scope of services and additional renovation work
to the Council Chamber
REASON FOR BUDGET CHANGE
FISCAL YEAR 2016-17
BUDGET CHANGE FORM
DECREASE BUDGET AMOUNT INCREASE BUDGET AMOUNT
EXP: Cable TV Facilities Fund - General Improve. - Civic Center
ModificationFund - Program - Account Description
City Council's Approval Required
G:\Budget Changes\9_2016-17\CC Approval\08_gi4099 CC Chamber Mod_120616 08_gi4099 CC Chamber Mod_120616