HomeMy WebLinkAbout8.1 - 1281 Authorization to Bid Dublin Boulevard Rule
Page 1 of 3
STAFF REPORT
CITY COUNCIL
DATE: January 10, 2017
TO: Honorable Mayor and City Councilmembers
FROM:
Christopher L. Foss, City Manager
SUBJECT:
Dublin Boulevard Improvements - Sierra Court to Dublin Court: Project
Update, Approval of Plans and Specifications and Authorization to Bid a
Project Phase
Prepared by: Michael Boitnott, Senior Civil Engineer
EXECUTIVE SUMMARY:
The City Council will receive an update on the Dublin Boulevard Improvements Project
(CIP No. ST1012). Additionally, Staff is requesting City Council approve the plans and
specifications, as well as authorize the bidding of the first phase of the project. The
undergrounding of utilities is the first phase of construction and provides for the
undergrounding of electric, cable TV, and communication lines, and the removal of
overhead poles, along Dublin Boulevard from Sierra Court to Dublin Court.
STAFF RECOMMENDATION:
Receive the Project update and adopt the Resolution Approving the Plans and
Specifications and Authorizing Bidding for the Undergrounding of Utilities in the City Of
Dublin Underground Utility District 2013-1 as Part of the Dublin Boulevard
Improvements – Sierra Court to Dublin Court Project (CIP No. St1012).
FINANCIAL IMPACT:
The Capital Improvement Program (CIP) budget for the Dublin Boulevard Improvements
Project is $6.9 million, and includes $1 million in PG&E Rule 20A funds for the
undergrounding of utilities. The construction estimate for the undergrounding work is
approximately $1.3 million. It is anticipated, based on the construction estimate, that
additional funds may be needed for the undergrounding work. Upon receipt and
evaluation of bids, if the lowest bid exceeds the existing budget, Staff will develop
funding options, such as other existing street improvement funds, or other non-General
Fund sources, to bring to City Council with the consideration of the construction
contract.
Page 2 of 3
DESCRIPTION:
Project Update
The Dublin Boulevard Improvements Project (CIP No. ST1012) provides for the
widening of Dublin Boulevard from Sierra Court to Dublin Court and for the
undergrounding of existing overhead utilities within the project limits. Completion of this
project will widen Dublin Boulevard from four to six lanes and install bike lanes, modify
two traffic signals, install pedestrian-scaled lights, and enhance the existing
landscaping. In addition to addressing traffic congestion and improving multi -modal
circulation on Dublin Boulevard, including improved access to the Dublin BART stations,
these improvements are necessary to conform to the General Plan.
The segment of Dublin Boulevard from Sierra Court to Dublin Court is a critical
east/west arterial that carries, on average, over 32,000 vehicle trips a day, with most
trips occurring during the daytime. The utility undergrounding, related Dublin San
Ramon Services District (DSRSD) sewer work, and road widening phases will require
temporary lane closures during construction. In an effort to minimize traffic congestion,
impacts to business, and impacts to the overall community, Staff is proposing to
construct the improvements at night between the hours of 8:00 pm and 6:00 am,
Sunday through Friday, with weekend work by special request requiring Staff approval.
Utility Undergrounding
On July 16, 2013, the City Council held a Public Hearing establishing Underground
Utility District 2013-1 on Dublin Boulevard - Civic Plaza/Sierra Court to Dublin Court, to
underground existing overhead utilities along Dublin Boulevard, in conjunction with the
widening of Dublin Boulevard from two lanes to three lanes in the westbound direction,
and the addition of a bike lanes in both directions. The undergrounding portion of the
project will be funded with California Public Utilities Commission Rule 20A funds.
The undergrounding work, which applies to Pacific Gas & Electric (PG&E), Comcast,
AT&T and Sprint utilities, is the first phase of the widening of Dublin Boulevard. The
project plans and specifications have been completed, and will include eliminating
overhead utility lines on wooden poles on both sides of Dublin Boulevard between
Sierra Court and Dublin Court, installing the utilities underground, and reconnecting
overhead services to utility customers with new underground service connections. As
part of this project, the surface improvements will be temporarily restored until the
ultimate improvements are installed during the second phase widening project.
This first phase of the project will be primarily funded with Rule 20A funds. Rule 20A is
an electrical tariff program lead by the California Public Utilities Commission which
requires a portion of new services to contribute towards the undergrounding of existing
overhead utility lines. In our area, PG&E holds agencies’ Rule 20A allotments and local
agencies can also borrow up to five years of future credits to be used to construct a
Rule 20A project. This Project budget includes $1 million of Rule 20A funds out of a
total allotment of $1.14 million (including the future five-year credits). Staff will update
the Project budget to include the full allotment once the bid results are presented to the
City Council at a future meeting.
In addition, the program allows for agencies to borrow or purchase credits with other
agencies for use on utility undergrounding projects. The purchase of credits is
Page 3 of 3
dependent upon the market, but usually available credits can be purchased at less than
face value. The current Engineer’s Estimate for the project is $1.3 million. The City
may consider the acquisition of credits should the actual construction work exceed the
current credit amount and would look to fund the credit purchase with funding sources
other than the General Fund. Once the construction bids are opened and evaluated,
Staff would bring back any options needed to bridge any remaining funding gaps for the
first phase of the project.
In addition to the utility undergrounding work, DSRSD will relocate a sanitary sewer lift
station that is located within the current roadway pavement. The DSRSD lift station will
be relocated behind the future sidewalk to clear the way for the road widening portion of
the project. The lift station work will be funded, constructed, and managed by DSRSD
and will be implemented concurrently with the undergrounding work to minimize impacts
to the community.
This work is exempt under Section 15302 (Replacement or Reconstruction) of the
California Environmental Quality Act (CEQA) Guidelines.
NOTICING REQUIREMENTS/PUBLIC OUTREACH:
Staff has started the process of reaching out to business and residential groups in the
vicinity of the project to inform them of the future improvements and night construction.
ATTACHMENTS:
1. Resolution Approving the Plans and Specifications and Authorizing Bidding for the
Undergrounding of Utilities in the City of Dublin Underground Utility District 2013-1
2. Draft Dublin Boulevard Preliminary Construction Schedule and Phasing Exhibit
RESOLUTION NO. - 17
A RESOLUTION OF THE CITY COUNCIL
OF THE CITY OF DUBLIN
* * * * * * * * *
APPROVING THE PLANS AND SPECIFICATIONS AND AUTHORIZING BIDDING FOR THE
UNDERGROUNDING OF UTILITIES IN THE CITY OF DUBLIN UNDERGROUND UTILITY
DISTRICT 2013-1 AS PART OF THE DUBLIN BOULEVARD IMPROVEMENTS – SIERRA
COURT TO DUBLIN COURT PROJECT (CIP NO. ST1012)
WHEREAS, the City of Dublin Capital Improvement Program includes the Dublin
Boulevard Improvements – Sierra Court to Dublin Court Project (CIP No. ST1012); and
WHEREAS, CIP No. ST1012 includes the undergrounding and relocation of overhead
utilities, funded by Rule 20A monies; and
WHEREAS, on July 16, 2013, the City Council held a Public Hearing establishing the City
of Dublin Underground Utility District 2013-1 (District 2013-1) on Dublin Boulevard – Sierra
Court to Dublin Court to underground existing overhead utilities; and
WHEREAS, this work is exempt under Section 15302 (Replacement or Reconstruction)
of the California Environmental Quality Act (CEQA) Guidelines ; and
WHEREAS, the design team has completed the plans and specifications and the utility
companies have approved the project plans for the undergrounding of existing overhead utilities
in District 2013-1 and the work is ready for public bidding; and
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Dublin
hereby approves the plans and specifications for the undergrounding of existing overhead
utilities in District 2013-1, as part of the Dublin Boulevard Improvements – Sierra Court to Dublin
Boulevard Project (CIP No. ST1012) and authorizes public bidding;
BE IT FURTHER RESOLVED that the City Council of the City of Dublin hereby
authorizes the project to be constructed at night between the hours of 8:00 pm and 6:00 am
Sunday through Friday and work on the weekends would be at a special request and require
staff approval, in an effort to minimize impacts to the community.
PASSED, APPROVED AND ADOPTED this 10th day of January, 2017, by the following
vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
________________________________________
Mayor
ATTEST:
__________________________________
City Clerk
Phase 1A DSRSD Lift Station Relocation Phase 1B Utility Undergrounding Phase 2 Street Improvements
DSRSD
Lift Station Relocation
Utility
Undergrounding
Street
Improvements
April 2017 through August 2017
Maintain 1 lane in both directions at all times
Hours Sun-Fri 9 PM to 6 AM
Late March 2017 through September 2017
Maintain 1 lane in both directions at all times
Hours Sun-Fri 8 PM to 6 AM
September 2017 through December 2018
Maintain 1 lane in both directions at all times
Hours Sun-Fri 8 PM to 6 AM
DRAFT DUBLIN BOULEVARD PRELIMINARY CONSTRUCTION SCHEDULE & PHASING
December 2016 City of Dublin Public Works Department www.dublin.ca.gov (925) 833-6630